Please see additional Board Correspondence below from FERC.
Shaina Paulsen
Administrative Assistant, Senior
Butte County Administration
25 County Center Drive, Suite 200
Oroville, CA 95969
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Monday, March 29, 2021 8:15 AM
Subject: Part 12 Consultant Safety Inspection Reports submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 3/29/2021, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
No Organization Found (as Agent)
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Part 12 Consultant Safety Inspection Reports
Description: Pacific Gas and Electric Company submits plans and schedules to address recommendations from the 11th 5-year Part 12D safety inspection report for Grizzly Forebay Dam, part
of
Bucks Creek Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20210329-
5056__;!!KNMwiTCp4spf!QQ295397UFfyahkI_HsXpIBcm3fdiKB3GYue7c4s8eRAmilsIyufo3pn3qdvdDWRQIwFJxVwsFw$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!QQ295397UFfyahkI_HsXpIBcm3fdiKB3GYue7c4s8eRAmilsIyufo3pn3qdvdDWRQIwFaOxCRo4$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!QQ295397UFfyahkI_HsXpIBcm3fdiKB3GYue7c4s8eRAmilsIyufo3pn3qdvdDWRQIwFjZ33WFI$
or for phone support, call 866-208-3676.
Power Generation
245 Market Street
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
March 26, 2021
Via Electronic Submittal (E-file)
Mr. Frank L. Blackett P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Grizzly Forebay Dam, NATDAM No. CA00333
11th Part 12D Inspection, Plan and Schedule
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Mr. Blackett:
This letter presents Pacific Gas and Electric Company’s (PG&E) plans and schedulesto
address recommendations from the 11th 5-year Part 12D safety inspection report for
Grizzly Forebay Dam, which is part of PG&E’s Bucks Creek Hydroelectric Project, Federal
Energy Regulatory Commission (FERC) No. 619. PG&E submitted the safety inspection
report, prepared by independent consultants (ICs) Mr. William Rettberg, P.E., and Mr.
Chad M. Masching, P.E., and dated January 2021, to FERC on January 29, 2021. PG&E’s
proposed plans and schedules to address the ICs’ recommendations are enclosed with
this letter (Enclosure 1).
Ongoing shelter-in-place orders issued by the State of California in response to the
COVID-19 pandemic require that nonessential PG&E staff work remotely, and hard copy
filings are not practical at this time. If FERC requires hard copies of this letter and/or
enclosures, please contact the license coordinator identified below. If necessary, hard
copies will be sent after the shelter-in-place restrictions have been lifted and PG&E staff
have returned to their normal work locations.
Should you have any technical questions concerning this matter, please contact PG&E’s
senior dam safety engineer, Mr. Ben Fontana, at (530) 762-9459. For general questions,
please contact PG&E’s senior license coordinator, Ms. Jamie Visinoni, at (530) 215-6676.
Mr. Frank L. Blackett, P.E., Regional Engineer
March 26, 2021
Page 2
Sincerely,
David L. Ritzman, P.E., G.E.
Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. Plans and Schedules