HomeMy WebLinkAbout89-161
;'
BARD OF SUPERVISORS
COUNTY OF BUTTE, STATE OF CALIFORNIA
Resolution No89-161
RESOLUTION OF THE BOARD OF SUPERVISORS
CERTIFYING EXPENDITURES ON THE
BUTTE COUNTY HAZARDOUS WASTE MANAGEMENT PLAN
WHEREAS, Butte County received $112,756.24 from the
Department of Health Services for preparation of a Hazardous
Waste Management Plan, Environmental Impact Report and revision
of various permit processes and procedures; and
WHEREAS, Butte County has spent approximately
$90,067.00 as of July 31, 1989; and
WHEREAS, Butte County is still awaiting response from
the Department of Health Services and anticipates some plan
changes; and
WHEREAS, Butte County still has to adopt the Final
Plan, amend the zoning ordinance and establish permit processes.
NOW, THEREFORE, BE IT RESOLVED, that Butte County will
utilize the remaining funds to complete the upgrading of the
Butte County Zoning Ordinance and the revision of various permit
processes and procedures.
PASSED AND ADOPTED by the Butte County Soard of
Supervisors on the 31st day of October 1989, by the following
vote:
AYES: Supervisors Uercruse, McLaughlin and Chairman Fulton
NOES : None
ABSENT: Supervisors McTnturf nd Dolan
NOT VOTING: None
LE ULT N, CHAIRM
B' to County Board of Supervisors
ATTEST: WILLIAM H. RANDOLPH, Chief Administrative
Officer and Clerk of the Board
By
STATE OF CALIFORNIA
DEPARTMENT OF HEALTH SERVICES
TOXIC SUBSTANCES CONTROL DIVISION
SAMPLE
EXPENDITQRE REPORT
For
County Hazardous Waste l~ianagement Plans
County Name: Butte County
Responsible Agency: Planning Department
Contact Name: Paula Leasure
--~
Phone Number: 916j 538-7501
Amount of Funds Provided By State: $112,756.24
Disposition of Funds:
Total Total
Allocated Expended
- Salaries: 47,468 29,846
- Benefits: 15,503 10,905
- Services/Supplies: N/A
- Consultant Costs: 35,000 25,312
- Overhead ( ]. ) : 4 , 9 7 0
- Travel Expenses: 1,750 1,453
- Meetinas/Hearin.gs: 1$,419 1,500
- Equipment: 5,067 6_,067
- Publications & Legal - 3,625 1,933
Office Expenses 9,950 5,000
Tota1:_ 137,,782 ,_. 86.;,986'
General Information:
- Include a description of al3 tasks related to CHWMP
development and Identify the number of personnel years
or full time equivalents charged to the project.
- Identify if time sheets were maintained for employees working
on development of the CHWMP.
(1) Based on approved Countywide Cost Allocation Pian)
* See Attached Addendu~r-
- Identify if funds were maintained in a separate account or
included in the overall county general fund. If maintained in
a separate account, identify by account name and agency or
department responsible far maintaining the account. Include
all pertinent contact names and telephone numbers.
CERTIFICATION:
I certify that the above expenditure ,report and all attachments
hereto is an accurate representation of funds received from the
Hazardous Waste Planning Subaccount and used for the development of
the County Hazardous Waste Management Plan, and is supported by
auditable accounting records maintained in conformity with the
Accounting Standards and Procedures for Counties issued by the
Office of the State Controller.
Signed by:
Title:
Date:
a: Report/Tanner 1
Accounting
A separate account was not opened far the monies received
from the Department of Health Services for preparation of the
Butte County Hazardous Waste Management Plan. The monies were
put into the general planning budget under the assumption that
the funds would not be adequate and Butte County would have to
augment the funds in order to complete the plan.
Time cards were kept by the Associate Planner who's primary
responsibility was to do the County Hazardous waste Management
Plan and the principal steno-clerk. Time cards were not kept by
the Planning Director, Senior Planner and Planning Technicians.
Salaries and Benefits
Butte County has a documented expenditure of $25,529 for
wages and $9,317 far benefits for the Associate Planner and
clerk/typist. This is a total of $34,846.00 through February 1,
1989. This amount does not cover the estimated time for the
Planning Director, Senior Planner and Planning Technician.
The estimated cost of funding those positions are as
follows:
Wages Benefits
Planning Director $1,743 $ 662
Senior Planner 1,500 525
Planning Technician 1,054 401
TQTAL $4,297 $1,588 = $5,885
The total salary and benefit package through February 1,
1989 is $40,731 ($34,846 ~ $5,885).
Consultant Costs
The contract with the consultant was in the amount of
$35,000. Butte County withheld a retention of $8,750 which has
been forfeited due to their breach of contract. An additional
$938.00 for printing was forfeited for a total of $9,688.00.
These funds will be unencumbered in the near future and placed
back into the Planning Departments budget for repayment of staff
time used to complete the document. In addition, there still
remains work to be done on the Final Plan, including printing.
The printing is estimated at $1,200 for 100 copies of the plan.
Overh.eac7
The estimated yearly overhead for the Butte County Planning
Department is $18,077 per year. The Planning Department has ten
employees resulting in an overhead amount of $1,808 per person
per year. This calculates out to approximately $4,970 of
overhead through February 1989.
Travel
As of February 1, 1989, $1,453.00 was spent far travel and
related expenses. There is still field work remaining due to
future amendments to the General Plan and zoning. Also, mileage
and other expenses is accrued during the supervision of the work
study student who is providing staff support.
Meetings and Hearings
Separate accounting for meetings and hearings was not
provided for. Butte County held monthly Advisory Committee
meetings. Also, monthly meetings were held by the sub-committees
on source reduction, public participation and intergovernmental
relations. All Advisory Committee meetings were staffed by an
Associate Planner and clerk. Technical, clerical and support
service was provided to all committees.
On the recommendation of the Advisory Committee, a work-
study student was hired to write news articles, assist in
establishing a hazardous waste program in the schools and to
speak to organizations about the Tanner Process. This position
runs through Map 1989. The position was allotted $1,000 with an
additional $500.00 for support services.
Staff also attended two rounds of hearings at each of
Butte's incorporated Cities and numerous appearances before the
Board of Supervisors.
Equipment
Butte County purchased a computer and software for hazardous
waste management. The Butte County Hazardous Waste Management
Plan and Environmental Impact Report are on disk as is all
related data.
Office Expenses
Office expenses, which include paper and copying for
letters, agendas, Advisory Committee packets and miscellaneous
educational materials is estimated at $5000.00. This does not
include publication of the draft and final plans, or the draft
and final EzR's.
Publications and Le al
The publications and legal expenses of $1,933 include only
costs associated with printing the draft County Hazardous Waste
Management Plan and the draft E.I.R. The Final Plan and Final
E.I.R. will be printed in March, 1989 at an estimated cost of
$1,200.
The printing costs for letters, agendas, committee packets,
and educational materials was not separated from the Planning
Department's regular budget.
ADDENDUM TO EXPENDITURE REPORT NO. 1
Between February 1, 1989 and March 31, 1989, an
Associate/Senior Planner spent 121 hours on Hazardous Waste
Management Planning.
Associate/Senior Planner
121 hours x $12.65/hour =
x 375 for overhead
Total expenditures through 1-31-89
Expenditures through 3-31-89
$1,531
566
$2,097
$86,986
89,623
Balance as of 4-1-89 is $23,133
ADDENDUM TO EXPENDITURE REPORT NO. 2
Between April 1, 1989 and July 31, 1.989, an Associate/Senior
Planner spent 25 1/2 hours on Hazardous Waste Management
Planning.
Associate/Senior Planner
25 1/2 hours x $12.65/hour = $322.58
x 375 for overhead 120.97
443..55
Total expenditures through 3/31/89 $89,623
Expenditures from 4~1-89/7-31-89 444
Balance as of 8-1-89 is $22,689