HomeMy WebLinkAbout07.06.21 Board Correspondence - Delegated Order issued in FERC P-619-167
From:Clerk of the Board
To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Hironimus, Patrizia;
Kimmelshue, Tod;Lucero, Debra;Paulsen, Shaina;Pickett, Andy;Reaster, Kayla;Ring, Brian;Ritter, Tami;Sweeney,
Kathleen;Teeter, Doug
Subject:Board Correspondence - Delegated Order issued in FERC P-619-167
Date:Tuesday, July 6, 2021 10:32:42 AM
Please see below correspondence.
Kayla Reaster, MBA, MAED
Associate Clerk of the Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
T: 530.552.3308 | F: 530.538.7120
Twitter | Facebook | YouTube | Pinterest
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, July 6, 2021 9:25 AM
Subject: Delegated Order issued in FERC P-619-167
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments,
clicking on links, or replying..
On 7/6/2021, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-619-167
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Delegated Order
Description: Order Approving As-Built Exhibit L Drawing re City of Santa Clara, California et al under P-619.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20210706-3021__;!!KNMwiTCp4spf!QXSR8gJF2DNuMwMs9R-
5RGrDv1ZLXDPm7T_MWQCo1C426lrPuj0jzDIJqnC87HatWsxoxwNPkLw$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!QXSR8gJF2DNuMwMs9R-
5RGrDv1ZLXDPm7T_MWQCo1C426lrPuj0jzDIJqnC87HatWsxoAYHLwD4$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!QXSR8gJF2DNuMwMs9R-
5RGrDv1ZLXDPm7T_MWQCo1C426lrPuj0jzDIJqnC87HatWsxo1qbB5P8$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
176 FERC ¶ 62,011
UNITEDSTATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
City of Santa Clara, CaliforniaProject No. 619-167
Pacific Gas & Electric Company
ORDERAPPROVING AS-BUILTEXHIBIT LDRAWING
(IssuedJuly6, 2021)
1.OnFebruary 11, 2021,the City of Santa Clara, CaliforniaandPacific Gas &
1
Electric Company, licenseesfor theBucks CreekHydroelectric Project No.619,fileda
revisedExhibit Ldrawingto reflect as-built changesto theGrizzly forebay dam.The
project is located on the North Fork Feather River and Bucks and Grizzly creeks in
Plumas County, California, and occupies federal land within the Plumas National Forest
administered by the U.S. Forest Service.
Background
2.OnMay 8, 2020, the Commission’s Division of Dam Safety and Inspections-San
Francisco Regional Office issued a letter authorizing the licenseesto proceed withtheir
modification ofthe low-level outletat the Grizzly forebaydam. The letter requires the
licensee to file as-builtdrawings following completion of construction.
Licensees’Filing
3.In itsFebruary 11, 2021filing, the licenseesincluded one Exhibit L drawing
showing the modifications to the low-level outletat the Grizzly forebaydam.
Our Review
4.Commission staff’sreview shows the drawing conformsto the Commission’s
rules and regulations and should be approved. In ordering paragraph (B) of this order,
Commission staffisrequiring the licenseesto file the approved exhibit drawing in
electronic file format.
1
Pacific Gas and Electric Company, 52 FPC 1898 (1974).
Project No. 619-1672
The Director orders:
(A)The following Exhibit Ldrawing filed on February 11, 2021for theBucks
CreekHydroelectricProject No. 619, conformsto the Commission's rules and
regulations, and isapproved and madepart of the licenseas labeled and numbered below.
This order supersedes the previous Exhibit L-4(drawingno. P-619-210) and deletes it
from the license.
FERCDrawing
ExhibitDrawing Title
2
Drawing No.Filename
Dam and Forebay –Grizzly Dam &
L-4P-619-216
Grizzly Forebay DamForebay
(B)Within 45 days of the issuance date of this order, as directed below, the
licenseesmust file the approved exhibit drawing in electronic file format.
The licenseesmust prepareadigital image of the approved exhibit drawing in
electronic format. Prior to preparing thedigital image, the licenseesmust add the FERC
Project-Drawing Number (i.e., P-619-216) in the margin below the title block of the
corresponding approved drawing. The licenseesmustlabel and file the Exhibit L
drawing as Critical Energy Infrastructure Information (CEII) material under 18
CFR § 388.113(The submission should be comprised of: 1) a public portion consisting
of a cover letter; and 2) a CEII portion containing only the Exhibit Ldrawing). Each
drawing must be a separate electronic file, and the file name must include: FERC Project-
Drawing Number, FERC Exhibit Number, Drawing Filename, date of this order, and file
extension in the following format \[P-619-216,L-4,Grizzly Dam & Forebay,MM-DD-
YYYY.TIFF\]. All digital images of the exhibit drawing must meet the following format
specification:
IMAGERY:black & white raster file
FILE TYPE:Tagged Image File Format, (TIFF) CCITT Group 4 (also
known as T.6 coding scheme)
RESOLUTION:300 dots per inch (dpi) desired, (200 dpi minimum)
DRAWING SIZE:22” x 34” (minimum), 24” x 36” (maximum)
FILE SIZE:less than 1 megabyte desired
2
The licenseesmust use this exact drawing title when filing the electronic file
format drawing required in ordering paragraph (B). Commission staff shortened the
drawing title due to filename character limits. There is no need to modify the title as it
appearson the drawing.
Project No. 619-1673
(C)This order constitutes final agency action.Any party may file a request for
rehearing of this order within 30 days from the date of its issuance, as provided
insection 313(a) of the FederalPowerAct, 16 U.S.C. § 825l(2018), and the
Commission’s regulationsat18 C.F.R. § 385.713 (2020).The filing of a request for
rehearing does not operate as a stay of the effective date of this order, or of any other date
specified in this order.The licensees’failure to file a request for rehearing shall
constitute acceptance of this order.
Kelly Houff
Chief, Engineering ResourcesBranch
Division of Hydropower Administration
and Compliance