HomeMy WebLinkAboutTRANSMITTAL OF RESPONSE AND RECLAMATION PLAN AND SUPPORTING DOCUMENTS (MIN 96-03)Butte County Department of Development Services
TIM SNELLINGS, DIRECTOR I PETE CALARCO, ASSISTANT DIRECTOR
7 County Center Drive
Oroville,.CA 95965
(530) 538-7601.Telephone
(530)538-7785 Facsimile
ADMINISTRATION " BUILDING * PLANNING
October 2, 2006
Mr. James S. Pompy
801 K Street, MS 09-06
Sacramento, CA 95814
RE: Transmittal of Response and Reclamation Plan and Supporting Documents
M&T Chico Ranch Mine Reclamation Plan
(MIN 96-03)
Dear Mr. Pompy:
Enclosed please find a Revised Reclamation Plan and materials provided by the
applicant, Baldwin Contracting Company.* This material includes a letter dated September
20, 2004, along with a bound document entitled "Reclamation" Plan and Supporting
Documents" that together responds to the Office of Mine Reclamation letter of June 10,
2004 (included in the attached). Where revisions were not necessary to the Reclamation
Plan comments within the Baldwin letter provide explanations orreferences to supporting
materials .that address the comment.
The Butte County Department of Development Services' finds that the amended
Reclamation Plan, including the responses provided by the applicant (Baldwin
Contracting Company, Inc.), address the comments provided in your letter of June 10,
2004. This Reclamation Plan is in compliance with the applicable requirements of
Article I (commencing with Section 3500) of Chapter 8 of Division 2 of Title 14 of the
California Code of Regulations.
Si rel
Dan Breedon
Principal Planner
Enclosure
cc: Chuck Thistlethwaite, Planning Manager
Pete Calarco, Assistant Director of Development Services
BALDWIN CONTRACTING COMPANY, INC.
GENERAL ENGINEERING CONTRACTORS
1764 SKYWAY / CHICO, CA 95928 (530) 891-6555 (530) 894-6220 FAx
Mr. Dan Breedon
Principal Planner
Butte County
Department of Development Services
n E CEO U E
V
SEP 2 3 2004
BUTTE COUNTY
PLANNING DIVISION
25 County Center Drive
Oroville, CA 95965
RE: Department of Conservation comment letter dated June 10, 2004.
Dear Dan,
This letter sets forth Baldwin Contracting Company's ("BCC") responses to the
Department Lof Conservation's ("DOC") comment letter, dated June 10, 2004. The
DOC's letter commented on BCC's reclamation plan for its M & T Ranch mining
operation.
The Surface Mining and Reclamation Act ("SMARA") requires that prior to
approving a surface mining operation, a lead agency submit the reclamation plan and
supporting documents to the Director of DOC (delegated to the office -of Mine
Reclamation ["OMR"]) for comments. (Cal. Pub. Resources Code § 2774(c).) OMR has
30 days to issue its comments. (Cal. Pub. Resources Code § 2774(d)(1).) The lead
agency then must prepare written responses to the issues raised by OMR. The lead
agency is not required to resubmit the reclamation plan to OMR for additional comments.
(See Cal. Pub. Resources Code § 2774 (c) -(d).).
This letter's headings are organized to correlate with the items raised in DOC's
June 10, 2004, letter. We have attached a bound version of the reclamation plan with
supporting documents, for your convenience.
OMR raised the following issues:
Paragraph 3• Page 1
OMR states on page one that the utilized reclamation plan format "is not
appropriate for a site of this size and complexity."
BCC used the reclamation plan format selected by Butte County ("County"). The
reclamation plan contains all the necessary requirements set forth is SMARA. The
reclamation plan's size and complexity is a reflection of the documents thoroughness
and the diligent collaboration between the County and BCC. Enclosed with this letter is a
bound copy of the reclamation plan, along with its supporting documents. BCC bate -
stamped the pages to make the reclamation planand its supporting documents easier to
navigate.
Item 1, page 2
OMR states in item one on page 2 that the reclamation plan needs to include "a
termination date for the operation" and a discussion of the time frame for reclamation.
SMARA section 2772(c)(3) requires reclamation plans to include "proposed
dates for. the initiation and termination of surface mining operations." (Emphasis added.)
BCC has both a proposed initiation and termination date in its reclamation plan.
The "proposed initiation date is the date all permits necessary to initiate operations are
approved by the regulatory agencies." The "proposed termination of surface mining
operations is 30 years after the proposed initiation date." (Reclamation Plan and
Supporting Documents, Attachment 2, bate -stamped page 22, paragraph two.)
Item 2, page 2
OMR states in item two on page two the following-.
The effects of siltation and the reduction in substrate transmissivity values
by deposition of suspended sediment carried in Little Chico Creek during
periods of flooding has not been evaluated in terms of the proposed end
use of the site as a ground water recharge "lake." The effectiveness of
groundwater recharge would be expected to diminish as the ponds silts in.
California Code of Regulations, title 14, section 3502(b)(2), cited by OMR, states
"[o]perations shall be conducted to substantially prevent siltation of ground -water
recharge areas." (Cal. Code Regs., tit. 14, § 3502(b)(2) [emphasis added].) California
Code of Regulations, title 14, section 3706(b), also cited by OMR, provides that the
"quality of water, recharge potential, and storage capacity of ground water aquifers which
are the source of water for domestic, agricultural, or other uses dependent on the water,
shall not be diminished, except as allowed in the approved reclamation plan."
Siltation will not be an issue at the M & T site. The lake, as designed, will
substantially prevent siltation of ground water recharge, and will preserve the quality,
recharge potential, and storage capacity of the lake. This is explained in greater detail in
the letter written to the County by Steve Deverel of Hydro Focus, Inc. (Reclamation Plan
and Supporting Documents, Attachment 18.)
-2-
Item 3, page 2
OMR states in.item three on page two that "there is no detailed engineered design
for the bypass channel or weir structure proposed to mitigate most of the floodplain
impacts that would result from the placement of a deep mining pit with 100 feet of Little
Chico Creek."
California Code of Regulations, title 14, section 3506(e), cited by OMR, states
"Where natural drainages are.... impacted by surface mining activities, mitigating
alternatives shall be proposed and specifically approved in the reclamation plan to assure
that runoff shall not cause increased erosion or sedimentation."
BCC's reclamation plan specifically incorporates mitigating alternatives for
natural drainages utilized in the M & T environmental impact report ("EIR"). The
reclamation plan incorporates the weir and bypass channel mitigations as set forth in
Mitigation Measure 4.4-3b and 4.4-7c. (Reclamation Plan and Supporting Documents,
Attachment 14.) The weir and bypass channel, as stated in the reclamation plan, will
"protect the water in the lake from flood water entry up to the 1.0 year event." The weir
and bypass channel will be made conditions of approval for the project.
BCC undertook substantial steps in the planning process to ensure that the weir
,and bypass channel would be viable and effective. Design information for both the weir
and the bypass channel are contained in Attachment 16 and Attachment 17 to the
Reclamation Plan. (Reclamation Plan and Supporting Documents, Attachments 16 and
1.7.) In addition NorthStar Engineering has designed a weir on Butte Creek to take
overflow, high water, upstream'of the "Oakie" Dam_ , off Honey Run Road, in Butte
County.
Item 4, page 2
OMR states in item four on page two that there is no design basis for the increase
in buffer width from 50 feet to 100 feet adjacent to Little Chico Creek. And in addition,
that "this buffer [100 foot] has not been incorporated in the cross sections or diagrams
supplied for the reclamation plan."
The buffer for the project was increased from 50 feet to 100 feet as an added
mitigation measure during the EIR process.
OMR is correct in noting that the previous version of Exhibit 2 did not
incorporate the 100 -foot buffer. This was a typographical error. BCC revised Exhibit 2 to
the reclamation plan to reflect this change. (Reclamation Plan and Supporting
Documents, Attachment 6.)
Item 5, page 3
-3-
OMR states in item five on ,page three that the mitigation for erosion of the
proposed bypass channel is, in part, repair by onsite heavy equipment. OMR states that
this mitigation would not be effective after mine closure and removal of the onsite
equipment. OMR opines that the "bypass must be designed as a long term solution and
have a maintenance agreement in place to perform repairs after site closure."
BCC designed the bypass channel as a long-term solution to replace water
overflow into the Little Chico Creek distributary. The bypass channel does not require a
maintenance agreement after site closure. The bypass channel will be designed to blend
into the natural topography of the surrounding area and Little Chico Creek. The
reclamation. plan, through the incorporation of EIR mitigation measures, requires that
native plant species be utilized in the bypass channel design to control erosion and to
provide long-term bank stability, thus making the bypass channel a suitable alternative to
the present downstream distributary on a long-term basis.
Item 6, page 3
OMR states in item six on page three that "[s]eparation of Little Chico Creek and
the lake formed following mining only limits commingling of the two water bodies to a
10 -year flood event...." OMR is concerned that commingling might create the
"Potential for movement of warm water prey species out of the lake and down the creek
to :the Sacramento River with possible impacts to anadromous fisheries."
Little Chico Creek is a warm water creek that could support warm water prey
species. The lake is an isolated lake on private property. Warm water prey species will
not be stocked in the lake. The only potential for warm water prey species to enter the
lake is if Little Chico Creek commingles with the lake via a storm event greater than a
10 -year storm event and warm water prey species enter the lake from Little Chico Creek.
In that case, however, any species that enter Sacramento River would have come from
Little Chico Creek, not the lake. .
Further, in its comment letter on the project, the Department of Fish and Game
("DFG") expressed no concern over warm water prey species in the lake.
Item 7, page 3
OMR states in item seven on page three the following:
The reclamation plan indicates that revegetation will be attained by natural
revegetation except those areas where revegetation is 'insufficient.' .. .
Reliance on natural revegetation is not an option under the statewide
reclamation standards regulations. Proactive measures to achieve the
stated end use must be described in the plan, including a complete
description of the number of plants, cuttings and or seed of each species
that will be used in the revegetation plan.
-4-
The performance standards for revegetation are set forth in California Code of
Regulations, section 3705. The standards do not ;prevent utilization of natural
revegetation. Rather, section 3705 measures success of revegetation "based upon the
effectiveness of the vegetation for the approved end use, and by comparing the quantified
measures of vegetative cover, density, and species -richness of the reclaimed mined -lands
to similar parameters of naturally occurring vegetation in the area." (Cal. Code Regs., tit.
14, § 3705(m).)
While sensitive to OMR's concerns, BCC has taken great care to ensure that the
current reclamation plan provides for a detailed, exhaustive, and legally supportable
revegetation plan. The reclamation plan revegetation standards track the statutory
requirements mandated by SMARA and its associated regulations. For example,
California Code of Regulations, section 3705(m) states the following:
Success of revegetation shall be judged based upon the effectiveness of
the vegetation for the approved end use, and by comparing the quantified
measures of vegetative cover, density, and species -richness of the
reclaimed mined -lands to similar parameters of naturally occurring
vegetation in the area.
(Cal. Code Regs., tit. 14, § 3705(m).)
The M & T Ranch reclamation plan tracks these requirements. The reclamation
plan states "Performance standards ... will be evaluated based on the effectiveness of the
vegetation for wildlife habitat by comparing appropriate measures of cover, density and
species richness of the reclaimed lands to similar parameters on reference areas."
In addition, the reclamation plan requires that "[m]ethods for monitoring and assessment
will be based on guidelines provided in the Department of Conservation's recently
published manual on the rehabilitation process for disturbed lands (Newton and Claassen,
2003)."
Item 8, pace 4
OMR states in item eight on page four that the present exhibits do not describe the
three plant community locations. OMR also asserts that the reclamation text indicates the
nesting island will be in the deepest portion of the lake, but Exhibit 2 shows the nesting
island as adjacent to the east shoreline.
Following OMR's suggestion, BCC prepared an additional map, Exhibit 3, that
shows, among other things, the precise locations of the three plant communities.
(Reclamation_Plan and Supporting Documents, Aftachment 7.)
The reclamation plan text explains that the nesting island is feasible. Specifically
it provides that, even if it were to be to constructed in the middle of the lake, there
would be sufficient backfill to create the island. The reclamation plan states as follows:
-5-
The nesting island will be constructed using excess overburden and silts
and clays removed from the aggregate in the processing plant. An
estimated 2.5 million cubic yards of... overburden materials and 500,000
cubic yards of fines will be available to construct the nesting island.... A
1 -acre nesting island constructed entirely of fill in the deepest part of the
lake would require only about 500,000 cubic yards of material so
sufficient excess overburden and fines are available for the reclamation
plan.
This analysis is.not intended to establish the location of the island. The actual
location of the island will be along the eastern shoreline as depicted in Exhibit 2.
(Reclamation Plan and Supporting Documents, Attachment 6 and Attachment 7.
Item 9, page 4
OMR states in item nine on page four that "the plan needs to contain more
detailed information concerning the water fluctuation levels and how this would impact
the 'margin habitat."' In addition, OMR states that the "plan does not describe any
irregular feature to the shoreline such as peninsulas or bays.... A final map illustrating the
modified shoreline needs to be included in the plan and a visual presentation of the 50-
foot.wide margin habitat illustrated."
BCC is monitoring wells to gather information on future water fluctuations within
the lake. As the excavation of the lake progresses, additional and more detailed
information on water level fluctuations will be acquired. The revegetation specialist wilt
take the water fluctuation data and use it to establish the exact location and scope of the
margin habitat. Currently, data has been collected from 2003-2004. This data is included
as Attachment 19. (Reclamation Plan and Supporting Documents, Attachment 19.)
As mentioned above, BCC created a new map, Exhibit 3, to respond to OMR's
comments.. This map includes a depiction of an irregular shoreline, designed to mirror
those found in natural environments. (Reclamation Plan and Supporting. Documents,
Attachment 7.)
Item 10, page 4
OMR states in item 10 on page four that "[c]onstruction of wildlife habitat
requires specific revegetation performance standards for each of the three habitats
proposed."
The reclamation plan contains revegetation performance standards for each of the
three habitats proposed, including the emergent zone, the shoreline zone, and the
marginal zone. As explained prior,. the reclamation plan states:
IN
Performance standards for the shallow wetlands [emergent zone species]
and lake perimeter [marginal and shoreline zone species] will be evaluated
based on the effectiveness of the vegetation for wildlife habitat by
comparing appropriate measures of cover, density and species richness of
the reclaimed lands to similar parameters on reference areas.
To make this point even more clear, these species can be observed on Exhibit 3 to
the reclamation ,plan, which is attached as Attachment 7 to the reclamation plan.
(Reclamation Plan and Supporting Documents, Attachment 7.)
Item 11, page 5
OMR states in item 11 on page five that the reclamation plan fails to describe
revegetation monitoring. Specifically, OMR claims the following:
The plan does mention that revegetation will be monitored for five years
but the plan fails to link monitoring to performance standards.... The plan
must state that revegetation will be monitored annually in the spring by a
qualified botanist or restoration ecologist for a minimum of five years
following planting. A description of the monitoring plan must include a
discussion of the statistical sampling method for determining revegetationr
success. The sampling method must provide at a minimum an 80%
confidence level that the portion of the revegetation sampled represents
the revegetation of the site as a whole.
BCC has taken great steps to ensure that its revegetation plan either meets or
exceeds all monitoring requirements set forth in SMARA and its regulations. The
reclamation plan specifically provides that revegetation monitoring will take place for
five years. During the five-year monitoring period, annual reports will be submitted to
the Bufte County Planning Division. The reports will describe the success of the,
revegetation plan and will include recommendations for how to improve, if possible, the
plan's success in the following year. In addition, the reclamation plan expressly provides.
as follows:
Methods for monitoring and assessment will be based on guidelines provided in
the Department of Conservation's recently published manual on the rehabilitation process
for disturbed lands (Newton and Claassen, 2003).
In other words, the reclamation plan is designed to mirror SMARA's revegetation
requirements.
Item 12, page 5
OMR states in item 12 on page five, that the reclamation plan must have a signed
statement of responsibility.
-7-
The reclamation'-plan has a signed statement of responsibility.
BCC carefully considered OMB's comments in preparing this letter. While many
of the comments were already addressed in the reclamation plan, some positive minor
changes were made as a result of OMR's comments.
Please call me at your earliest convenience to discuss this letter and to set up a
meeting to establish a timeline to approve the reclamation plan.
Sincerely,
Rene A. Vercruyssen
cc: Jeffrey K. Dorso, Esq. ,
The Diepenbrock Law Firm
K
/ I
y
.8.
NorthStar
ENGINEERING
Civil Engineers • Surveyors
October 19, 2005
Rene Vercrussen
Baldwin Contracting Company, Inc
1764 Skyway .
Chico, CA 95828
RE: Public. Works Comments 6-22-05 - M&T Chico Ranch Mine
Dear Rene;
This letter is in response to the comments received on 6-22-05 from the
Department of Public Works. Their comments were limited to concerns
involving drainage and flood control aspects of the "Reclamation Plan
and Supporting Documents for M&T Chico Ranch Mine; dated
September 2004".
A large number of their comments are in regards to supporting
documents in the plan, many of which are from the original
Environmental Impact Report (EIR) dated September 2002. It should be
noted that the County has already reviewed and commented on the EIR.
The intent of submitting this to the county was not a second review of
the EIR but a review of the supporting material that has been asked for
by various agencies. J
We realize that the County is an important party in the review and
approval process, but at the same time we would like the county to
understand that they are but one of many agencies that are reviewing
and approving the project. Many of these agency's "area of concern"
overlap and may not directly agree, because of this we are seeking the
counties help in coming to compromises with the other agencies
involved.
Please read through the responses to the Public Works comments and
keep in mind that at this stage of the proposed project only approval of
the project concept and EIR is being proposed, not specific engineering
plans for construction. There will be more than adequate time to review
engineering plans and file for permits after the EIR approval.
Si cerel ,
Ross Simmons, P.E.
NorthStar Engineering
20 DECLARATION DRIVE
CHICO, CALIFORNIA 95973
530-893-1600
FAX -893-2113
The comments from the 6-22-05 Public Work's review are shown in
italics and responses to comments follow.
1. The weir and bypass channel locations shown in attachment 6'
disagree with the mitigations in attachment 14 and designs in
attachments 16 and 17.
Response: Attachment 6 has been revised to clear up mis-
understandings and discrepancies. .One major point of confusion is that
there are 2 separate bypass channels with 2 separate purposes
mentioned in the EIR.
The bypass channel described in 4.4-3b is along the western side of the
pit and is to be designed to accept flows from Little Chico Creek that
historically went through the pit location. Its purpose is to alleviate the
impacts of the low levee/weir on the Jones parcel by mimicking the
current splitting of Little Chico Creek. Attachment 16 demonstrates a
possible design for this bypass channel.
One of two options for mitigating closures on River Road due to flood
waters is removing an existing levee and constructing a setback levee.
The other.option includes installing larger culverts and raising the road
at the low points in River Road.
The second bypass channel mentioned in the text (MM 4.4-7a) is in
reference to the setback levee. The existing levee just west of the
proposed plant site could be removed and a new. levee (not to exceed the
original's elevation) could be constructed 200' to the east of the old levee.
In a 1-17-02'preliminary report by NorthStar Engineering one mitigation
measure .was to construct a set back levee, leave the existing levee intact,
and construct a bypass channel between the levees. This bypass .
channel would convey flood waters that overtopped the existing levee to
enlarged culverts at the south edge of the plant and back into Little
Chico Creek. A report was issued on 2-27-02 that suggested (as one
mitigation option) the existing levee be removed completely allowing
flooding waters complete access to the area and thus negating the
purpose of the bypass channel. Attachment 6 shows this mitigation
measure.
Attachment 17 is a possible design for the low levee/weir described in
the EIR and matches schematically what is shown on Attachment 6.
Attachment 6 has been revised to match the wording used in the' EIR and
attachment 17.
2. Attachment 14, mitigation measure (MM) 4.4-3a indicates that the
storm water from the processing plant will not enter the pit but does
1
not disclose where or how the storm water will be handled.. Impact
4.4-4 indicates "Internally generated storm water will be retained
on-site", then indicates a permit will be required to allow this water
to go off-site. The plan needs to define and analyze what is actually
proposed either on-site, retention or on-site detention with drainage
to a natural water course?
Response: It is correct that storm waters will be kept from entering the
pit, this includes existing field ditches 'to the east and south of the pit as
described in MM 4.4-3c as well as storm water from the plant site in MM
4.4-3a. The purpose of keeping field runoff and plant runoff from
entering the pit up to a 10 year event, is to minimize any possible impacts
to groundwater. It is recognized that runoff from farmed fields can
contain high levels of pollutants, that in high concentrations can.
jeopardize ground water safety.
What the statement in MM 4.4-3a is saying is that storm waters from the
plant SHALL NOT enter the pit. The statement in 4.4-4 then elaborates
on where these waters CAN go, which is back into Little Chico Creek
(with the proper permitting). These permits would include a basic site
development plan with the County of Butte. Included in this would be
pre and post storm water runoff estimates and likely (as required by the
County) a no net increase in peak runoff requirement. When a
construction permit is applied for a detention pond can be sized and
included in the southwest corner of the proposed plant area. The entire
plant facility would be tributary to this detention pond and flows released
to Little Chico Creek would be less than the pre -development flows.
3. Attachment 14, MM 4.4-3b, how will floodwater be drained from the
pit? See the second paragraph on page 243 "As a worst case, in
theory, overflows could erode down the buffer and Little Chico Creek
could be diverted, in its entirety, through the created lake." -How
will the pit and subsequent reclaimed lake be operated and
maintained to protect the existing Little Chico Creek?
Response: In the 10+ year event it is recognized that Little Chico
Creek will spill over the weir and enter the pit. This will raise the lake
water level up to a point where the lake will spill out of the south end
and back into Little Chico Creek. This flow path currently exists now
at the proposed location of the weir. As the 10 year flood recedes tale
water level in the pit will steadily drop to the bottom of the existing
channel out, then slowly drop to its base level through steady
infiltration to the creek bed and aquifer. There will be no need to
"drain" the pit entirely as it is proposed to be wet mine.
The "worst case scenario" depicted on page 243 is mitigated in both
MM 4.4-5 and MM 4.4-6.. The mitigation measures state that the
slope of the buffer shall be designed by a registered civil engineer to
prevent erosion, approval of the plan by Butte County is required.
Both structural and vegetative measures shall be used to stabilize the
buffer strip (pg. 4.4-70 of the EIR).
Note that originally a 50' wide buffer between the top bank of Little
Chico Creek and the pit edge was proposed but this has been
increased to 100'.
4. Attachment 14, MM 4.4-3c, the channels to be improved and
proposed improvements need to be shown on the plans and fully
addressed in the text.
It is unclear whether ditches within 1, 000 feet on the east side or
ditches on the east side to 1, 000 feet southerly (no plan view
associated with text) are proposed to be improved to a 10 -year
capacity. No design calculations or plans were provided for these
ditches. The flood impact studies by NorthStar Engineering do not
show the boundaries of the 10 -year event, however the FEMA
mapping indicates the 100 -year flood plain :extends more than 1, 000
feet east of the mine site and includes the topsoil stockpile areas.
What is the purpose of improving the ditches on the east side to a 10
year design capacity? Provide analysis for the impacts of the topsoil
stockpiles to the flood plain elevations.
Also this MM identifies the fact that all the proposed' levees will be
overtopped by flood flows from the Sacramento River, but does not
identify erosion control measures to be taken to protect the levees
and pit slopes during operation or to provide protection for the
reclaimed lake.
Response: The ditches in question have been added to attachment 6 to
help clarify the wording in the EIR. The existing ditches are to include
the ditch at the southern edge. of the pit as well as all existing ditches
within 1,000 feet of the eastern side of the pit. The ditches carry local
storm water from the fields to the north and east and do not carry flows
from Little Chico Creek. The purpose of ensuring these ditches will
accommodate' the 10 year design flows is to keep the direct field runoff
from overflowing the ditches and entering the pit. _
The 10- year flood in Little Chico Creek does not enter the pit area
staying instead to the west of the pit (in the bypass channel and in Little
Chico Creek through the Jones parcel): The topsoil piles are to the west
3
of the pit beyond a levee and do not effect the 10 -yr flood plan elevation.
The 100 year flood plain topic is covered on page 4.4-6 of the EIR.
5. Attachment 14, pages 243 and 244, proposed project with and
without batch plant identifies a 50 foot not 100 foot wide buffer
between Little Chico Creek and the northern edge of the pit. This
conflicts with other information contained in the document, including
attachment 6.
Response: This is correct. The EIR continually references a 50'
buffer, however this has been increased this to 100'.
6. Attachment 14, it appears pages are missing from the document so v
a complete evaluation cannot be made. Page 244 is identified as
4.4-73,'page 245 is identified as 4.4-75.and the content does not
flow from one page to the .next. Also page 245 (the last page of this
attachment) ends in the middle of a sentence. Provide a complete,
comprehensive copy of this attachment for review and comment.
Response: This is correct. The document provided for review was a
compilation of relevant Reclamation Plan documents, titled
"Reclamation, Plan and Supporting Documents". 'To give context to
the discussions the document contains some excerpts from the EIR,
BUT does not include the complete EIR. This document is intended to
support and be read with the EIR. Attention is drawn to the fact that
the pages mentioned above have the words "M&T Chico Ranch Draft
EIR" written next the EIR page number and then followed by a bold
single page #. The attempt was not to' confuse the county but to
provide clarity by organizing all the supporting documentation in one
place.
7. Attachment 16 provides some design calculations for a Little Chico
Creek bypass channel, but does not provide information with
respect to the construction location or design flow of 1, 000 cfs.
Response: Attachment 16 is difficult to understand out of context.'
What it is attempting to show is that. a sufficient bypass channel can
be designed to mitigate the flooding of the Jones tract which would
occur once the low levee/weir was installed. The bypass channel
would be designed to mimic the existing flow event through the pit
area. This existing flow occurs when the. Little Chico Creek flows top
300 cfs. Once the project is approved detailed plans for the bypass
channel and its head works will be developed and submitted to the
county for review and approval.
0
8. Attachment 17 provides a design for an overflow weir for Little Chico
Creek, but does not provide a backwater analysis for the flood plain
and does not address how Sacramento River overflows will react to
the weir and setback levee. The design appears to be for the 50
year event, not the base flood, 100 -year event. Page 304 profile, is
the left levee looking upstream or downstream. Sections 1, 2, and .
2.5 appear to intersect the pit, but there is no information with
respect to the sections looking upstream or downstream and the pit
is not shown.
Response: Attachment 17 does contain a backwater analysis for the
flood plain. The report analyzes the water surface elevation from
cross section 8 to section 0.5 as shown on page 300. The addition of
flows from the Sacramento River complicates the area and makes a
dependable hydraulic analysis extremely difficult; this is why no 100
yr flooding is shown." It should be noted that the detailed study area
with 100 year water surface elevations prepared by FEMA ended just
upstream from the Sacramento River sloughs and the project area.
The 100 year flood plain topic is further covered on page 4.4-6 of the
EIR.
Note that.all HEC RAS model river stations are viewed from the path
of flow meaning you start at the upper most and view them traveling
downstream.'.This makes the "left levee" the same as the east levee for
this study. The pit is not shown on the cross sections; but flow
through the pit equals. that over the weir.
5
_
_ BALDWIN CONTRACTING COMPANY, INC.
GENERAL ENGINEERING CONTRACTORSs�t
��CTINGC�' 1764 SKYWAY/CHICO, CA 95928 (530) 891-6555 (530) 894-6220 FAX
_ NOV V.1
DEVELOPN"I
- SERVICES
October 18, 2005
Butte County -,
Department of Development Services
Attention: Dan Breedon
7 County Center Drive
Oroville, CA 95965
Re: M&T Ranch Mine, Butte County Department of Public Works (DPW) comments on
Reclamation Plan and Supporting Documents, submitted on September 20, 2004, by
Baldwin Contracting Company, Inc. "
Dear Dan:
_ On September 20, 2004, Baldwin Contracting Company, Inc. (Baldwin) submitted a letter
- and a document titled, Reclamation Plan and Supporting Documents, in reply to Department
of Conservation (DOC) letter of comment dated June 10, 2004. As most of the questions
contained in the DOC letter had already been addressed in other documents, Baldwin was
concerned that there was some confusion among the agencies with review authority about _
the reclamation plan for the M&T Ranch Mine project. For that reason Baldwin used the
time between June and September of 2004 to compile a document, made up entirely of
documents already submitted and reviewed by state and county agencies, that was intended
to provide the agencies a comprehensive compilation of the reclamation plan and portions of
other documents referenced in the reclamation plan in one place. Over ten months later, on
August 2, 2005, Baldwin received a letter from Butte County Development Services, with
an Inter -Departmental Memo from the Public Works Department, dated June 22, 2005. This
memo had eight numbered comments, regarding "drainage and flood control aspects of the
Reclamation Plan and Supporting Documents for M&T. Chico Ranch Mine". Many of the
DPW comments were on excerpts from the Draft EIR prepared for the M&T Ranch Mine -
Project in September 2002, and already commented upon on several occasions by the state
and county agencies. The Draft EIR was extensively excerpted in compiling the
Reclamation Plan and Supporting Documents.
Baldwin submitted the DPW comments to NorthStar Engineering, who did the flood
study work for the Draft EK for reply: Attached is a cover letter and replies from
NorthStar Engineering. -
Very truly Yours
David Barney
President
Baldwin Contracting Company, Inc.
Butte County Department of.Development Services UT T
PAUL MCINTOSH, INTERIM DIRECTOR
o� Fo.
7 County Center Drive o 0
Oroville, CA 95965 0 0
(530) 538.7601 Telephone o
(530) 538.7785 Facsimile o- o,
COU IN
ADMINISTRATION * BUILDING * GIS * PLANNING
August 2, 2005 ;
Mr. Rene A. Vercruyssen
Baldwin Contracting Company, Inc.
1764 Skyway
Chico, CA 95928
RE:, Department of Public Work's,Review of "Reclamation_ Plan and Supporting
Documents for M&T Chico Ranch -Mine, September 2004"
Dear Mr. Vercruyssen:
Enclosed please find. comments received from the Butte County'Department of Public .
Works concerning the September 20, 2004 submittal 'referenced above. Prior to
transmitting this document to the Department of Conservation, *the comments provided,by
the Department of PublicWorks must be addressed. Please provide a response to the
issues brought forward by the Department of Public Works in the attached June 22„2005
memo. This response must be received prior to scheduling this project before the
Planning Commission:
This project has been continued' off the Planning Commission Agenda, 'due to the
Williamson Act Contract, cancellation. and non -renewal process that has been under
consideration by your company. Therefore I am not sure when this project will again be
scheduled fora Planning Commission hearing.
Thank you for your attention to this matter. Should you have any questions, please
contact me at this office.
ye1
Dan Breedon
Principal Planner
Enclosure
Y
INTER -DEPARTMENTAL MEMORANDUM
PUBLIC WORKS DEPARTMENT
TO: DAN BREEDON, PRINCIPLE PLANNER.
o.�V.T,
O: 0
i - 0 0'
U N�
A�Crc. wOP�y �+
FROM: STUART EDELL, MANAGER, LAND DEVELOPMENT DIVISION
PUBLIC WORKS ,
SUBJECT: RECLAMATION PLAN AND SUPPORTING DOCUMENTS FOR
M&T CHICO RANCH MINE
DATE: JUNE 22, 2005
We have the following comments with respect to drainage and flood control aspects of the
"Reclamation Plan and Supporting Documents for M&T Chico Ranch Mine, dated September
2004":
1. The weir and'bypass channel locations shown in attachment 6 disagree with the
mitigations in attachment 14 and designs in attachments 16 and 17.
V
2. Attachment 14, Mitigation Measure (MM) 4.4-3a indicates that the stormwater,
from the processing site will not enter the pit but does not disclose where or how
the storm water will be handled. Impact 4.4-4 indicates "Internally generated
stormwater will be retained on-site", then indicates a permit will be required to
allow this water to go off-site. The plan needs to define and analyze what is
actually proposed either on-site retention or on-site detention with drainage to a
natural water course?
3. Attachment 14, MM 4.4-3b, how will floodwater be drained from the pit? See the
second paragraph on page 243 "As a worst case, in theory, overflows could erode
down through the buffer and Little Chico Creek could be diverted, in its entirety,
through the created .lake." How will the pit and subsequent, reclaimed lake.be
operated and maintained to protect the existing Little Chico Creek?
4. Attachment 14, MM 4.4-3c, the channels to be improved and proposed
improvements need to be shown on the plans and fully addressed in the text.
f
It is unclear whether ditches within 1,000 feet on the east side or ditches on the
east side to 1,000 feet southerly (no plan view associated with text) are. proposed
to be improved to a 10 -year capacity. No design calculations or plans were
M&T Reclamation Plan Comments
June 22, 2005
Page 2 of 2
provided for these ditches. The flood impact studies by NorthStar Engineering do
not show the boundaries of the 10 -year event, however the FEMA mapping
indicates the 100 -year flood plain extends more than 1,000 feet east of the mine
site and includes the topsoil stockpile areas. What is the purpose of improving the
ditches on the east side to a 10 -year design capacity? Provide analysis for the
impacts of the topsoil stockpiles to the flood plain elevations.
Also this mitigation measure identifies the fact that all the proposed levees will be
overtopped by flood flows from. the Sacramento River, but does not identify
erosion control measures to be taken to protect the levees and pit slopes during
operation or to provide protection for the reclaimed lake.
5, Attachment 14, pages 243 and 244, proposed project with and without Batch
plants identifies a 50 -foot not 100 -foot wide buffer between Little Chico Creek
and the northern edge of the pit. This conflicts with other information contained
in the document, including attachment 6.
6. Attachment 14, it appears pages" are missing from the document so a complete
evaluation cannot be made. Page -244 is identified as 4.4-73, page 245 is
identified as 4.4-75 and the content does not flow from one page to the next.. Also
page 245 (the last page of this attachment) ends in the middle of a sentence.
Provide a complete, comprehensive copy of this attachment for review and•
comment.
7. Attachment 16 provides some design calculations for a Little Chico Creek bypass
channel, but does not provide information with respect to the construction
location or design flow of 1,000 cfs.
8. Attachment 17 provides a design for an overflow weir for Little Chico Creek, but
does not provide a backwater analysis for the flood plain, and does not address
how Sacramento River overflows will react to the weir and setback levee. The
design appears to be for the 50 -year event, not the base flood, 100 -year event.
Page 304 profile, is the left levee looking upstream or downstream. Sections 1, 2
and 2.5 appear to intersect the pit, but there is no information with respect to the
sections looking upstream or downstream and the pit is not shown.
cc: Mike Crump, Director of Public Works (File 180.2)
�% T rF o
p p
d
emoranumJ_ o
°
TO: Mike Crump, Public Works Director
FROM: Dan Breedon, Principal Planner
w SUBJECT: M&T Chico Ranch Mine
DATE: May 23, 2005
Department of Development. Services
Planning Division
° Mike,
This document ("Reclamation Plan,.and Supporting Documents") represents Baldwin Contracting
Companies response to the Department of Conservations critique of their submitted reclamation
plan pursuant to SMARA. Some.of the issues that,the DOC comments upon involve drainage,
'flooding,engineering and design information pertaining to these subjects. I am requesting that
the Department of Public Works review, Bald iw n's responses prior to accepting this document as
complying with:SMARA and the concerns brought up by DOC. The area that I would request
Public Work's input on' concerns the "Geotechnical Requirements, Hydrology and Water
Quality" Section (Items.3 -5) of DOC's June 10, 2004 letter. Although this project has been
continued off the Agenda, I am requesting a response from your Department within the next 30
days.
Thanks for your attention to this matter. I am also requesting that the "Reclamation Plan. and
Supporting Documents" provided with this Memo be returned to me when your review is
completed.