HomeMy WebLinkAbout08.31.21 Board Correspondence - FW_ Monthly Sewer Update Memo - August 2021
From:Paulsen, Shaina
To:Alpert, Bruce;Bennett, Robin;Clerk of the Board;Connelly, Bill;Cook, Holly;Cook, Robin;Hironimus, Patrizia;
Kimmelshue, Tod;Lucero, Debra;Paulsen, Shaina;Pickett, Andy;Reaster, Kayla;Ring, Brian;Ritter, Tami;
Sweeney, Kathleen;Teeter, Doug
Subject:Board Correspondence - FW: Monthly Sewer Update Memo - August 2021
Date:Tuesday, August 31, 2021 3:08:49 PM
Attachments:202108 Butte County Monthly Status Report August 2021.pdf
image002.png
Please see Board Correspondence below.
Shaina Paulsen
Administrative Assistant, Senior
Butte County Administration
25 County Center Drive, Suite 200
Oroville, CA 95965
T: 530.552.3304 | F: 530.538.7120
From: Mattox, Marc <mmattox@townofparadise.com>
Sent: Tuesday, August 31, 2021 3:00 PM
To: Costa, Shannon <SCosta@buttecounty.net>; Clerk of the Board
<clerkoftheboard@buttecounty.net>
Cc: Buttz, John <John.Buttz@hdrinc.com>; Brendan Ottoboni <brendan.ottoboni@Chicoca.gov>;
Tice, Leslie <Leslie.Tice@hdrinc.com>; Phillips, Kevin <KPhillips@townofparadise.com>; Hatcher,
Casey <CHatcher@buttecounty.net>; Snyder, Clint@Waterboards
<clint.snyder@waterboards.ca.gov>; Lucas, Steve <SLucas@buttecounty.net>
Subject: Monthly Sewer Update Memo - August 2021
ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
..
attachments, clicking on links, or replying.
Good afternoon Butte County and LAFCo!
Please find attached our fourth regular monthly update for the purpose of keeping the Butte County
Board of Supervisors and LAFCo Board apprised of progress in the Sewer Project. We will continue to
send these on a regular basis and welcome any opportunities to address the Board(s) as requested.
Sincerely,
Marc Mattox
Public Works Director | Town Engineer
Town of Paradise | 530-872-6291 x125
Website | Contact Us | Facebook
Memorandum
Paradise Sewer Project
Subject: August 2021 Monthly Status Report for Paradise Sewer Project to Butte County Agencies
Date: August 31, 2021
Authors: Marc Mattox (Town of Paradise), John Buttz (HDR)
This monthly memo is intended to be a high level summary of activities for the purpose of regular
communication with Butte County agencies and to identify any need for formal Board presentations.
For project information, please see www.paradisesewer.com.
Efforts for Past Month:
The Central Valley Regional Water Quality Control Board (Regional Board) hosts meetings of
the Sewer Regionalization Project Advisory Committee (SRPAC). The SRPAC met on August
9, 2021 at 1:00 pm. The meeting was held in-
Continued analysis efforts for the Draft EIR. Finalized estimatation of construction impacts.
Updated Project Description and Alternatives sections.
Continued to update public website (www.paradisesewer.com).
The City of Chico, through its consultant Carollo Engineers, continued its analysis of the
potential to treat Paradise wastewater at the Chico Water Pollution Control Plant.
Efforts for Next Month:
th
meeting, the SRPAC decided to shift to a meeting frequency of once every two
months, with the next meeting planned for October 11, 2021 at 1:00 pm at the Town of
. Information about SRPAC meetings can be found at
www.paradisesewer.com.
Continue analysis efforts on the Draft Environmental Impact Report (EIR).
The City of Chico, through its consultant Carollo Engineers, will continue its analysis of the
potential to treat Paradise wastewater at the Chico Water Pollution Control Plant.
Requests/Interactions with County Agencies:
EIR field work would benefit from access to several private parcels in south Chico (outside of
the city limits). We would like to continue to explore potential rights-of-entry requests for those
parcels.