HomeMy WebLinkAbout03.24.21 Board Correspondence - FW_ Project Operations Compliance Report submitted in FERC P-1962-001,et al. by Pacific Gas and Electric Company,et al.
From:Clerk of the Board
To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Kimmelshue, Tod;Lucero,
Debra;Paulsen, Shaina;Pickett, Andy;Ring, Brian;Ritter, Tami;Rodas, Amalia;Sweeney, Kathleen;Teeter, Doug
Subject:Board Correspondence - FW: Project Operations Compliance Report submitted in FERC P-1962-001,et al. by Pacific Gas
and Electric Company,et al.
Date:Wednesday, March 24, 2021 3:33:03 PM
Please see Board Correspondence below from FERC.
Shaina Paulsen
Administrative Assistant, Senior
Butte County Administration
25 County Center Drive, Suite 200
Oroville, CA 95969
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Wednesday, March 24, 2021 1:15 PM
Subject: Project Operations Compliance Report submitted in FERC P-1962-001,et al. by Pacific Gas and Electric
Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments,
clicking on links, or replying..
On 3/24/2021, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington
D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas and Electric Company (as Agent)
Docket(s): P-1962-001
P-2105-000
P-619-000
P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits DeSabla Watershed Sudden Failure Assessments for Projects
under P-619, et al.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20210324-5167__;!!KNMwiTCp4spf!RVxofHrTPHFEyFnf7a1U-RJXpPLM1vCSJ8LjDv-
wuLR3AGI9ww3YRct9wiHfZd_xZo6DWWFPoxM$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!RVxofHrTPHFEyFnf7a1U-
RJXpPLM1vCSJ8LjDv-wuLR3AGI9ww3YRct9wiHfZd_xZo6DbzGZpRk$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!RVxofHrTPHFEyFnf7a1U-
RJXpPLM1vCSJ8LjDv-wuLR3AGI9ww3YRct9wiHfZd_xZo6DmqwGtb0$
or for phone support, call 866-208-3676.
DeSabla Watershed SFA Dams Enclosure 2
FERC Project No. Dam Name NATDAM No.
619 Three Lakes Dam CA00334
Power Generation
245 Market Street
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
March 24, 2021
Via Electronic Submittal (E-File)
Mr. Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
SUBJECT: DeSabla Watershed Sudden Failure Assessments FERC Projects:
619, 803, 1962, 2105
Enclosure 1Contains Controlled Unclassified Information // Critical Energy
Infrastructure Information (CUI // CEII) DO NOT RELEASE
Dear Mr. Blackett:
Pursuant to FERC Chapter VI: Emergency Action Plans (revised July 2015) Section 6-5,
Pacific Gas and Electric Company (PG&E) has completed a sudden failure assessment
(SFA) for the dams listed in enclosure 2 for the DeSablaWatershed, which includes the
following Federal Regulatory Energy Commission (FERC) projects: Bucks Creek Project
No. 619, DeSabla-Centerville Project No. 803, Rock Creek-Cresta Project No. 1962, Upper
North Fork Feather River Project No. 2105.
On December 31, 2020 PG&E submitted an EAP status report for the DeSablaWatershed.
In the status report, PG&E indicated that we were nearing completion of updating the
SFAs for all non-time sensitive PG&E EAP dams to verify if those dams continue to be
non-time sensitive. PG&E indicated that we would provide the results of these SFAs to
FERC by March 31, 2021. This letter and attached report serve as our submission of this
task.
The report is attached to this letter in enclosure 1. The dams assessed in the sudden
failure assessment are provided in enclosure 2. The assessment was performed by
Cardno, and PG&E has reviewed and accepted the study and concurs with the results.
As a result of this assessment, PG&E is beginning development of a plan and schedule to
reduce the excess response times and evaluate early warning technologies. PG&E
requests to submit the plan and schedule for these items by September 30, 2021.
Mr. Frank L. Blackett, P.E., Regional Engineer
March 24, 2021
Page 2
If you have any questions, please contact me at (530) 616-1079, or email
AWH9@pge.com.
Sincerely,
Andrew Hagen
EAP Coordinator/Public Safety Specialist
Power Generation
Enclosures:
•Enclosure 1: EAP Sudden Failure Assessment (CUI // CEII) – DO NOT RELEASE