HomeMy WebLinkAbout02.01.21 BOS Correspondence - FW_ Request for Delay of Action_Extension of Time submitted in FERC P-2105-000,et al. by Pacific Gas and Electric Company,et al.
From:Schuman, Amy
To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Kimmelshue, Tod;Lambert, Steve;Lucero, Debra;McCracken, Shari;Paulsen, Shaina;Pickett, Andy;Ring,
Brian;Ritter, Tami;
Rodas, Amalia;Sweeney, Kathleen;Teeter, Doug
Subject:BOS Correspondence - FW: Request for Delay of Action/Extension of Time submitted in FERC P-2105-000,et al. by Pacific Gas and Electric Company,et al.
Date:Monday, February 1, 2021 9:01:52 AM
Please see the email below from FERC.
Amy Schuman
Associate Clerk of the Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
O: 530.552.3300 |D: 530.552.3308 | F: 530.538.7120
Twitter | Facebook | YouTube | Pinterest
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Monday, February 1, 2021 6:05 AM
Subject: Request for Delay of Action/Extension of Time submitted in FERC P-2105-000,et al. by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 2/1/2021, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas and Electric Company (as Agent)
Docket(s): P-2105-000
P-2155-001
P-2310-000
P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Request for Delay of Action/Extension of Time
Description: Pacific Gas and Electric Company submits Status Update and Request for Extension of Time under P-2310, et. al.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20210201-
5020__;!!KNMwiTCp4spf!QXrPRdFbr2CVh8HOpeShOV2YEmDEhWbYos8m8PEynpqoCW3t2dHWsR_y6cn_UGKGQVrfwarglGo$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!QXrPRdFbr2CVh8HOpeShOV2YEmDEhWbYos8m8PEynpqoCW3t2dHWsR_y6cn_UGKGQVrfyBPgDx8$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!QXrPRdFbr2CVh8HOpeShOV2YEmDEhWbYos8m8PEynpqoCW3t2dHWsR_y6cn_UGKGQVrfEBpak_s$
or for phone support, call 866-208-3676.
245 Market Street
tƚǞĻƩ DĻƓĻƩğƷźƚƓ
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
January 29, 2021
Via Electronic Submittal (E-File)
Mr. Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
Re: Status Update and Request for Extension of Time
Drum-Spaulding Hydroelectric Project, FERC No. 2310
DeSabla-Centerville Hydroelectric Project, FERC No. 803
Upper North Fork Feather River Hydroelectric Project, FERC No. 2105
Chili Bar Hydroelectric Project, FERC No. 2155
Dear Mr. Blackett:
In accordance with ongoing efforts for
continuous improvement in achieving timely responses to filings requested in numerous
letter
presents in Enclosure 1, an update on the status of efforts to address near-term coming
due items. The status of efforts for items for not yet resolved includes Extension of Time
(EOT) requests.
Should you have any technical questions concerning this matter, please contact PG&E
chief dam safety engineer, Mr. Dave Ritzman, at (415) 264-1795. For general questions,
please contact Manager of FERC Compliance, Teri Smyly, at (415) 624-4218.
Sincerely,
Teri Smyly
Manager, FERC Compliance
Enclosure: Status Update and Extension of Time Request
Time
Date for
3/15/20211/31/20221/31/20225/30/20215/30/20214/30/20216/30/20218/31/20218/31/2021
Requested
Extension of
PG&E Status for
Extension of Time Request
Developing a plan and schedule to from their 12/16/2020 letter. Evaluating potential alternatives for reducing inflows and dewatering the gallery.Completing investigation on waterproofing
the gallery access doors as part of the gallery study proposed in relation to R-4. New ladder rung installed on the spillway access ladder and will provide photos. Rocks in the spillway
channel broken up and will provide photos. Report preparation is in progress. Completed the hydraulic modeling and analysis of the spillway channel and are currently reviewing the
results of the analysis with the ICs. Currently working on the design package for the construction project to complete erosion protection improvements for the spillway channel. Currently
working on the design package for the construction project to remove the trees during construction of the erosion protection.
1/13/20218/27/20208/27/20205/18/20203/29/20192/19/20192/19/2019
12/30/201912/30/2019
Most Recent
Correspondence
Date
01/30/202101/31/202101/31/202101/31/202101/31/202102/09/202102/28/202102/28/202102/28/2021
Current Due
830083828972828972830083830083824709829193830152830152
Dam Number
ENCLOSURE 1 - STATUS UPDATE AND EXTENSION OF TIME REQUEST
Description
Fordyce Dam Geotechnical Investigation: Response to FERC comments2019 11th P12D Inspection Chili Bar: R4 - Gallery drainage study2019 11th P12D Inspection Chili Bar: R6 - Evaluate waterproofing
gallery doors2018 P12D Inspection Fordyce: R-10 - Spillway Channel Access2018 P12D Inspection Fordyce: R-11 - Remove Boulders From SpillwayCaribou 1 Penstock Shotcrete Project Final
Construction Report2018 P12D Inspection Halsey AB: R2 - Perform spillway routing study2018 P12D Inspection Upper Peak Lake: R-1 Armor masonry wall 2018 11th P12d Inspection-Upper Peak
Lake: R-9 Vegetation adjacent to spillway
No.
231021552155231023102105231023102310
FERC
Project
Time
Date for
5/30/2021
Requested
Extension of
PG&E Status for
Extension of Time Request
Continuing investigation and evaluation of potential sources of the ponded water through the fall of 2020. A technical memorandum presenting the findings from the evaluation is currently
being prepared for the ICs to review.
8/27/2020
Most Recent
Correspondence
Date
02/28/2021
Current Due
830083
Dam Number
Description
2018 P12D Inspection Fordyce: R-16. Measure leakage through valvehouse.
No.
2310
FERC
Project