From:Schuman, Amy
To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Kimmelshue, Tod;
Lambert, Steve;Lucero, Debra;McCracken, Shari;Paulsen, Shaina;Pickett, Andy;Ring, Brian;Ritter, Tami;
Rodas, Amalia;Sweeney, Kathleen;Teeter, Doug
Subject:BOS Correspondence - FW: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas
and Electric Company,et al.
Date:Thursday, January 28, 2021 3:18:42 PM
Please see the email below from FERC.
Amy Schuman
Associate Clerk of the Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
O: 530.552.3300 |D: 530.552.3308 | F: 530.538.7120
Twitter | Facebook | YouTube | Pinterest
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Thursday, January 28, 2021 2:45 PM
Subject: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric
Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 1/28/2021, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC),
Washington D.C.:
Filer: Pacific Gas and Electric Company
No Organization Found (as Agent)
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits Grizzly Forebay Dam-Low Level Outlet Modification
Final Construction Report for Creek-Grizzly Hydroelectric Project under P-619.
To view the document for this Filing, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20210128-
5207__;!!KNMwiTCp4spf!Uvs8p_P44O5N-I-
uXDxPWyOb_IZ4YBSCilQXLpSuH8RpiQz_TXbZlnaVL32yOTxnltUYT9U0rAc$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!Uvs8p_P44O5N-I-
uXDxPWyOb_IZ4YBSCilQXLpSuH8RpiQz_TXbZlnaVL32yOTxnltUYAeW9B9A$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!Uvs8p_P44O5N-I-
uXDxPWyOb_IZ4YBSCilQXLpSuH8RpiQz_TXbZlnaVL32yOTxnltUYNcXRdkk$
or for phone support, call 866-208-3676.
245 Market Street
tƚǞĻƩ DĻƓĻƩğƷźƚƓ
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
January 28, 2021
San Francisco, CA 94177
Via Electronic Submittal (E-File)
Hard copy to follow via U.S. Mail
Mr. Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek-Grizzly Hydroelectric Project, No. 619-CA
Grizzly Forebay Dam Low Level Outlet Modification
Final Construction Report
ENCLOSURE CONTAINS CRITICAL ENERGY INFRASTRUCTURE
INFORMATION (CUI//CEII) - DO NOT RELEASE
Dear Mr. Blackett:
In a letter to Pacific Gas and Electric Company (PG&E), dated May 8, 2020, the Federal Energy
Regulatory Commission (FERC) granted authorization for construction of PG&E Grizzly Forebay
Dam Low Level Outlet Modification project, part of the Bucks Creek-Grizzly Hydroelectric Project,
FERC No. 619.
Construction of the Grizzly Forebay Dam Low Level Outlet Modification project was completed on
September 2, 2020. Enclosed you will find the Final Construction Report which includes as-built
drawings and verified construction certifications from the Design Engineer, Quality Control Manager,
and Licensee (PG&E).
Due to the ongoing shelter-in-place orders issued by the State of California in response to the
COVID-19 pandemic, non-essential PG&E staff are currently working remotely, and hard copy filings
are not possible at this time. If you require a hard copy of the letter and/or enclosure, please provide
this request in your response and copies will be sent after the shelter-in-place restrictions have been
lifted and PG&E staff have returned to their normal work locations.
Should you have questions, license coordinator, Jamie Visinoni, at (530)
215-6676.
Sincerely,
Teri Smyly
Manager, FERC Compliance
Enclosure: CUI//CEII DO NOT RELEASE
1. Final Construction Report