WASHINGTON, DC 20426
March 5, 2014
OFFICE OF ENERGY PROJECTS
Project No: 619-158— California
Bucks Creek Project
Pacific Gas & Electric Company
City of Santa Clara, California
Tina Bartlett, Regional Manager--North Central. Region
California Department of Fish and Wildlife
1701 Nimbus Road, Suite A
Rancho Cordova, CA 95670
Earl W. Ford, Forest Supervisor
Plumas National Forest
159 Lawrence Street
1%
Quincy, CA 9.5971
Subject-, Extension of Time for Filing Study Requests and Comments on Pre-
application Document and Scoping Document I for the Bucks Creek Project
Dear Ms. Bartlett and Mr. Ford:
On March 3. 2013, you requested a 30-day extension of time, from March
159 2014 to April 14, 2014, to file study requests and comments on the Pre-
application Document (PAD) and Scoping Document I (SDI) for the Bucks Creek
Project. You indicate that additional time is needed because of the increase in
workload associated with draught-related deviations from license conditions for
projects located in the Sierra Nevada Region of California.
Your request would allow the necessary time to consult with licensees on
the requested variances to minimum flow requirements due to the unprecedented
draught in California. Granting your request would minimally affect the overall
Process Plan and Schedule. Therefore, your requested extension until April 14,
2014 is granted. The Process Plan and Schedule is thereby revised as follows:
PA
Responsible
Pre-Fifing, Milestone
Date
FERC
Regelation
f
P D 1, C6mments and Study
411,41201,4'
5.9
stakeholders
Requests Due.
FERC
Issue Scoping Document 2
5129114
5.1
The
File Ptoposed: Study Plan, (PSP)
5129114
5.11(a)
applicants
All
slakcholdm
Proposed Study Plan Meeting
6129114
5.11 (e)
All
stakehokkxs
Proposed, Study Pte.. Comments Due
9/2,7114
5.12
File Revised S� Plan
9126114
5.13(a)
appli cmts
All
Revised. Study Plan Commerds Due,
10111114
5.13(b)
sbakemdMI
x,
F ERC' -
do
M Detmnvn
E 4 grecwr's: SID P I ni
(cL) l
If yco have- an-y- quc. pk&se cofAacl Alan: N'llitchnick at (2023 502 -.
cc: Mailing List
Public Files
Alan Somda, Sr. Project Manager
Pacific Gas& Electric Company
Mail Code N13E
P.O. Rox 770000:
San Francisco, CA 94177
Sincerely,
Vince Yearick
Director
Division of Hydrop'ower Licensing