HomeMy WebLinkAboutPRED21-0001_Meeting NotesPRE-DEVELOPMENT MEETING PRED21-0001
February 17, 2021 1:00 PM – 3:00 PM via Skype Enterprise Rancheria APN: 079-150-001
Enterprise Rancheria and applicant Blu Nelson are proposing 12 stick built homes, each 1,360 square feet to be constructed on the
63.66-acre property currently zoned Rural Residential 5-acre minimums with a General Plan designation of RR. The property has two unnamed waterways (blue-lined streams) – one along the western side running north-south, the other bisecting the parcel with a confluence of the streams located in the lower third of the property. The property is undeveloped without an address, and has Oak
Woodland habitat throughout. The proposed access is via Crane Avenue from the east and potentially punching through two PG&E parcels (zoned Resource Conservation and Rural Residential, respectively) to the west and crossing one of the blue lined streams to connect with the stub out and continuation of Crane Avenue in the Copely Acres Unit #3 Phase 2 subdivision. Project is located within
the LOAPUD and SFWP districts and is proposed to be connected to sewer and water. Departments Comments
Planning Division Land Use, Zoning, & Permitting
• PD General Plan Amendment and Rezone, subject to Section 24-32 planned development zone
requirements of the Butte County Code (Code), and a Zoning Ordinance Map Amendment subject to Article
VI. Division 4. Zoning Ordinance Amendments of the Code, to allow for the specific land uses and
Development Plan proposed under the Project.
• PD rezoning requirements are needed to be met in order to evaluate the proposal prior to PD submittal.
• Tentative Subdivision to be required as part of the PD as indicated by the draft site plan.
• Riparian buffer regulations apply to any structure(s) built within 50’ of the top of bank for a blue line stream,
an approved Minor Use Permit is required.
• We anticipate Archeological, Biological, and potentially Traffic studies to be conducted as part of the
environmental review of the project.
• CEQA will evaluate the whole parcel, and any phases, as proposed to the Planned Development land use
entitlement.
• We don’t want to go through CEQA review more than once, what are the phases, if any?
• Settled on 12 units on the northern area.
For additional information regarding these requirements, please contact: Tristan Weems, Associate Planner at 530. 552.3685 / tweems@buttecounty.net
Public Works
• Concerns with access, both west side and east side Crane Ave, not connected on the property. Crane Avenue on the east side stops short but does not connect to the property.
• On the west side PG&E owns two parcels.
• On the draft plans, Crane is shown to connect to the west.
• Some potential challenges on the western side, lots owned by PG&E
• Mark M. Easements to the west are in place for the tribe to cross that land. There are easements to that side.
• On the east side Crane Ave. stops short.
• According to Mark, there is dedicated 40’ access/road to the east.
• Public portion of Crane needs to be addressed to punch through.
• Preliminary water drainage needs to be addressed.
• Tentative Map application guide stipulates needed details (contours, topography, etc.)
• Assumed public road subdivision, Public Permanent Road division. Any new dedicated roads in the County
require a PRD.
• Maintenance of the road will have to be addressed.
• Ensure that the instrument we ultimately approve with this development there will need to be some conditioning that speaks to road maintenance.
• East side section of Crane does not show it is public.
• Resolution of the east side of Crane needs to occur as the project moves forward.
• Engage County Surveyor Bill Bridgnell on the nature of the dedication (Radley) – applicant representative will contact Bill Bridgnell. This is a fundamental piece to move forward with application (Dan).
• No access strip on west side (1’) talk with Bill Bridgnell about this too.
• Bridge? Not proposing a bridge, proposing culverts. Consider some kind of clogging factor on the up hill side for the pipe anywhere form 50-75%.
For additional information regarding these requirements, please contact: Feraidon Ataie, Engineer Assistant, Land Development 530.538.7681 / fataie@buttecounty.net
Environmental
Health • The parcel is proposed to be connected to city sewer and water.
• EH will be looking for will-serve letters in future reviews and any existing septic or wells, which, would need
to go through a destruction office.
• KT believes that there is one well on the site – if it is not being used it will need to be destroyed through a
permit, per Nikolay Ostrovskiy.
For additional information regarding these requirements, please contact:
Nikolay Ostrovskiy, Program Manager 530.552.3869 / nostrovskiy@buttecounty.net
Butte County Fire/Cal Fire • Construction, installation or development of buildings and/or roads, driveways, gates and bridges on
parcels/lots shall comply with the latest California Fire Safe Regulations—Public Resources Code 4290,
4291 and current Butte County Improvement Standards, whichever is stricter.
• Prior to building construction, provide an all-weather access of at least 10 feet wide for residential, and 20
feet wide for commercial, and 15 feet vertical clearance that will allow for ingress and egress and
accommodate a 40,000-pound fire apparatus to within 150 feet of all structures.
• Place a note on a separate document, which is to be recorded concurrently with the Parcel or Final map, or
on an additional map sheet stating, “Building identification and/or addresses shall be installed in
conformance with Public Resources Code 4290 and shall be posted at the time of permit issuance and
maintained continuously thereafter.
• Prior to construction, a pressurized community water system for fire protection is required. Bonding may be
allowed with the approval of the County Fire Chief. Average required hydrant spacing is 500 feet (reduce by
100 feet on dead-end streets and roads), hydrant size 6 inches, and residual fire flow of 1000 GPM. Fire
hydrant identification, road reflectors or post reflectors acceptable to the County Fire Chief shall be installed
or bonded, prior to Parcel or Final map recordation. Submit plans to the Fire Department for review and
approval prior to construction.
For additional information regarding these requirements, please contact: John Gaddie, Prevention Life Safety Officer 530.538.6320 / john.gaddie@fire.ca.gov
Building Division • They would need permits to current code at time of building permit applications.
For additional information regarding these requirements or additional information, please contact: Efrain Ruvalcaba, Assistant Building Official 530.552.3651 / eruvalcaba@buttecounty.net
Agricultural Commissioner’s Office
• No issues if 100’ buffer remains
• No agricultural operations on the site itself
• Current phase with 12 homes does not have any adjacent agriculture
For additional information regarding these requirements or additional information, please contact:
Uriah Johnson, Agricultural Biologist/Weights and Measures Inspector 530.552.4091 / ujohnson@buttecounty.net
LOAPUD • Needed proper easements for sewer lines under PG&E properties – to email to applicant engineer.
• Looks like it will fall under standard agreement
• Parcels looking to served, question for LAFCO if the property will need to be annexed.
• Have the capacity to provide will serve letters – less than 20 units.
For additional information regarding these requirements or additional information, please contact: Scott McCutcheon, General Manager LOAPUD scottm@loapud.com Blu Nelson Next steps on access? Radley: that road to the east was offered for dedication and not accepted, technically the County does not own it, dedicated 1907 book 7 page 56. Last 600’ we don’t have as CO
maintained… note that developers wanted it to be a public highway, public road. Each property goes to
20’ into the road area, on either sides.