HomeMy WebLinkAboutA072319SUSHARI MCCRACKEN
CHIEF ADMINISTRATIVE OFFICER
CLERK OF THE BOARD
3. CONSENT AGENDA
BUTTE COUNTY
BOARD OF SUPERVISORS
SUPPLEMENTAL AGENDA
JULY 23, 2019
9:00 AM
MEETING LOCATION
BOARD OF SUPERVISORS CHAMBERS
25 COUNTY CENTER DRIVE, SUITE 205
OROVILLE, CALIFORNIA 95965-3380
MEMBERS OF THE BOARD
STEVE LAMBERT, CHAIR, DISTRICT 4
BILL CONNELLY, DISTRICT 1
DEBRA LUCERO, DISTRICT 2
TAMI RITTER, DISTRICT 3
DOUG TEETER, VICE CHAIR, DISTRICT 5
BRUCE ALPERT, COUNTY COUNSEL
3.38 Purchase and Sale Agreement with Gorrill Land Company and R. Gorrill Ranch Enterprises
(Gorrill) for the Midway Bridge Project -The County entered into an agreement on December 16,
2010 with Caltrans to complete the Midway Road Bridge Replacement Project across Butte Creek
and Butte Creek Overflow. The bridge replacement project is funded by the Federal Highway
Bridge Program. In general, this project will replace two existing bridges originally constructed
in 1915 and 1918 respectively. The proposed project will construct the new bridge along the
current alignment of the existing bridges. The project agreement requires the County to acquire
all rights-of-way and easements necessary to construct the project. One of Gorrill's existing
agricultural wells is located close to the new and wider bridge location, and the fill slope will
encroach into the well location, which necessitates the abandonment and replacement of the
well. The well replacement has a base cost of $275,086 with a not -to -exceed amount of
$350,000. The agreement allows for potential additional costs incurred during construction of
the new well. The cost of right-of-way purchase for the temporary construction easement and
fee title for these properties is $19,549, which makes the total base cost of the agreement
$294,635 and the total not -to -exceed cost of $369,549. A resolution authorizing the Director of
Public Works to negotiate and enter into agreements for the acquisition of real property,
temporary construction easements, and permits to enter and construct improvements for the
Midway Road Bridge Replacement Project across Butte Creek & Butte Creek Overflow was
adopted by the Board on January 9, 2018. Due to the overall cost of the agreement the
Department of Public Works is bringing forth this agreement for Board consideration — action
requested — APPROVE PURCHASE AND SALE AGREEMENT AND AUTHORIZE THE DIRECTOR OF
THE DEPARTMENT OF PUBLIC WORKS TO SIGN. (Public Works)