Loading...
HomeMy WebLinkAbout03.01.21 Board Correspondence - FW_ Project Operations Compliance Report submitted in FERC P-1061-019,et al. by Pacific Gas and Electric Company,et al. From:Paulsen, Shaina To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Kimmelshue, Tod;Lucero, Debra;Paulsen, Shaina;Pickett, Andy;Ring, Brian;Ritter, Tami;Rodas, Amalia; Sweeney, Kathleen;Teeter, Doug Subject:Board Correspondence - FW: Project Operations Compliance Report submitted in FERC P-1061-019,et al. by Pacific Gas and Electric Company,et al. Date:Monday, March 1, 2021 2:39:29 PM Good afternoon, Please see the email correspondence below from FERC. Shaina Paulsen Administrative Assistant, Senior Butte County Administration 25 County Center Drive, Suite 200, Oroville, CA 95965 O: 530.552.3300 |D: 530.552.3304 | F: 530.538.7120 -----Original Message----- From: 'FERC eSubscription' <eSubscription@ferc.gov> Sent: Monday, March 1, 2021 6:55 AM Subject: Project Operations Compliance Report submitted in FERC P-1061-019,et al. by Pacific Gas and Electric Company,et al. .ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying.. On 2/26/2021, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.: Filer: Pacific Gas and Electric Company Pacific Gas & Electric Company (as Agent) Docket(s): P-1061-019 P-1121-000 P-1354-000 P-137-000 P-175-000 P-1962-001 P-1988-000 P-2105-000 P-2106-000 P-2107-000 P-2130-000 P-2155-001 P-2310-000 P-233-000 P-2687-000 P-2735-000 P-619-000 P-77-001 P-803-000 Lead Applicant: Pacific Gas and Electric Company Filing Type: Project Operations Compliance Report Description: Pacific Gas and Electric Company submits the Multiple Status Update Overdue Items for the Potter Valley Hydroelectric Project et al under P-77 et al. To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20210226- 5438__;!!KNMwiTCp4spf!SfvfkaEyc5J4sUS5BbSipeB5EtzT2n0eNeENQ2BUth35GiMjBHo7D27O4iJUv4AgRl8Km0ahMyA$ To modify your subscriptions, click here: https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!SfvfkaEyc5J4sUS5BbSipeB5EtzT2n0eNeENQ2BUth35GiMjBHo7D27O4iJUv4AgRl8Kd41r5a4$ ------------------------------------------------------------------------ Please do not respond to this email. Online help is available here: https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!SfvfkaEyc5J4sUS5BbSipeB5EtzT2n0eNeENQ2BUth35GiMjBHo7D27O4iJUv4AgRl8KOcRGzNY$ or for phone support, call 866-208-3676. 245 Market Street tƚǞĻƩ DĻƓĻƩğƷźƚƓ San Francisco, CA 94105 Mailing Address: Mail Code N11D P.O. Box 770000 San Francisco, CA 94177 February 26, 2021 Via Electronic Submittal (E-File) Mr. Frank L. Blackett, P.E., Regional Engineer Federal Energy Regulatory Commission Division of Dam Safety and Inspections San Francisco Regional Office 100 First Street, Suite 2300 San Francisco, CA 94105-3084 RE: Overdue Items: Status Update Potter Valley Hydroelectric Project, FERC Project No. 77 Mokelumne River Hydroelectric Project, FERC Project No. 137 Balch Hydroelectric Project, FERC Project No. 175 Pit 3, 4, and 5 Hydroelectric Project, FERC Project No. 233 Bucks Creek-Grizzly Hydroelectric Project, FERC Project No. 619 DeSabla-Centerville Hydroelectric Project, FERC Project No. 803 Phoenix Hydroelectric Project, FERC Project No. 1061 Battle Creek Hydroelectric Project, FERC Project No. 1121 Crane Valley Hydroelectric Project, FERC Project No. 1354 Rock Creek-Cresta Hydroelectric Project, FERC Project No. 1962 Haas Kings River Hydroelectric Project, FERC Project No. 1988 Upper North Fork Feather River Hydroelectric Project, FERC Project No. 2105 McCloud-Pit Hydroelectric Project, FERC Project No. 2106 Poe Hydroelectric Project, FERC Project No. 2107 Spring Gap-Stanislaus Hydroelectric Project, FERC Project No. 2130 Chili Bar Hydroelectric Project, FERC Project No. 2155 Drum-Spaulding Hydroelectric Project, FERC Project No. 2310 Pit 1 Hydroelectric Project, FERC Project No. 2687 Helms Pumped Storage Hydroelectric Project, FERC Project No. 2735 Dear Mr. Blackett: This letter presents an update on the status of PG&E, dated July 20, September 16, and November 24, 2020, for the above-listed projects. As of February 26, 2021, 35 of the items have been completed. The status of each remaining overdue item is provided in enclosure 1. Mr. Frank L. Blackett, P.E., Regional Engineer February 26, 2021 Page 2 Should you have any technical questions concerning this matter, please contact me at (415) 624-4218. Sincerely, Teri Smyly Manager FERC Compliance Enclosure: Status Update of Overdue Items ENCLOSURE 1 4/30/20214/30/20217/31/20217/31/20216/30/20216/30/20214/30/20214/30/2021 PG&E DUE DATE (DATE) 2/10/20212/10/20212/10/20212/10/20212/10/20212/10/2021 EOTR GRANTED 1/7/20211/7/20211/7/20211/7/20211/7/20211/7/2021 12/24/202012/24/2020 TIME REQUESTED DATE EXTENSION OF PG&E STATUS - 2/26/2021 Filed EOT request for 12/24/2020: In consultation with the Filed EOT request for 12/24/2020: In consultation with the Conducting engineering review and developing plan and Final PFMA report undergoing internal review. STATUS OF FERC ITEM RESPONSES Pending completion of 7th Board of Consultants Meeting in Conducting substantial revisions to plan and schedule based Analysis required to complete prior to update of plan and : Pit 1 completed field inspection in December 2020 and Ongoing currently finalizing report. Ongoing:Q1 of 2021, will file updated schedule with final reports of site-specific probable maximum precipitation and flood studies.Ongoing: IC, PG&E is currently collecting and reviewing available information to identify potential gaps and concerns for which additional investigation and evaluation are needed to support the recommended FEM analyses.Ongoing: IC, PG&E is currently collecting and reviewing available temperature-related information for the dam. Following detailed review of the information, PG&E will work with the IC to determine whether a new temperature study is needed to develop revised temperature-related parameters for an updated structural analysis of the dam.Ongoing: schedule requirements consistent with 2019 PFMA and 5/29/2020 FERC letter.Ongoing:on 5/29/2020 FERC letter outlining recommended updates to 2019 PFMA.Ongoing: Ongoing:schedule. OVERDUE ITEMS DESCRIPTION Pit 1 DamScott Dam: 2014 Part 12D Recommendations (R-8, R-13, R-39, R-66, R-70): Updated Plan & Schedule2019 Part 12D Balch Div. (R-7, R-13, R-14); Balch AB (R-7, R-11, R-12): Results of Data Collection EffortsBalch Div. (R-12): Results of Documentation Review Evaluation of Potential effects of Overtopping effects and a plan & Schedule for Mitigation against any adverse effectsSeven items due within 90 days of FERC acceptance of studiesPit 3 Dam: Fault 3432 PFMA Workshop ReportPit 5 Open Channel: Plan & Schedule for completing recommendations from the Focused Spillway Assessmentletter). 77 No. 175175233233 2687 FERC Project 233, 1121, 2106, 2688233, 1121, 2106, 2688 10-Year Spillway Radial Gate Inspection Reports (GIRs) 35 101112131517 No. FERC Item Potter ValleyBalchPMF & Wind-Wave StudiesPit No. 3, 4 and 5DeSabla Centerville 5/31/20215/31/20214/30/20214/30/20214/30/20214/30/20217/31/2021 4/30/2021 2/10/20212/10/20212/10/20212/10/20212/10/2021 1/4/2021 1/7/20211/7/20211/7/20211/7/20211/7/2021 12/29/202012/29/2020 Revised construction package under development for final Plan and schedule undergoing internal review. Filed EOT request on 12/29/2020. PG&E is revising the DPP Revised construction package under development for final Plan and schedule undergoing internal review. Filed EOT request 1/4/2021. The project team is currently : Filed EOT request on 12/29/2020. PG&E is revising the DPP : Filed EOT request on 1/6/2021. PG&E is currently finalizing Ongoing:for Round Valley Dam to reflect updates to the Cape Horn Dam DPP that were necessary for FERC authorization of that effort. Ongoing for Philbrook Main and Auxiliary Dams to reflect updates to the Cape Horn Dam DPP that were necessary for FERC authorization of that effort. Ongoing: internal review prior to approval.Ongoing:internal review prior to approval.Ongoing:Ongoing: Ongoing construction documents and preparing project certifications to support the project construction report which will be submitted to FERC.Ongoing:developing design criteria and performing analyses to validate and advance the design elements that were conceptually developed and evaluated during the project alternatives analysis. PG&E is currently planning a dive inspection to confirm as-built conditions in the spring of 2021 and expects to complete its 50 percent project design package in the summer of 2021, with a scheduled target for construction in the fall of 2023. By July 31, 2021, PG&E will submit to FERC an update on the status and schedule for design and construction of the proposed tower improvements. Round Valley Dam: Revised DPP*Philbrook Dam: Revised DPP*Hendricks Head Dam: Repair Plan to address seepRound Valley Dam: Log Boom Construction PackageRound Valley Dam: Plan & Schedule for Focused Spillway Assessment recommendationsletter)Philbrook Dam: Memorandum/a regarding subterranean water flow and plan and schedule for completing recommendations from the Focused Spillway Assessment Coleman Intake Siphon No. 1: Final Construction Report for Automated Trash Rake ProjectCrane Valley Dam: Status update and plan and schedule for completing the outlet tower retrofit design 803803803803803803 11211354 1819222324252731 Battle CreekCrane ValleyRock Creek Cresta 4/30/20219/30/20216/30/20215/31/2021 1/7/2021 12/29/202012/29/202012/29/2020 Plan and schedule undergoing internal review. Filed EOT request on 12/29/2020. PG&E has initiated an Filed EOT request on 12/29/2020. PG&E has retained a Filed EOT request on 12/29/2020. PG&E has completed an Ongoing:Ongoing:engineering review of potential alternatives for modifying the parapet wall manways to mitigate the potential for concentrated flows beneath the manway boards during flood conditions. The review options, such as using alternative construction details or materials to better seal the access portals against leakage. PG&E plans to complete the review, including a constructability assessment to evaluate the feasibility of the various alternatives, in the summer of 2021.Ongoing:consultant to perform stochastic flood modeling of Courtright Reservoir to develop the recommended probabilistic reservoir elevation parameters. To support the modeling effort, PG&E has successfully procured engineering documents, operation records, and the results of previous probable maximum precipitation (PMP) and probable maximum flood (PMF) studies. PG&E plans to collect additional information, including historical hydrologic data; however, because of challenges related to the volume of information and limited ability to access archived files during the COVID-19 pandemic, PG&E requires additional time to collect and review the necessary data. Ongoing:investigation into the cause of the bolt failure at the top of the butterfly valve seat ring and is preparing an assessment report to document field findings, material testing results for the failed bolt, and an engineering evaluation of the remaining seat ring bolts. PG&E also completed its annual full-travel exercise of the valve in August 2020. Leakage and monitoring observations during the exercise will also be noted in the assessment report. Because of delays in scheduling the investigation, additional time is needed to complete the report and provide the results of the assessment to the Part 12D IC for review and comment Rock Creek Cresta Dam: 2019 FERC annual dam safety inspection: Plan and schedule for addressing the follow-up itemsCourtright Dam P12D (R-7): Feasibility study for modifying the parapet wall manwaysCourtright Dam Part 12D (R-8): Results of data collection efforts as a first step to evaluating the potential for overtopping Wishon Dam Part 12D (R-7): Investigation and evaluation report for the LLO butterfly valve seat ring bolt failure 1962198819881988 32343536 Haas-Kings 9/30/20216/30/20214/30/20214/30/2021 1/7/20211/7/2021 12/29/202012/29/2020 Filed EOT request on 12/29/2020. PG&E has initiated an Filed EOT request on 12/29/2020. PG&E has retained a Contracting additional analysis support for plan and Plan and schedule undergoing internal review. Ongoing:engineering review of potential alternatives for modifying the parapet wall manways to mitigate the potential for concentrated flows beneath the manway boards during flood conditions. The review options, such as using alternative construction details or materials to better seal the access portals against leakage. PG&E plans to complete the review, including a constructability assessment to evaluate the feasibility of the various alternatives, in the summer of 2021. Ongoing:consultant to perform stochastic flood modeling of Wishon Reservoir to develop the recommended probabilistic reservoir elevation parameters. To support the modeling effort, PG&E has successfully procured engineering documents, operation records, and the results of previous probable maximum precipitation (PMP) and probable maximum flood (PMF) studies. PG&E plans to collect additional information, including historical hydrologic data; however, because of challenges related to the volume of information and limited ability to access archived files during the COVID-19 pandemic, PG&E requires additional time to collect and review the necessary data. Following the collection efforts, PG&E plans to work with its consultant to identify potential data gaps, additional information sources, and additional studies that may be necessary to complete the modeling effort.Ongoing:schedule development.Ongoing: Wishon Dam Part 12D (R-8): Feasibility Study for modifying Parapet Wall Manways Wishon Dam Part 12D (R-11): Results of data collection efforts as a first step to evaluating the potential for overtopping Courtright & Wishon Dams: Plan and schedule to address Focused Spillway Assessment Report recommendations2019 FERC annual dam safety inspection: Plan and schedule for addressing the follow-up items 1988198819882107 37383946 PoeSpring Gap Stanislaus 6/30/20214/30/20214/30/20214/30/20214/30/2021 1/7/20211/7/20211/7/20211/7/2021 12/29/2020 : PG&E will investigate the oak tree and provide a Vegetation removed. Contracting additional analysis support for plan and Developing documentation to address recommendations Developing documentation to address recommendations : Filed EOT request on 12/29/2020. PG&E has completed an Ongoing engineering and geologic reconnaissance of the Main Strawberry Dam spillway control structure including visual observations, measurements, and geologic mapping of the structure and underlying foundation conditions. Information gathered during the reconnaissance was used to support an updated stability analysis of the structure. Preliminary results of the analysis indicate that the structural stability is within acceptable limits for normal, flood, and seismic load cases. PG&E provided the results of the updated spillway stability analysis to the eleventh Part 12D ICs for review and is Ongoing: schedule development.Rock Creek Ongoing specific evaluation of the subject oak tree, along with a plan and schedule if necessary, for FERC review by 4/30. Wise FB Complete:Ongoing:and plan and schedule if necessary to meet them.Ongoing:and plan and schedule if necessary to meet them. Strawberry Dam: Part 12D (R-6): Updated stability analyses of the spillway Relief & Strawberry Dams: Plan and schedule to address Focused Spillway Assessment Report recommendations. (no Rock Creek & Wise FB: 49 .Plan and schedule for addressing follow-up items No. 16 and 17 , respectively) from the 2018 FERC annual dam safety inspection: (no response received on these items from Halsey AB: Focused Spillway Assessment: Plan and schedule to address recommendations from and FERC comments: Due by 2/22/20 (no response Halsey FB 1: Focused Spillway Assessment: Plan and schedule to address recommendations from and FERC comments: Due by 2/22/20 (no response 21302130231023102310 4748495152 Drum Spaulding 4/30/20216/30/20216/30/20216/30/2021 1/7/20211/7/20211/7/2021 8/27/2020 Analysis completed, developing report for independent COVID19 impact to inspections schedules associated with Analysis completed, developing report for independent : Filed EOT request 8/27/2020. PG&E has performed Ongoing preliminary seismic deformation studies for Upper Peak Lake Dam based on the available geotechnical data from both Upper Peak and Kidd Lake Dams. As noted in the original P12 response, the studies at Kidd Lake are relevant to Upper Peak because of the similar location, age, and composition of the dams. PG&E has been delayed in completing the Upper Peak seismic deformation study.Ongoing: subdrain system. Updating timeline to reflect delay and resulting plan and schedule associated with findings.Ongoing: consultant review and comment.Ongoing: consultant review and comment. Upper Peak Lake: Seismic stability and deformation analysis (Eleventh Part 12D recommendation R-3): Due by 3/31/20, Halsey FB Dam 2: Internal video inspection report for the subdrain system: (Eighth Part 12D recommendation R-6): Due by 9/30/20, Halsey FB Dam1: Review of existing information regarding subsurface conditions and the liquefaction susceptibility of the foundation materials: (Eighth Part 12D recommendation R-1): Due letter.Wise FB: Review of existing information regarding subsurface conditions and the expected seismic performance of the foundation materials: (Fifth Part 12D recommendation R-10): Due by 11/1/20, 2310231023102310 54646566