HomeMy WebLinkAbout12.13.19 Email from FERC - Docket P-619-167 PGE Bucks Creek-Grizzly Project RE Requests for Minimum Instream Flow and Lake Level Variance
From:Lose, Sarah@Wildlife
To:Visinoni, Jamie; Lind, Amy -FS; Edlund, Leslie - FS; Lawson, Beth@Wildlife; Aondrea_Bartoo@fws.gov
Cc:Joseph, Matthew
Subject:RE: Updated Review/Approval Request - Bucks Creek Project, FERC No. 619 - Flow and Lake Elevation Variance
Date:Wednesday, October 16, 2019 1:36:39 PM
Attachments:LowerBucksVarianceRequest_CP_10-16-19.docx
*****CAUTION: This email was sent from an EXTERNAL source. Think before clicking links
or opening attachments.*****
Hi Jamie-
We have made some edits to the proposed variance request. Please see the edits on the attached
document. With the acceptance of these edits, CDFW approves this variance request. Thank you!
Sarah C. Lose
Senior Environmental Scientist (Specialist)
CA. Dept of Fish and Wildlife/North Central Region
Water Program-FERC Coordinator
1701 Nimbus Rd.
Rancho Cordova, CA. 95670
(916) 747-5226: cell
From: Visinoni, Jamie <JNVS@pge.com>
Sent: Monday, August 26, 2019 12:18 PM
To: Lind, Amy -FS <amy.lind@usda.gov>; Edlund, Leslie - FS <leslie.edlund@usda.gov>; Lawson,
Beth@Wildlife <Beth.Lawson@wildlife.ca.gov>; Lose, Sarah@Wildlife <Sarah.Lose@wildlife.ca.gov>;
Aondrea_Bartoo@fws.gov
Cc: Joseph, Matthew <MWJA@pge.com>
Subject: Updated Review/Approval Request - Bucks Creek Project, FERC No. 619 - Flow and Lake
Elevation Variance
Importance: High
Hello All,
Thank you for sharing your questions and concerns regarding the Bucks Creek variance request
when we met last week. We have provided more detail on the water management approach in our
variance request, please see the updated request below:
Pacific Gas and Electric Company (PG&E) plans to perform extensive repairs and
maintenance in 2020 at Lower Bucks Lake Dam and Grizzly Forebay Dam, part of
PG&E’s Bucks Creek Hydroelectric Project, Federal Energy Regulatory Commission
(FERC) Project No. 619. PG&E is requesting U.S. Forest Service (Forest Service),
California Department of Fish and Wildlife (CDFW), and the U.S. Fish and Wildlife
Department review and approval to temporarily reduce the minimum instream flows
(MIF) and minimum lake elevation to levels below those required under Article 13 for
Bucks Creek and Grizzly Creek. The request for flow reduction may not be needed
but is being submitted as a precautionary measure to ensure construction crews
safe access to the perform work on and around the dams.
Scope of Construction and Schedule
Lower Bucks Dam Work – In a letter dated December 17, 2014, FERC requested
that PG&E address several follow-up action items from the 2014 Dam Safety
Inspection for the Project. The letter stated that “Severe spalling and surface
delamination of concrete has occurred on the downstream abutments and
downstream face of the \[Lower Bucks\] dam. The condition should be carefully
evaluated, and a repair plan developed.” PG&E performed a condition assessment
in 2016 and 2017 which resulted in the installation of a geomembrane liner as one
of the recommended repairs. Engineering is underway to address the downstream
lining per the 2014 direction.
The proposed project includes installation of a geomembrane liner on the upstream
face of the dam to reduce seepage and protect the dam from further freeze-thaw
damage. To install the liner, Lower Bucks Lake will be completely dewatered, and
sediment will be excavated adjacent to the dam to support the geomembrane
placement access. The initial drawdown of Lower Bucks Lake will be conducted
using a combination of pumping, drafting water through the Grizzly Intake, and
exercising the Lower Bucks Dam low level outlet (LLO) until reservoir elevation falls
below the minimum operating elevation of the Grizzly Intake. The remaining pool of
water in the reservoir will be dewatered using a combination of the LLO and/or
pumps. The drawdown and dewatering of Lower Bucks Lake, sediment removal,
and geomembrane installation effort will be coordinated with a multi-unit outage
scheduled for May to November 2020.
During the dewatered period, instream flows downstream of Lower Bucks Dam into
Bucks Creek will be satisfied by either: 1) the Milk Ranch Conduit (MRC), which
usually flows directly into Lower Bucks Lake but may be re-routed downstream of
Lower Bucks Dam, or 2) a bypass gravity flow system from Bucks (Storage) Lake
LLO that will be routed downstream of Lower Bucks Dam. The ideal phasing would
be to start with MRC into Bucks Creek utilizing flows from the various diversions;
once those flows begin to recede and approach the Bucks Creek required MIF, the
system will be switched over to the Bucks Storage LLO gravity system; then finally
towards the end of the work, based on a calculation of storage volume in Three
Lakes, the system would by switched back to MRC for the remainder of the work.
This approach provides a redundancy in the system for the duration of work.
Grizzly Forebay/Dam Work – Logs and woody debris build up at the Grizzly Forebay
overpour spillway during the wet season. Some of these have become waterlogged
and have sunk, accumulating upstream of the dam. This project proposes to wet
dredge woody debris and accumulated sediment from the reservoir adjacent to the
LLO and the Bucks Powerhouse intake structure. This accumulated material
impacts both the intake and LLO.
The sediment drawn into the intake is causing deterioration to the Bucks
Powerhouse runners creating increased maintenance. Debris build up may also be
drawn into the LLO which could affect its reliability to provide required instream flow
releases downstream of the structure. PG&E has identified May to November 2020
as the potential outage window for the dual Bucks/Grizzly Powerhouses to support
this work.
License Requirement
License Article 13 requires, in part, that PG&E maintain a minimum instream flow in
Bucks Creek below the Lower Bucks Dam and from Grizzly Forebay to Grizzly
Creek. Minimum streamflows are:
(1) Minimum streamflows from Lower Bucks Lake to Bucks Creek:
Period Flow, in cubic feet
per second (cfs)
November 1 through April 30 4 cfs
May 1 through June 30* 8 cfs
July 1 through October 31 6 cfs
(2) Minimum streamflows from Grizzly Forebay to Grizzly Creek:
Flow, in cubic feet
Period
per second (cfs)
November 1 through April 30 4 cfs
May 1 through June 30* 8 cfs
July 1 through October 316 cfs
License Article 13 also requires PG&E maintain a minimum water elevation for all
lakes. The minimum elevation for Lower Bucks Lake is 4,966 feet.
Schedule for Temporary Flow and Reservoir Elevation Variances
Bucks Creek Variance
To ensure safe and efficient constructability, cost, and schedule, PG&E is seeking a
stst
temporary flow variance of 6 cfs from June 1 through July 1. A flow of 6 cfs will
be achieved through the bypass piping system from Bucks Lake to Bucks Creek and
may be augmented with water from the Milk Ranch Conduit (MRC), if available. If
enough water is available through the MRC, PG&E expects to be able to achieve
the License required MIF of 8 cfs.
In addition to the flow variance, PG&E requests the 24-hour average of the flow
(mean daily flow) be used for minimum stream flow measurement and reporting for
May 1 through November 1, 2020. PG&E will average all the instantaneous
readings from midnight of one day to 11:59 pm of the next day. Flow monitoring will
be achieved by installing a temporary flow meter on the bypass piping system.
Grizzly Creek Variance
To support the debris and sediment removal work, a pump system will be deployed
to maintain a consistent lake elevation. PG&E is seeking a variance from July 1
through November 1, 2020 to allow flow releases below Grizzly Dam to match the
natural inflow into the reservoir, which may drop below the license required 6 cfs
depending on water year.
In addition to the flow variance, PG&E requests the 24-hour average of the flow
(mean daily flow) be used for minimum instream flow measurement and reporting
for July 1 through November 1, 2020. PG&E will average all the instantaneous
readings from midnight of one day to 11:59 pm of the next day. Flows will be
monitored and recorded at NF22. Adjustments to pumping will be made daily to
maintain the reservoir elevation, whereby generally matching inflow to outflow.
Lower Bucks Lake Water Elevation Variance
PG&E requests a variance to the minimum elevation for Lower Bucks Lake, the lake
will be completely dewatered for the majority of the outage between May 1 to
November 1 of 2020.
Biological Resource Evaluation
Bucks Creek
Minimum Instream Flow Variance
In the event of a very dry year that results in June flows of less than 2 cfs in the
MRC, flow in Lower Bucks Creek could drop below the MIF of 8 cfs, to as low
as 6 cfs. Based on surveys conducted during relicensing (PG&E 2018), Lower
Bucks Creek is inhabited by rainbow and brown trout, with brown trout being
dominant at the upstream end of the creek, and rainbow trout being dominant
further downstream. There are no special status aquatic species known from
this stream. All lifestages of rainbow trout (adult, juvenile, fry and spawning)
are likely to be present in June, although spawning may be complete by that
time, and alI lifestages of brown trout, except spawning would be present.
An instream flow study was prepared for Lower Bucks Creek (Thomas R.
Payne and Associates 1991. Instream Flow Study for Milk Ranch, Bucks, and
Grizzly Creeks. Bucks Creek Project (FERC 619). Prepared for PG&E).
Based on this study, a flow reduction from 8 cfs to 6 cfs would result in a
reduction in habitat for rainbow trout of 11 % for fry, 15% for juveniles, and 6%
for adults. Spawning habitat would be reduced by 45%, if spawning has not
completed by that time. Habitat reductions for brown trout would generally be
less, ranging from 3% for juveniles to 7% for adults. For all lifestages except
rainbow trout spawning, the habitat reduction would be minor and would adjust
the timing of the License required MIF reduction from 8 to 6 cfs forward by up
to 4 weeks. This would have minimal to no effect on the abundance or health
of these fisheries. For rainbow trout spawning, the effect might be more
pronounced if redds were still active at the time of the flow reduction, and if
redds were placed relatively high in the channel.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour
MIF requirement is likely negligible. This variance would allow flows to drop
below 6 cfs during a brief period (a couple of hours during any given day)
during May through October 2020, without requiring a variance report for each
such occurrence. Trout would not be affected by such short-term variations in
flow.
Lower Bucks Lake Minimum Pool Variance
As described above, Lower Bucks Lake will be completely dewatered. PG&E
is working with the California Department of Fish and Wildlife (CDFW) to
develop a plan for conducting a fish rescue and to develop a restocking plan.
To the extent a fish rescue may safely be implemented, PG&E does not expect
the fish rescue to provide a biological/environmental benefit. Fish that are
rescued will likely be moved to Bucks Lake (Storage), where they would be
available to anglers, but will not appreciably increase fish populations (or
angler catch-per-unit-effort) in Bucks Lake given the much smaller size of
Lower Bucks Lake and the proportion of fish the crews will likely be able to
safely rescue. All fish that are not rescued are expected to perish. PG&E and
CDFW are also working together to develop a restocking plan for Lower Bucks
Lake that will be implemented after the lake refills. This plan will be focused on
restocking rainbow trout over a range of sizes. Bucks Lake supports the same
species of fish as Lower Bucks Lake. Other fish species will gradually
recolonize Lower Bucks Lake, but relicensing studies found that entrainment
rates are low in Bucks Lake, and therefore, this is expected to take several
years.
Lower Bucks Lake and the portion of Bucks Creek immediately downstream of
Lower Bucks Dam are within designated critical habitat for Sierra Nevada
yellow-legged frog SNYLF), listed as endangered under the Endangered
Species Act. Surveys during relicensing did not identify any occurrences of
this species in either of these areas. The nearest SNYLF observation was in
Bear Ravine located in a drainage about 0.3 miles north of Lower Bucks Dam.
The flow and water level variances associated with this project would not
adversely affect habitat values for this species. A separate biological
assessment is being prepared for submission to the U.S. Fish and Wildlife
Service regarding the potential impacts of this project on SNYLF and its
habitat, but no impacts are anticipated.
Grizzly Creek
Flow Variance
Grizzly Creek has the same fish assemblage as Bucks Creek, rainbow trout
and brown trout, with no special status aquatic species. As with Bucks Creek,
brown trout dominate the fish community closer to the dam, while rainbow trout
are dominant at the more downstream end of the reach. Grizzly Creek
receives flow from Lower Bucks Lake when the Grizzly Powerhouse is in
operation, but both the Grizzly powerhouse and the tunnel will be offline, and
so flow from Lower Bucks Lake will not be available to supplement natural
inflow. A flow reduction below the current MIF of 8 cfs in May and June is
unlikely to occur based on either the unimpaired flow analysis done as part of
relicensing or a review of hydrology since 2000. Flow reductions below the
current MIF of 6 cfs from July 1 through October 31 are more likely to occur,
with naturally occurring inflows having dropped below 6 cfs during the summer
months in 10 of 19 years between 2000 and 2018, with flows dropping to less
than 2 cfs for some months in three of those years. However, those years had
varied water year types, one each in above normal, below normal and critical,
and other years with the same water types had higher flows. Therefore, it is
not possible to predict what naturally occurring inflow might be in any given
year.
PG&E is proposing to release the full natural inflow of Grizzly Creek below
Grizzly Forebay (i.e., inflow equals outflow), so fish would experience the same
natural conditions they would if the project were not present. However, during
normal project operation, the natural flow regime below Grizzly Forebay is
supplemented under some conditions by water diverted from Lower Bucks
Lake. This ability to supplement flows would not be available with the proposed
work, as both the Grizzly Powerhouse and tunnel would be offline for
maintenance and repairs and the source flows from Lower Bucks will be
unavailable during the Lower Bucks Lake dewatering. The impacts of flow
reductions to less than 6 cfs would depend on the water year type and the
magnitude and duration of the variance. For short-term variations of minor
magnitude, that would be experienced under normal or wetter water years, fish
would move into deeper habitat to adapt to the flow change, and few impacts
would be anticipated. Under longer-term variations of greater magnitude, as
would be experienced under dry water years, the impacts would increase.
Instream flow models for Grizzly Creek (TRPA 1991) indicate that flows of 2
cfs provide 8 to 12% less habitat for brown trout lifestages (fry, juvenile and
adult) than flows of 6 cfs based on 50% exceedance condition accretion flows
downstream of the dam in September (selected as a worst-case month). For
rainbow trout, this flow reduction would reduce habitat by 14 to 29%. This
reduction in habitat would crowd fish into a smaller area but is unlikely to result
in large scale fish mortality. If flows were reduced to zero cfs, habitat for brown
trout would be reduced by 17 to 23% and for rainbow trout by 26 to 56%. This
might result in more mortality for rainbow trout, but the populations of both
species would persist.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour MIF
requirement is likely negligible. This variance would account for lags between
reservoir elevation monitoring and adjustment of pumping rates to match outflow to
inflow during May through October 2020, without requiring a variance report for
each such occurrence. Trout would not be affected by such short-term variations in
flow.
PG&E requests your review and concurrence as soon as possible. Thank you for your timely
attention to this matter. All concurrence emails and/or letters we receive will be included in our
filing with FERC.
PG&E staff is available to discuss this variance request in more detail, if needed. If you have any
questions, please call:
General Questions – Jamie Visinoni, 530-215-6676
Project/Engineering – Jeff Jukkola, 530-624-8640
Biological Review – Larry Wise, 925-415-6353
Thank you,
Jamie Visinoni
Hydro License Coordinator | Power Generation
Pacific Gas and Electric Company
d: N/A | m: (530) 215-6676 | e: jamie.visinoni@pge.com
Pacific Gas and Electric Company (PG&E) plans to perform extensive repairs and
maintenance in 2020 at Lower Bucks Lake Dam and Grizzly Forebay Dam, part of
PG&E’s Bucks Creek Hydroelectric Project, Federal Energy Regulatory Commission
(FERC) Project No. 619. PG&E is requesting U.S. Forest Service (Forest Service),
California Department of Fish and Wildlife (CDFW), and the U.S. Fish and Wildlife
review and approval to temporarily reduce the minimum instream flows (MIF) and
minimum lake elevation to levels below those required under Article 13 for Bucks Creek
and Grizzly Creek. The request for flow reduction may not be needed but is being
submitted as a precautionary measure to ensure construction crews safe access to the
perform work on and around the dams.
Scope of Construction and Schedule
Lower Bucks Dam Work – In a letter dated December 17, 2014, FERC requested that
PG&E address several follow-up action items from the 2014 Dam Safety Inspection for
the Project. The letter stated that “Severe spalling and surface delamination of concrete
has occurred on the downstream abutments and downstream face of the \[Lower Bucks\]
dam. The condition should be carefully evaluated, and a repair plan developed.” PG&E
performed a condition assessment in 2016 and 2017 which resulted in the installation of
a geomembrane liner as one of the recommended repairs. Engineering is underway to
address the downstream lining per the 2014 direction.
The proposed project includes installation of a geomembrane liner on the upstream face
of the dam to reduce seepage and protect the dam from further freeze-thaw damage. To
install the liner, Lower Bucks Lake will be completely dewatered, and sediment will be
excavated adjacent to the dam to support the geomembrane installation. The initial
drawdown of Lower Bucks Lake will be conducted using a combination of pumping,
drafting water through the Grizzly Intake, and exercising the Lower Bucks Dam low level
outlet (LLO) until reservoir elevation falls below the minimum operating elevation of the
Grizzly Intake. The remaining pool of water in the reservoir will be dewatered using a
combination of the LLO and/or pumps. The drawdown and dewatering of Lower Bucks
Lake, sediment removal, and geomembrane installation effort will be coordinated with a
multi-unit outage scheduled for May to November 2020.
During the dewatered period, instream flows downstream of Lower Bucks Dam into
Bucks Creek will be satisfied by either: 1) the Milk Ranch Conduit (MRC), which usually
flows directly into Lower Bucks Lake but may be re-routed downstream of Lower Bucks
Dam, or 2) a bypass gravity flow system from Bucks (Storage) Lake LLO that will be
routed downstream of Lower Bucks Dam. The ideal phasing would be to start with MRC
into Bucks Creek utilizing flows from the various diversions; once those flows begin to
recede and approach the Bucks Creek required MIF, the system will be switched over to
the Bucks Storage LLO gravity system; then finally towards the end of the work, based
on a calculation of storage volume in Three Lakes, the system would by switched back
to MRC for the remainder of the work. This approach provides a redundancy in the
system for the duration of work.
Grizzly Forebay/Dam Work – Logs and woody debris build up at the Grizzly Forebay
overpour spillway during the wet season. Some of these have become waterlogged and
have sunk, accumulating upstream of the dam. This project proposes to wet dredge
woody debris and accumulated sediment from the reservoir adjacent to the LLO and the
Bucks Powerhouse intake structure. This accumulated material impacts both the intake
and LLO.
The sediment drawn into the intake is causing deterioration to the Bucks Powerhouse
runners creating increased maintenance. Debris build up may also be drawn into the
LLO which could affect its reliability to provide required instream flow releases
downstream of the structure. PG&E has identified May to November 2020 as the
potential outage window for the dual Bucks/Grizzly Powerhouses to support this work.
License Requirement
License Article 13 requires, in part, that PG&E maintain a minimum instream flow in
Bucks Creek below the Lower Bucks Dam and from Grizzly Forebay to Grizzly
Creek. Minimum streamflows are:
(1) Minimum streamflows from Lower Bucks Lake to Bucks Creek:
Period Flow, in cubic feet
per second (cfs)
November 1 through April 304 cfs
May 1 through June 30* 8 cfs
July 1 through October 31 6 cfs
(2) Minimum streamflows from Grizzly Forebay to Grizzly Creek:
Period Flow, in cubic feet
per second (cfs)
November 1 through April 30 4 cfs
May 1 through June 30* 8 cfs
July 1 through October 31 6 cfs
License Article 13 also requires PG&E maintain a minimum water elevation for all lakes.
The minimum elevation for Lower Bucks Lake is 4,966 feet.
Schedule for Temporary Flow and Reservoir Elevation Variances
Bucks Creek Variance
To ensure safe and efficient constructability, cost, and schedule, PG&E is seeking a
stst
temporary flow variance of 6 cfs from June 1through July 1.A flow of 6 cfs will be
achieved through the bypass piping system from Bucks Lake to Bucks Creek and may
be augmented with water from the Milk Ranch Conduit (MRC), if available. If enough
water is available through the MRC, PG&E expects to be able to achieve the License
required MIF of 8 cfs.
In addition to the flow variance, PG&E requests the 24-hour average of the flow (mean
daily flow) be used for minimum stream flow measurement and reporting for May 1
through November 1, 2020. PG&E will average all the instantaneous readings from
midnight of one day to 11:59 pm of the next day. Flow monitoring will be achieved by
installing a temporary flow meter on the bypass piping system.
Grizzly Creek Variance
To support the debris and sediment removal work, a pump system will be deployed to
maintain a consistent lake elevation. PG&E is seeking a variance from July 1 through
November 1, 2020 to allow flow releases below Grizzly Dam to match the natural inflow
into the reservoir, which may drop below the license required 6 cfs depending on water
year.
In addition to the flow variance, PG&E requests the 24-hour average of the flow (mean
daily flow) be used for minimum instream flow measurement and reporting for July 1
through November 1, 2020. PG&E will average all the instantaneous readings from
midnight of one day to 11:59 pm of the next day. Flows will be monitored and recorded
at NF22. Adjustments to pumping will be made daily to maintain the reservoir elevation,
whereby generally matching inflow to outflow.
Lower Bucks Lake Water Elevation Variance
PG&E requests a variance to the minimum elevation for Lower Bucks Lake, the lake will
be completely dewatered for the majority of the outage between May 1 to November 1 of
2020.
Biological Resource Evaluation
Bucks Creek
Minimum Instream Flow Variance
In the event of a very dry year that results in June flows of less than 2 cfs in the MRC,
flow in Lower Bucks Creek could drop below the MIF of 8 cfs, to as low as 6 cfs. Based
on surveys conducted during relicensing (PG&E 2018), Lower Bucks Creek is inhabited
by rainbow and brown trout, with brown trout being dominant at the upstream end of the
creek, and rainbow trout being dominant further downstream. There are no special
status aquatic species known from this stream. All lifestages of rainbow trout (adult,
juvenile, fry and spawning) are likely to be present in June, although spawning may be
complete by that time, and alI lifestages of brown trout, except spawning would be
present.
An instream flow study was prepared for Lower Bucks Creek (Thomas R. Payne and
Associates 1991. Instream Flow Study for Milk Ranch, Bucks, and Grizzly Creeks.
Bucks Creek Project (FERC 619). Prepared for PG&E). Based on this study, a flow
reduction from 8 cfs to 6 cfs would result in a reduction in habitat for rainbow trout of 11
% for fry, 15% for juveniles, and 6% for adults. Spawning habitat would be reduced by
45%, if spawning has not completed by that time. Habitat reductions for brown trout
would generally be less, ranging from 3% for juveniles to 7% for adults. For all lifestages
except rainbow trout spawning, the habitat reduction would be minor and would adjust
the timing of the License required MIF reduction from 8 to 6 cfs forward by up to 4
weeks. This would have minimal to no effect on the abundance or health of these
fisheries. For rainbow trout spawning, the effect might be more pronounced if redds
were still active at the time of the flow reduction, and if redds were placed relatively high
in the channel.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour MIF
requirement is likely negligible. This variance would allow flows to drop below 6 cfs
during a brief period (a couple of hours during any given day) during May through
October 2020, without requiring a variance report for each such occurrence. Trout
would likely not be affected by such short-term variations in flow.
Lower Bucks Lake Minimum Pool Variance
As described above, Lower Bucks Lake will be completely dewatered. PG&E is working
with the California Department of Fish and Wildlife (CDFW) to develop a restocking
plan that will be implemented after the lake refills. A fish rescue was not considered a
viable option during the lake’s drawdown due to steep terrain, safety concerns and
limited access. . This plan will be focused on restocking rainbow trout over a range of
sizes including stocking trophy-sized rainbow trout into Lower Bucks Lake to jump-start
the fishery for the 2021 fishing and camping season. Bucks Lake supports the same
species of fish as Lower Bucks Lake. Other fish species will gradually recolonize Lower
Bucks Lake, but relicensing studies found that entrainment rates are low in Bucks Lake,
and therefore, this is expected to take several years.
Lower Bucks Lake and the portion of Bucks Creek immediately downstream of Lower
Bucks Dam are within designated critical habitat for Sierra Nevada yellow-legged frog
SNYLF), listed as endangered under the Endangered Species Act. Surveys during
relicensing did not identify any occurrences of this species in either of these areas. The
nearest SNYLF observation was in Bear Ravine located in a drainage about 0.3 miles
north of Lower Bucks Dam. The flow and water level variances associated with this
project would not adversely affect habitat values for this species. A separate biological
assessment is being prepared for submission to the U.S. Fish and Wildlife Service
regarding the potential impacts of this project on SNYLF and its habitat, but no impacts
are anticipated.
Grizzly Creek
Flow Variance
Grizzly Creek has the same fish assemblage as Bucks Creek, rainbow trout and brown
trout, with no special status aquatic species. As with Bucks Creek, brown trout dominate
the fish community closer to the dam, while rainbow trout are dominant at the more
downstream end of the reach. Grizzly Creek receives flow from Lower Bucks Lake when
the Grizzly Powerhouse is in operation, but both the Grizzly powerhouse and the tunnel
will be offline, and so flow from Lower Bucks Lake will not be available to supplement
natural inflow. A flow reduction below the current MIF of 8 cfs in May and June is
unlikely to occur based on either the unimpaired flow analysis done as part of relicensing
or a review of hydrology since 2000. Flow reductions below the current MIF of 6 cfs
from July 1 through October 31 are more likely to occur, with naturally occurring inflows
having dropped below 6 cfs during the summer months in 10 of 19 years between 2000
and 2018, with flows dropping to less than 2 cfs for some months in three of those years.
However, those years had varied water year types, one each in above normal, below
normal and critical, and other years with the same water types had higher
flows. Therefore, it is not possible to predict what naturally occurring inflow might be in
any given year.
PG&E is proposing to release the full natural inflow of Grizzly Creek below Grizzly
Forebay (i.e., inflow equals outflow), so fish would experience the same natural
conditions they would if the project were not present. However, during normal project
operation, the natural flow regime below Grizzly Forebay is supplemented under some
conditions by water diverted from Lower Bucks Lake. This ability to supplement flows
would not be available with the proposed work, as both the Grizzly Powerhouse and
tunnel would be offline for maintenance and repairs and the source flows from Lower
Bucks will be unavailable during the Lower Bucks Lake dewatering. The impacts of flow
reductions to less than 6 cfs would depend on the water year type and the magnitude
and duration of the variance. For short-term variations of minor magnitude, that would
be experienced under normal or wetter water years, fish would move into deeper habitat
to adapt to the flow change, and few impacts would be anticipated. Under longer-term
variations of greater magnitude, as would be experienced under dry water years, the
impacts would increase.
Instream flow models for Grizzly Creek (TRPA 1991) indicate that flows of 2 cfs provide
8 to 12% less habitat for brown trout lifestages (fry, juvenile and adult) than flows of 6 cfs
based on 50% exceedance condition accretion flows downstream of the dam in
September (selected as a worst-case month). For rainbow trout, this flow reduction
would reduce habitat by 14 to 29%. This reduction in habitat would crowd fish into a
smaller area but is unlikely to result in large scale fish mortality. If flows were reduced to
zero cfs, habitat for brown trout would be reduced by 17 to 23% and for rainbow trout by
26 to 56%. This might result in more mortality for rainbow trout, but the populations of
both species would persist.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour MIF
requirement is likely negligible. This variance would account for lags between reservoir
elevation monitoring and adjustment of pumping rates to match outflow to inflow during
May through October 2020, without requiring a variance report for each such
occurrence. Trout would not be affected by such short-term variations in flow.
From:Bartoo, Aondrea
To:Visinoni, Jamie
Cc:Lind, Amy -FS; Edlund, Leslie - FS; Lawson, Beth@Wildlife; Lose, Sarah@Wildlife; Joseph, Matthew
Subject:Re: \[EXTERNAL\] Updated Review/Approval Request - Bucks Creek Project, FERC No. 619 - Flow and Lake
Elevation Variance
Date:Thursday, October 10, 2019 7:54:53 AM
*****CAUTION: This email was sent from an EXTERNAL source. Think before clicking links
or opening attachments.*****
The USFWS has reviewed the variance requests for the Lower Bucks Lake
Geomembrane retrofit project. The USFWS concurs with all portions of the requests,
with the one exception of dewatering Lower Bucks Lake. As this portion of the project
is in critical habitat for the Sierra Nevada yellow-legged frog, we would need to analyze
the potential impacts to the species through consultation under Section 7 of the ESA
prior to providing concurrence. We look forward to future collaboration for the
project and are available for any follow-up discussions.
I appreciate PG&E's patience while waiting for this response.
Thank you!
On Mon, Aug 26, 2019 at 12:18 PM Visinoni, Jamie <JNVS@pge.com> wrote:
Hello All,
Thank you for sharing your questions and concerns regarding the Bucks Creek variance
request when we met last week. We have provided more detail on the water management
approach in our variance request, please see the updated request below:
Pacific Gas and Electric Company (PG&E) plans to perform extensive repairs
and maintenance in 2020 at Lower Bucks Lake Dam and Grizzly Forebay
Dam, part of PG&E’s Bucks Creek Hydroelectric Project, Federal Energy
Regulatory Commission (FERC) Project No. 619. PG&E is requesting U.S.
Forest Service (Forest Service), California Department of Fish and Wildlife
(CDFW), and the U.S. Fish and Wildlife Department review and approval to
temporarily reduce the minimum instream flows (MIF) and minimum lake
elevation to levels below those required under Article 13 for Bucks Creek and
Grizzly Creek. The request for flow reduction may not be needed but is
being submitted as a precautionary measure to ensure construction crews
safe access to the perform work on and around the dams.
Scope of Construction and Schedule
Lower Bucks Dam Work – In a letter dated December 17, 2014, FERC
requested that PG&E address several follow-up action items from the 2014
Dam Safety Inspection for the Project. The letter stated that “Severe spalling
and surface delamination of concrete has occurred on the downstream
abutments and downstream face of the \[Lower Bucks\] dam. The condition
should be carefully evaluated, and a repair plan developed.” PG&E
performed a condition assessment in 2016 and 2017 which resulted in the
installation of a geomembrane liner as one of the recommended repairs.
Engineering is underway to address the downstream lining per the 2014
direction.
The proposed project includes installation of a geomembrane liner on the
upstream face of the dam to reduce seepage and protect the dam from
further freeze-thaw damage. To install the liner, Lower Bucks Lake will be
completely dewatered, and sediment will be excavated adjacent to the dam
to support the geomembrane placement access. The initial drawdown of
Lower Bucks Lake will be conducted using a combination of pumping,
drafting water through the Grizzly Intake, and exercising the Lower Bucks
Dam low level outlet (LLO) until reservoir elevation falls below the minimum
operating elevation of the Grizzly Intake. The remaining pool of water in the
reservoir will be dewatered using a combination of the LLO and/or pumps.
The drawdown and dewatering of Lower Bucks Lake, sediment removal, and
geomembrane installation effort will be coordinated with a multi-unit outage
scheduled for May to November 2020.
During the dewatered period, instream flows downstream of Lower Bucks
Dam into Bucks Creek will be satisfied by either: 1) the Milk Ranch Conduit
(MRC), which usually flows directly into Lower Bucks Lake but may be re-
routed downstream of Lower Bucks Dam, or 2) a bypass gravity flow system
from Bucks (Storage) Lake LLO that will be routed downstream of Lower
Bucks Dam. The ideal phasing would be to start with MRC into Bucks Creek
utilizing flows from the various diversions; once those flows begin to recede
and approach the Bucks Creek required MIF, the system will be switched
over to the Bucks Storage LLO gravity system; then finally towards the end of
the work, based on a calculation of storage volume in Three Lakes, the
system would by switched back to MRC for the remainder of the work. This
approach provides a redundancy in the system for the duration of work.
Grizzly Forebay/Dam Work – Logs and woody debris build up at the Grizzly
Forebay overpour spillway during the wet season. Some of these have
become waterlogged and have sunk, accumulating upstream of the dam.
This project proposes to wet dredge woody debris and accumulated
sediment from the reservoir adjacent to the LLO and the Bucks Powerhouse
intake structure. This accumulated material impacts both the intake and LLO.
The sediment drawn into the intake is causing deterioration to the Bucks
Powerhouse runners creating increased maintenance. Debris build up may
also be drawn into the LLO which could affect its reliability to provide
required instream flow releases downstream of the structure. PG&E has
identified May to November 2020 as the potential outage window for the dual
Bucks/Grizzly Powerhouses to support this work.
License Requirement
License Article 13 requires, in part, that PG&E maintain a minimum instream
flow in Bucks Creek below the Lower Bucks Dam and from Grizzly Forebay
to Grizzly Creek. Minimum streamflows are:
(1) Minimum streamflows from Lower Bucks Lake to Bucks Creek:
Flow, in cubic feet
Period per second (cfs)
November 1 through April 30 4 cfs
May 1 through June 30* 8 cfs
July 1 through October 31 6 cfs
(2) Minimum streamflows from Grizzly Forebay to Grizzly Creek:
Flow, in cubic feet
Period per second (cfs)
November 1 through April 30 4 cfs
May 1 through June 30* 8 cfs
July 1 through October 316 cfs
License Article 13 also requires PG&E maintain a minimum water elevation
for all lakes. The minimum elevation for Lower Bucks Lake is 4,966 feet.
Schedule for Temporary Flow and Reservoir Elevation Variances
Variance
Bucks Creek
To ensure safe and efficient constructability, cost, and schedule, PG&E is
stst
seeking a temporary flow variance of 6 cfs from June 1 through July 1. A
flow of 6 cfs will be achieved through the bypass piping system from Bucks
Lake to Bucks Creek and may be augmented with water from the Milk Ranch
Conduit (MRC), if available. If enough water is available through the MRC,
PG&E expects to be able to achieve the License required MIF of 8 cfs.
In addition to the flow variance, PG&E requests the 24-hour average of the
flow (mean daily flow) be used for minimum stream flow measurement and
reporting for May 1 through November 1, 2020. PG&E will average all the
instantaneous readings from midnight of one day to 11:59 pm of the next
day. Flow monitoring will be achieved by installing a temporary flow meter
on the bypass piping system.
Grizzly Creek Variance
To support the debris and sediment removal work, a pump system will be
deployed to maintain a consistent lake elevation. PG&E is seeking a
variance from July 1 through November 1, 2020 to allow flow releases below
Grizzly Dam to match the natural inflow into the reservoir, which may drop
below the license required 6 cfs depending on water year.
In addition to the flow variance, PG&E requests the 24-hour average of the
flow (mean daily flow) be used for minimum instream flow measurement and
reporting for July 1 through November 1, 2020. PG&E will average all the
instantaneous readings from midnight of one day to 11:59 pm of the next
day. Flows will be monitored and recorded at NF22. Adjustments to pumping
will be made daily to maintain the reservoir elevation, whereby generally
matching inflow to outflow.
Lower Bucks Lake Water Elevation Variance
PG&E requests a variance to the minimum elevation for Lower Bucks Lake,
the lake will be completely dewatered for the majority of the outage between
May 1 to November 1 of 2020.
Biological Resource Evaluation
Bucks Creek
Minimum Instream Flow Variance
In the event of a very dry year that results in June flows of less than 2 cfs in
the MRC, flow in Lower Bucks Creek could drop below the MIF of 8 cfs, to as
low as 6 cfs. Based on surveys conducted during relicensing (PG&E 2018),
Lower Bucks Creek is inhabited by rainbow and brown trout, with brown trout
being dominant at the upstream end of the creek, and rainbow trout being
dominant further downstream. There are no special status aquatic species
known from this stream. All lifestages of rainbow trout (adult, juvenile, fry
and spawning) are likely to be present in June, although spawning may be
complete by that time, and alI lifestages of brown trout, except spawning
would be present.
An instream flow study was prepared for Lower Bucks Creek (Thomas R.
Payne and Associates 1991. Instream Flow Study for Milk Ranch, Bucks,
and Grizzly Creeks. Bucks Creek Project (FERC 619). Prepared for PG&E).
Based on this study, a flow reduction from 8 cfs to 6 cfs would result in a
reduction in habitat for rainbow trout of 11 % for fry, 15% for juveniles, and
6% for adults. Spawning habitat would be reduced by 45%, if spawning has
not completed by that time. Habitat reductions for brown trout would
generally be less, ranging from 3% for juveniles to 7% for adults. For all
lifestages except rainbow trout spawning, the habitat reduction would be
minor and would adjust the timing of the License required MIF reduction from
8 to 6 cfs forward by up to 4 weeks. This would have minimal to no effect on
the abundance or health of these fisheries. For rainbow trout spawning, the
effect might be more pronounced if redds were still active at the time of the
flow reduction, and if redds were placed relatively high in the channel.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour
MIF requirement is likely negligible. This variance would allow flows to drop
below 6 cfs during a brief period (a couple of hours during any given day)
during May through October 2020, without requiring a variance report for
each such occurrence. Trout would not be affected by such short-term
variations in flow.
Lower Bucks Lake Minimum Pool Variance
As described above, Lower Bucks Lake will be completely dewatered. PG&E
is working with the California Department of Fish and Wildlife (CDFW) to
develop a plan for conducting a fish rescue and to develop a restocking
plan. To the extent a fish rescue may safely be implemented, PG&E does
not expect the fish rescue to provide a biological/environmental benefit. Fish
that are rescued will likely be moved to Bucks Lake (Storage), where they
would be available to anglers, but will not appreciably increase fish
populations (or angler catch-per-unit-effort) in Bucks Lake given the much
smaller size of Lower Bucks Lake and the proportion of fish the crews will
likely be able to safely rescue. All fish that are not rescued are expected to
perish. PG&E and CDFW are also working together to develop a restocking
plan for Lower Bucks Lake that will be implemented after the lake refills. This
plan will be focused on restocking rainbow trout over a range of sizes. Bucks
Lake supports the same species of fish as Lower Bucks Lake. Other fish
species will gradually recolonize Lower Bucks Lake, but relicensing studies
found that entrainment rates are low in Bucks Lake, and therefore, this is
expected to take several years.
Lower Bucks Lake and the portion of Bucks Creek immediately downstream
of Lower Bucks Dam are within designated critical habitat for Sierra Nevada
yellow-legged frog SNYLF), listed as endangered under the Endangered
Species Act. Surveys during relicensing did not identify any occurrences of
this species in either of these areas. The nearest SNYLF observation was in
Bear Ravine located in a drainage about 0.3 miles north of Lower Bucks
Dam. The flow and water level variances associated with this project would
not adversely affect habitat values for this species. A separate biological
assessment is being prepared for submission to the U.S. Fish and Wildlife
Service regarding the potential impacts of this project on SNYLF and its
habitat, but no impacts are anticipated.
Grizzly Creek
Flow Variance
Grizzly Creek has the same fish assemblage as Bucks Creek, rainbow trout
and brown trout, with no special status aquatic species. As with Bucks
Creek, brown trout dominate the fish community closer to the dam, while
rainbow trout are dominant at the more downstream end of the reach.
Grizzly Creek receives flow from Lower Bucks Lake when the Grizzly
Powerhouse is in operation, but both the Grizzly powerhouse and the tunnel
will be offline, and so flow from Lower Bucks Lake will not be available to
supplement natural inflow. A flow reduction below the current MIF of 8 cfs in
May and June is unlikely to occur based on either the unimpaired flow
analysis done as part of relicensing or a review of hydrology since 2000.
Flow reductions below the current MIF of 6 cfs from July 1 through October
31 are more likely to occur, with naturally occurring inflows having dropped
below 6 cfs during the summer months in 10 of 19 years between 2000 and
2018, with flows dropping to less than 2 cfs for some months in three of
those years. However, those years had varied water year types, one each in
above normal, below normal and critical, and other years with the same
water types had higher flows. Therefore, it is not possible to predict what
naturally occurring inflow might be in any given year.
PG&E is proposing to release the full natural inflow of Grizzly Creek below
Grizzly Forebay (i.e., inflow equals outflow), so fish would experience the
same natural conditions they would if the project were not present. However,
during normal project operation, the natural flow regime below Grizzly
Forebay is supplemented under some conditions by water diverted from
Lower Bucks Lake. This ability to supplement flows would not be available
with the proposed work, as both the Grizzly Powerhouse and tunnel would be
offline for maintenance and repairs and the source flows from Lower Bucks
will be unavailable during the Lower Bucks Lake dewatering. The impacts of
flow reductions to less than 6 cfs would depend on the water year type and
the magnitude and duration of the variance. For short-term variations of
minor magnitude, that would be experienced under normal or wetter water
years, fish would move into deeper habitat to adapt to the flow change, and
few impacts would be anticipated. Under longer-term variations of greater
magnitude, as would be experienced under dry water years, the impacts
would increase.
Instream flow models for Grizzly Creek (TRPA 1991) indicate that flows of 2
cfs provide 8 to 12% less habitat for brown trout lifestages (fry, juvenile and
adult) than flows of 6 cfs based on 50% exceedance condition accretion
flows downstream of the dam in September (selected as a worst-case
month). For rainbow trout, this flow reduction would reduce habitat by 14 to
29%. This reduction in habitat would crowd fish into a smaller area but is
unlikely to result in large scale fish mortality. If flows were reduced to zero
cfs, habitat for brown trout would be reduced by 17 to 23% and for rainbow
trout by 26 to 56%. This might result in more mortality for rainbow trout, but
the populations of both species would persist.
Flow Averaging Period Variance
The impact of moving from an instantaneous MIF requirement to a 24-hour
MIF requirement is likely negligible. This variance would account for lags
between reservoir elevation monitoring and adjustment of pumping rates to
match outflow to inflow during May through October 2020, without requiring a
variance report for each such occurrence. Trout would not be affected by
such short-term variations in flow.
PG&E requests your review and concurrence as soon as possible. Thank you for your
timely attention to this matter. All concurrence emails and/or letters we receive will be
included in our filing with FERC.
PG&E staff is available to discuss this variance request in more detail, if needed. If you have
any questions, please call:
General Questions – Jamie Visinoni, 530-215-6676
Project/Engineering – Jeff Jukkola, 530-624-8640
Biological Review – Larry Wise, 925-415-6353
Thank you,
Jamie Visinoni
Hydro License Coordinator | Power Generation
Pacific Gas and Electric Company
d: N/A | m: (530) 215-6676 | e: jamie.visinoni@pge.com
--
A. Leigh Bartoo
Fish and Wildlife Biologist
Bay-Delta Fish and Wildlife Office
U.S. Fish and Wildlife Service
650 Capitol Mall, 8-300
Sacramento, CA 95814
916-930-5621