PUMP CHECK REPORT
2313 Durham -Dayton Hwy.
Durham, CA 95938 530.891.4821 CSA#172 Autumn Park Subdivision
CUSTOMER NAME: Butte County Fire Dept. DATE:
12/12/19
Motor Mfg: Franklin HP: 2 Meter #:
RPM Volts 240 Phase 1
Rated Amps:
TM 80E—] Yes F—]No Serial #
PG &E Acct. # Other:
Panel Mfg: Franklin control box NEMA Size:
Type: F—]X/L F—] P/VV Other:
Pump Mfg: Serial#:
Non -Running Checks: Pump Model Manufacturer
na F]Lubricant Levels - Service and Change if Necessary
na Oiler Unit and/or Packing
Electrical Leads & Connections - Repair and Tighten as Necessary
Incoming Idle Voltage: F]W/I Acceptable Limits
Unacceptable
F]Fuses - Replace if Necessary FIReplaced Size:
15 amp
F]Perform General Clean -Up of Electrical Panel and Motor
Running Checks: Motor winding resistance:
Excessive or Unusual Noise F]Ok
Excessive or Unusual Vibration F]Ok
Control Devices: MX H.O.A. FIStart Switch
Time Clock
Frost Start Time Delay Other:
Press. Sw. 40-60
Amperage: Expected: 9.8
Actual: Red. 2 Yellow. 11.3 Black: 10.4
Average: 7.9
Overload Underload
Even Load
Bowl Adjustment: N/A Yes F—]No
Comments:
GPS: 39°487.51"N 121°53'40.31"W
The above readings reflect the site and pump conditions at the time of inspection.
This report does not guarantee the continuation of these conditions, nor warranty any part of the existing system.
S:\Pump Dept. Files\PUMP TESTS & INSPECTIONS\Cal Fire CSA's\172 Autumn Park\172 Reports
Durham, . PUMP
2313 Durham -Dayton Hwy.
Durham, CA 95938 530.891.4821
PUMP CHECK REPORT
CSA#172 Autumn Park Subdivision
CUSTOMER NAME: Butte County Fire Dept.
DATE: 12/12/19
Motor Mfg: Franklin HP: 25 Meter #: X11162
RPM 3450 Volts 460 Phase 3
Rated Amps: 75max
TM 80❑Yes ❑X No Serial #
PG &E Acct. # Other:
Panel Mfg: Furnas NEMA Size: 3
Type: F—]X/L F� PNU Other:
Discharge Mfg: Fabricated steel 6" Serial#:
Non -Running Checks: Pump Model Manufacturer
na ❑ Lubricant Levels - Service and Change if Necessary
na Oiler Unit and/or Packing
❑ Electrical Leads & Connections - Repair and Tighten as Necessary
Incoming Idle Voltage: F]W/I Acceptable Limits
Unacceptable
Fuses - Replace if Necessary 1-1 Replaced Size:
100 amp MCP
❑ Perform General Clean -Up of Electrical Panel and Motor
Running Checks: Motor winding resistance: 1.2 Megs to ground
Excessive or Unusual Noise F]Ok
Excessive or Unusual Vibration F]Ok
Control Devices: ❑X H.O.A. ❑X Start Switch
ElTime Clock
Frost Start Time Delay Other:
Pres. Sw.
Amperage: Expected: 75.0 max
Actual: L1: 73.6 L2: 71.8 L3: 72.8
Average: 72.73
Overload Underload
❑ Even Load
Bowl Adiustment: N/A Yes F—] No
Comments:
High idle voltage. 490V, 492V, 490V
Gate broken
GPS: 39'48'7.51"N 121'53'40.31"W
The above readings reflect the site and pump conditions at the time of inspection.
This report does not guarantee the continuation of these conditions, nor warranty any part of the existing system.
S:\Pump Dept. Files\PUMP TESTS & INSPECTIONS\Cal Fire CSA's\172 Autumn Park\172 Reports