FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
(415) 369-3300 Office (415) 369-3322 Facsimile
February 18, 2020
In reply refer to:
Project No. 2088-CA
Mr. Rath Moseley
General Manager
South Feather Water and Power Agency
2310 Oro-Quincy Highway
Oroville, CA 95965
Re: Notification of 2019 and 2020 Penstock Dewatering Schedules
Dear Mr. Moseley:
This is in response to a December 13, 2019 letter from Ms. Kristen McKillop and
Mr. Matt Colwell that notified our office that the 2019 annual non-emergency
inspection/maintenance of the Kelly Ridge and Miners Ranch Conduit penstocks was
postponed until January 2020, and the planned 2020 inspections are scheduled for
November 2-13, 2020. The letter also provided the planned 2020 inspection schedule for
the Woodleaf, Forbestown, and Sly Creek Powerhouse penstocks, which are part of the
South Feather Power Project, FERC No. 2088.
Your request to postpone the 2019 inspection of Kelly Ridge and Miners Ranch
Conduit penstocks until January 2020, and the proposed schedules to conduct the 2020
inspections of the penstocks by the dates listed in the letter are acceptable. We appreciate
any questions, please contact Mr. Ricardo Galdamez at (415) 369-3310.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer