DATE: February 23, 2022
TO: California State Clearinghouse
Responsible and Trustee Agencies
Interested Parties and Organizations
SUBJECT: Notice of Preparation of an Environmental Impact Report for the Proposed Tuscan
Ridge Project
REVIEW PERIOD: February 23, 2022 to March 24, 2022
Butte County is the lead agency for the preparation of an Environmental Impact Report (EIR) for the Tuscan Ridge
Project (proposed project) in accordance with the California Environmental Quality Act (CEQA), Section 15082.
The purpose of the Notice of Preparation (NOP) is to provide responsible agencies and interested persons with
sufficient information in order to enable them to make meaningful comments regarding the scope and content of
the EIR. Your timely comments will ensure an appropriate level of environmental review for the project.
Project Location: The project site consists of approximately 165 acres located on the southeast side of Skyway
Road, in unincorporated Butte County, between Chico and Paradise, California, and is identified by eight
Assessor’s Parcel Numbers (APNs) 040-520-104, 040-520-105, 040-520-106, 040-520-107, 040-520-108, 040-
520-109, 040-520-110, and 040-520-111. The site is located approximately three miles southwest of the Town of
Paradise, 0.5-mile northeast of the Rocky Bluffs residential subdivision, across the Skyway, and four miles east
of the City of Chico. The project site is situated on a prominent ridge, which is the location of the previous Tuscan
Ridge Golf Club. Skyway, which is identified by the Butte County General Plan as a County Scenic Highway, runs
the entire length of the northwest site boundary and Paradise Rod & Gun Club is located adjacent to the northeast
of the site.
Project Description Summary: The proposed project would include subdivision of the project site to develop a
total of 165 single-family residential lots. The lots would range in size from 4,000 square feet (sf) to 40,000 sf. The
proposed project would additionally include commercial development occupying approximately 17.3 acres of the
project site, including approximately four acres for improved buildings and parking and approximately 13.3 acres
for mini storage units (53,000 square feet) and outdoor RV and boat storage. The proposed project would also
include the development of a sanitary waste disposal station. Additionally, approximately 49.4 acres of the site
would consist of landscaped areas, as well as recreational and open space areas to include bicycle and pedestrian
trails. Various associated improvements would be included in the development of the proposed project
infrastructure. Access to the site would be provided through the existing driveway from Skyway Road near the
center of the site, which would be improved as part of the project, and a new access near the eastern end of the
site. Internal roadways throughout the site would be public, to be dedicated to the County for maintenance. The
area of the project site within 350 feet of the centerline of Skyway Road is within the associated Scenic Highway
(SH) Overlay Zone. The proposed project would require County approval of a General Plan Text Amendment;
Planned Development (PD) Rezone; Subdivision Map; and a Minor Use Permit for development within the SH
Overlay Zone. Additional Minor Use Permits and/or Conditional Use Permits may subsequently be required in the
future for specific commercial uses. Other approvals necessary to implement the proposed project would include
annexation of the project site into the service area of the Paradise Irrigation District (PID) for the operation of the
on-site water and wastewater facilities, subject to approval by the Butte Local Agency Formation Commission
(LAFCo), and formation of a Permanent Road Division for maintenance of the proposed roads, drainage facilities
and lighting.
2
Contact Information: For more information regarding the proposed project, please refer to the following detailed
project description or contact Kevin Valente, Contract Planner, at (916) 372-6100 or
kvalente@raneymanagement.com. A copy of the NOP is available for review at the Butte County Public Library
located at 1108 Sherman Avenue, Chico, CA, 95926; the Butte County Development Services Department
located at 7 County Center Drive, Oroville, CA, 95965; and on the Butte County website at:
https://www.buttecounty.net/dds/Planning/Notable-Projects
NOP Comment Period: Written comments should be submitted at the earliest possible date, but not later than
5:00 PM on March 24, 2022 to Kevin Valente, Contract Planner, by mail at 1501 Sports Drive, Suite A,
Sacramento, California, 95834; by fax at (916) 419-6108; or by email at kvalente@raneymanagement.com.
Please limit public comments to the scope of the EIR as described in this NOP.
NOP Scoping Meeting: In addition to the opportunity to submit written comments, a NOP scoping meeting will
be held in person and virtually via WebEx to inform interested parties about the proposed project, and to provide
agencies and the public with an opportunity to provide comments on the scope and content of the EIR. Further
information on the date and time of the scoping meeting is provided below.
EIR Scoping Meeting on the Tuscan Ridge Project
Monday | March 14, 2022 | 10:00AM
Butte County Human Resources
3 County Center Drive
Oroville, CA
or
Teleconference Meeting
WebEx: https://bit.ly/Scoping_Attendee
Phone: 1+ (844) 992 4726 | Meeting Number: 2553 102 8723 | Password: Scoping
1.0 PROJECT DESCRIPTION
1.1 Location and Setting
The project site consists of approximately 165 acres of what was formerly the Tuscan Ridge Golf Club, located
on the southeast side of the Skyway, in unincorporated Butte County, between Chico and Paradise, California.
The Skyway is the sole roadway in the immediate project vicinity and is identified by the Butte County General
Plan as a County Scenic Highway. Currently, access is provided through an existing driveway from Skyway near
the center of the site, which has boulder accent walls on either side and two metal gates prohibiting public entry.
State Route (SR) 99 lies approximately four miles to the west and SR 191 is approximately five miles to the east
(see Figure 1).
The project site is predominantly bound by large undeveloped parcels to the east, south, and west, with the
exception of Paradise Rod & Gun Club, which is located adjacent to the northeast border of the site (see Figure
2). The site is currently highly disturbed, with large graveled and/or paved areas void of vegetation, due to damage
sustained immediately before, during, and after the 2018 Camp Fire. In mid-2018, prior to the Camp Fire, the site
was used as a Pacific Gas and Electric Co. (PG&E) vegetation management camp. The site was subsequently
burnt during the wildfire, then leveled and graveled for use as a base camp and staging area by PG&E and ECC
Constructors during the wildfire response. PG&E continued to use portions of the site as a base camp for debris
removal until March 2020. A secondary access point from the Skyway was created in the northeastern portion of
the site during the site’s use as a base camp, but has since been blocked off by boulders and is currently
inaccessible. A small area near the secondary access point location is currently being leased by Henkels & McCoy
for materials storage and a portable administrative building.
3 Figure 1 Regional Location
4 Figure 2 Project Location
5
The terrain of the site is varied from flat to gently sloped, with elevations ranging from approximately 650
feet above mean sea level (amsl) in the west to approximately 925 feet amsl in the east. Vegetation on the
site consists primarily of sparse ruderal vegetation, along with scattered oak and pine trees. An existing
drainage ravine is located within the northwestern portion of the site, generally parallel with Skyway, and
includes a culvert under the main access driveway, as well as under an existing access easement in the
western portion of the site. An existing outfall is located near the westernmost border of the site. A number
of easements are present throughout the project site, including the access easement within the western
portion of the site for the adjacent agricultural property, as well as power utility easements across the site.
The access easement is currently used only occasionally by the adjacent property owner to move small
pieces of equipment to and from their property.
Three unused and unoccupied structures associated with the previous Tuscan Ridge Golf Club currently
exist on-site: a 2,440-sf grill building, an 1,830-sf clubhouse, and a Quonset hut. In addition, an existing
potable water well and associated system, as well as an existing wastewater treatment system, including
septic tanks, leach field, and disposal ponds, are located in the southwestern portion of the site. The existing
potable water and wastewater treatment systems are described in further detail in the Public Services and
Utilities section of the Project Components description below.
1.2 Surrounding Land Uses
With the exception of the Paradise Rod & Gun Club adjacent to the northeast of the site boundaries, the
land surrounding the project site is undeveloped. The Paradise Rod & Gun Club consists of two buildings
with associated parking spaces, and two outdoor shooting ranges. Agricultural land, primarily used for
grazing, is located to the south and southwest of the site. As shown in Figure 2, Butte Creek is located to
the north of, and runs roughly parallel to, the Skyway. The Butte Creek Ecological Preserve is also located
north of the site, across the Skyway, with Butte Creek Canyon located further to the northeast. Butte Creek
and the Butte Creek Ecological Preserve are separated from the project site by the Skyway and an
approximately 380-foot decline in elevation. The nearest existing residential uses to the project site would
be the Rocky Bluffs residential subdivision located approximately 4,100 feet to the southwest, across the
Skyway, and a number of rural single-family residences located along Honey Run Road, approximately
2,700 feet to the north of the project site, across the Skyway. The rural residences are separated from the
project site by Butte Creek, the Butte Creek Ecological Preserve, the Skyway, and an associated decline
in elevation of approximately 434-feet.
1.3 Existing Land Use and Zoning Designations
The project site currently has a County of Butte General Plan land use designation of Planned Unit
Development (PUD) and is zoned Planned Development (PD). In adopting the Butte County 2030 General
Plan, the County prepared an EIR in 2010 and a subsequent EIR (SEIR) in 2012. Both the 2010 EIR and
2012 SEIR assume that the project site will be built out with a golf course and 165 dwelling units (see, e.g.,
2010 Draft EIR, pg. 3-49 [Table 3-5]; and 2012 Draft SEIR, pg. 3-45 [Table 3-5].) In addition, the Skyway is
identified by the Butte County 2030 General Plan as a County Scenic Highway; thus, the area extending
350 linear feet from the centerline of the roadway is considered to be a SH Overlay Zone and is subject to
the requirements of Section 24-42 of the Butte County Code.
The land to the south of the project site is designated Agriculture (AG) in the General Plan and zoned
Agricultural with a minimum parcel size of 40 acres and a maximum of one unit per parcel (AG-40). The
land across the Skyway, north of the project site, is designated as Foothill Residential (FR) and zoned
Foothill Residential with a maximum of one unit per 20-acre parcel (FR-20). The area designated FR is
separated from the project site by an approximately 2,700-foot distance and an approximately 434-foot
decline in elevation. The Rocky Bluffs subdivision, located approximately 4,100 feet to the southwest of the
project site, is designated and zoned Medium Density Residential (MDR), which allows for a maximum
density of six dwelling units per acre.
6
1.4 Project Components
The proposed project would include subdivision of the project site to develop a total of 165 residential units,
commercial development, recreation areas, open space, various on-site road improvements, and a sanitary
waste disposal station. The proposed project would require County approval of a General Plan (GP) Text
Amendment; Planned Development (PD) Rezone; Subdivision Map; and a Minor Use Permit for
development within the SH Overlay Zone. Other approvals necessary to implement the proposed project
would include annexation of the project site into the service area of the Paradise Irrigation District (PID),
subject to approval by the Butte LAFCo. The proposed project components, along with all required
entitlements and approvals, are described in further detail below.
General Plan Text Amendment
A General Plan Text Amendment is requested to revise Section D, Future Planned Unit Developments,
Area Plans, and Specific Plans, on page 4-31 of the Land Use Element of the General Plan, as shown
below. The requested General Plan Text Amendment would remove the requirement to retain a golf course
on-site and add commercial uses. As previously mentioned, the former Tuscan Ridge Golf Course was
destroyed by the Camp Fire.
“The Tuscan Ridge PUD will determine the mix of uses that will occur in a 172 165-acre
area located along the Skyway at the site of the previously existing Tuscan Ridge Golf
Course. Residential A mix of residential uses, community commercial uses, water and/or
sanitary sewer facilities provided by a public or private entity may be developed in this area,
provided that the golf course is also maintained.”
Planned Development Rezone
The site currently has a Butte County land use designation of PUD and a zoning designation of PD. The
land use and zoning designations of the site were approved by the Board of Supervisors as part of the
development of the Butte County General Plan 2030 and the 2012 Zoning Map update, respectively, at the
request of the property owner. According to Article II, Division 6, Section 24-28 (D) of the Butte County
Code, the purpose of the PD zone is to allow for high-quality development that deviates from standards and
regulations applicable to other zones within the County. The PD zone is intended to promote creativity in
building design, flexibility in permitted land uses, and innovation in development concepts. The PD zone is
also intended to ensure project consistency with the General Plan, sensitivity to surrounding land uses, and
the protection of sensitive natural resources. The PD zone provides land owners with enhanced flexibility
to take advantage of unique site characteristics to develop projects that will provide public benefits for
residents, employees, and visitors to Butte County. Accordingly, the PD zone is intended to allow for a
variety of uses and development.
Pursuant to Article II, Division 6, Section 24-32, Planned Development Zone Requirements, and Article VI,
Division 4, Zoning Ordinance Amendments, of the Butte County Code, the proposed project would require
a PD rezoning to specifically allow for the proposed uses. The proposed Land Use Plan (see Figure 3)
provides a visual depiction of the anticipated land uses proposed as part of the project.
Subdivision
The proposed project would include a Vesting Tentative Subdivision Map (see Figure 4) to subdivide the
project into 165 single-family residential lots, five commercial use lots, 49.4 acres of open space, a 3.7-acre
amenity center, and 36.4 acres of special utility district associated with the on-site water and sewer systems,
as shown in Table 1.
7 Figure 3 Land Use Plan
8 Figure 4 Tentative Subdivision Map
9
Table 1
Proposed Land Uses
Proposed Land Use Acreage
Single-Family Residential 58.1
Commercial 17.3
Amenity Center 3.7
Open Space 49.4
Special Utility District 36.4
Total 165.0
Single-Family Residential
The proposed 165 residential lots would range from 4,000 sf to 40,000 sf. The residences would generally
be located in the center of the site, with the largest residential lots located nearest to the southern border
of the project site, where expansive views are available to the south. The Amenity Center would include the
existing clubhouse, which would be used as a community space for the residents and for back-of-house
operations.
Commercial Development
The proposed project would include 17.3 acres divided into five lots for commercial uses. As currently
designed, the proposed project would include an approximately 3,600-sf gas station/convenience store with
up to 16 fuel dispensers and up to approximately 76,000 sf of commercial space, across one- and two-story
buildings, along the primary site entrance. Additionally, the eastern portion of the project site would be
developed with a mini storage use with outdoor RV and boat storage. The mini storage would offer up to
approximately 53,000 sf of space for storage units. While the specific uses within the approximately 76,000
sf of commercial space near the main entry is currently unknown, the uses under the PD zoning would be
limited to the permitted and conditionally permitted uses allowed within the General Commercial (GC) and
Neighborhood Commercial (NC) zoning districts, pursuant to Table 24-22-1, Permitted Land Uses in the
Commercial and Mixed Use Zones, of the County Code. In addition, as part of the PD zoning, the maximum
floor area ratio would be limited to 0.4 and the maximum height would be limited to 50 feet, as required for
development within the GC zoning district. The anticipated gas station/convenience store and mini storage
uses would be consistent with the allowable uses under the GC and NC zoning districts. The following list
of additional commercial uses that would be consistent with the GC and NC zoning districts, subject to the
permit or approval noted, would be permissible through the PD zoning:
Drive-Through Facility – subject to a Minor Use Permit;
Offices, Professional – Permitted, subject to a Zoning Clearance;
Personal Services – Permitted, subject to a Zoning Clearance;
Restaurant – Permitted, subject to a Zoning Clearance;
Retail, General – Permitted, subject to a Zoning Clearance;
Commercial Recreation, Indoor – subject to a Minor Use Permit;
Construction, Maintenance and Repair Services – subject to a Minor Use Permit;
Child Care Center (facility providing child care) – subject to a Minor Use Permit;
Child Day Care, Large (home providing child care for seven to fourteen children) – subject to a
Minor Use Permit;
Child Day Care, Small (home providing child care for eight or fewer children) – Permitted, subject
to a Zoning Clearance;
Community Centers – subject to a Conditional Use Permit;
Medical Office and Clinic – Permitted, subject to a Zoning Clearance; and
Bars, Nightclubs, Lounges – subject to a Conditional Use Permit.
10
Access and Circulation
Access to the proposed project would be provided by two entrances from the Skyway, as shown in Figure
3 and Figure 4. The existing entrance located near the center of the site would be improved and a new
entrance would be established in the eastern portion of the site. The two proposed access points, as
currently configured, would contain full intersections that would allow for left turns from the Skyway. The
existing access easement in the western portion of the project site for the adjacent agricultural property
would remain and could serve as additional emergency ingress/egress, if needed.
The main entrance from the Skyway would connect to the internal roadways at a roundabout, from which
the internal roadways would extend to the northeast and southwest, providing access to the residences.
The main entry road would be designed with a 96-foot right-of way with a greenway and sidewalk along
both sides. The proposed gas station/convenience store and up to approximately 76,000 sf of commercial
space would be located along the main entry road. The internal roadway extending to the northeast from
the roundabout would consist of an 80-foot right-of-way before transitioning to the typical internal roadway
design of a 60-foot right-of-way, containing two 12-foot lanes and allowing eight feet for street parking on
both sides. The internal roadway extending to the southwest from the main entry roundabout would consist
of a 110-foot right-of-way to a four-way roundabout further southwest, where the main roadway would then
transition from a 90-foot right-of-way to the typical internal roadway design of a 60-foot right-of-way. All
project roadways would be public and would be dedicated to the County for maintenance.
The eastern driveway from Skyway Road would be located at the currently blocked-off access point that
was previously used during wildfire response efforts. The eastern entrance would primarily serve the
proposed sanitary waste disposal station and mini storage use proposed in the eastern portion of the site,
while also providing secondary access to the residences within the northeastern portion of the site. The
intersection would also provide more convenient access to patrons of the Paradise Rod & Gun Club, located
east of the project site, traveling westbound along Skyway Road.
Open Space, Trails, and Landscaping
As part of the proposed project, a total of approximately 49.4 acres of open space is proposed within the
project site (see Figure 3), which would primarily be located within an approximately 300- to 400-foot area
along the frontage of the Skyway, within the SH Overlay Zone. In addition, open space would be located
along the southwest border of the project site, thinning to a 50-foot area between the southeasternmost
residential lots and the eastern edge of the project site, as well as within landscaped areas along internal
roadways. Throughout the open space, predominantly within the northern portion of the project site, multi-
use trails would be developed to allow for passive recreation, such as walking, jogging, and bicycling. A
formal improved park space is not proposed.
Landscaping on the project site would reflect the native vegetation in the area. For example, landscaping
within the open space areas would include the planting of native vegetation along the sound wall proposed
for the eastern border of the site, adjacent to the Paradise Rod & Gun Club, and revegetation of any
disturbed areas with native vegetation, consistent with the surrounding area.
Public Services and Utilities
The existing on-site water system consists of an on-site well at a depth of 735 feet. Water produced from
the well is currently sent to two 10,000-gallon above-ground storage tanks using a 75 horse power (hp)
turbine pump, and subsequently pulled from the tank using two 10 hp pumps and pressurized into a
distribution system through four pressure tanks. The water system is generally located near the center of
the southern border of the project site. The existing well was initially installed in 1999 for the purposes of
irrigating the Tuscan Ridge Golf Course and providing services to the associated bistro. The well was
subsequently used for potable water purposes by PG&E and ECC Constructors during their occupation of
the site. The water system is currently permitted as a domestic water supply through the Butte County
Environmental Health Division (Permit Number 04-09182) and the State Water Resources Control Board
(SWRCB) Division of Drinking Water.
11
A number of improvements to the existing on-site water system would be required in order to upgrade the
system to accommodate the proposed project, including the installation of an additional water supply well,
a water treatment system, a water distribution system, water meters at each service connection, and
additional water tanks for storage. The proposed water system would be subject to the standards and
monitoring requirements set forth by federal, State, and local laws, including, but not limited to, public health
standards of Title 22 of the California Code of Regulations (CCR), the California Safe Drinking Water Act,
and Butte County standards. The water distribution system and proposed second well would be constructed
in accordance with the California Waterworks Standards (Title 22, Chapter 16). The water system would
be capable of meeting the maximum daily demand of the proposed project, in accordance with Title 22,
Section 64554(c). Any additional water tanks needed to support the proposed development would be
constructed using materials that meet appropriate California Department of Forestry and Fire Protection
(CAL FIRE) standards. A minimum of 300,000 gallons of water storage is anticipated to be required to meet
minimum fire flows; however, the water storage requirements would be determined in consultation with the
Butte County Fire Department and CAL FIRE. A 500,000-gallon water tank is anticipated to be located in
the easternmost portion of the project site. A new permit through the SWRCB and/or Butte County
Environmental Health Division would be required to allow use of the system as a community water system.
The existing wastewater treatment system was constructed to serve the temporary base camp that provided
wildfire response efforts and currently operates under the SWRCB General Order 2014-0153-DWQ-R5309.
The existing system is currently designed with a peak flow capacity of 100,000 gallons per day (gpd), with
the capability to expand to up to 150,000 gpd. The treatment process currently include solids separation
and anaerobic digestion, aerobic digestion, media filtration, and ultraviolet light (UV) disinfection.
Processing is accomplished using septic tanks, aerobic treatment modules, and UV disinfection units. More
specifically, wastewater is pumped through four 40,000-gallon septic tanks then through one of four 25,000
gpd Presby multi-level treatment beds. Effluent from each Presby module is collected via gravity to a
connected 3,000-gallon collection pump tank with UV treatment, providing tertiary treatment. The treated
effluent is then routed through a two-inch force main to the evaporative ponds with bottom-mounted
aerators for disposal. The two ponds, located in the southernmost portion of the project site, are 48.6 and
6.1 acre-feet and have 3:1 (Horizontal:Vertical) interior and external slopes and a minimum 15-foot wide
crest that provides access around the perimeter. The containment system for the ponds consists of a 40-
mil high-density polyethylene (HDPE) geosynthetic liner, eight-ounce non-woven geotextile fabric, and a
leak collection/detection system to fully contain the treated effluent.
In order to adequately handle the wastewater generated by the proposed uses and the associated
wastewater characteristics, improvements to the existing wastewater system and additional infrastructure
are needed. For example, a new sewer collection system would be required in order to collect and convey
the wastewater from the proposed residential and commercial land uses to the treatment system. In addition
to the proposed residential and commercial land uses, the proposed project would include a new sanitary
waste disposal station that would be located at a cul-de-sac at the end of the proposed eastern entryway
to the project site, which would also serve as the main entrance to the mini storage use. The sanitary waste
disposal station is primarily intended to serve future patrons of the mini storage use, particularly by providing
a convenient location for dumping sewage waste from RVs and boats stored on-site. The sanitary waste
disposal station would include an adjacent 20,000-gallon septic tank, which would connect to the on-site
wastewater treatment system. Wastewater generated by the proposed uses, including wastewater from the
septic tank associated with the sanitary waste disposal station, would flow by gravity through a network of
eight- and 10-inch sewer laterals and mains located within the internal roadways to two new 20,000-gallon
equalization tanks located near the existing wastewater treatment system in the southwestern portion of
the project site. Grease interceptors would be installed, where necessary, to intercept fats, oils, and grease
(FOG) prior to entering the collection system. From the equalization tanks, wastewater would be pumped
through a new headworks/bar screen before being processed through the existing wastewater treatment
system (e.g., septic tanks, Presby modules, and UV disinfection). Effluent from the wastewater treatment
system would continue to be disposed of through the existing evaporative ponds, as well as pumped
through a new three-inch effluent force main to proposed spray dispersal fields to be located within the
open space area adjacent to the Skyway. A new Waste Discharge Requirements (WDR) Permit from the
SWRCB would be required for the proposed improvements to the existing wastewater treatment system.
Due to the capacity of the on-site wastewater treatment system, the opportunity exists for the sanitary waste
12
disposal station to accept sewage from additional sources, subject to SWRCB permitting requirements.
Additional specificity and analysis regarding the proposed sanitary waste disposal station will be included
in the EIR.
As noted in further detail below, the proposed on-site water and sewer systems are anticipated to be owned,
operated, and maintained by the PID, subject to Butte LAFCo approval of annexation into the District.
Stormwater generated on the project site would be collected by surface flow into a system of curbs and
gutters, vegetated swales, and drain inlets throughout the site that would allow the collected stormwater to
transition to the subsurface stormwater collection system of pipes that would convey the stormwater into
strategically located retention basins. The proposed stormwater drainage system would be designed in
compliance with the standards and requirements of Chapter 50, Stormwater Management and Discharge
Control, of the Butte County Code.
PG&E will provide electricity to the site by way of an existing on-site connection. Natural gas would not be
used at the site; however, propane or another form of gas may be used by both residential and commercial
users, for residential and commercial applications. As propane supply is not part of the proposed project, it
would be the responsibility of individual users to establish propane service from a local provider such as
Suburban Propane or Hunt Propane, both of which are located in Chico, California. Additionally, the
proposed project would be served by the Butte County Sheriff’s Department, California Highway Patrol
(CHP), Butte County Fire, and Chico Unified School District (grades K-12). Law enforcement would be
provided by the Sheriff’s Department, while traffic-related enforcement services would be provided by CHP.
The nearest Butte County Fire Station is South Chico Fire Station, located at 2334 Fair Street, Chico, which
is approximately 6.5 miles west from the site by road.
Minor Use Permit
The proposed project would include a request for the approval of a Minor Use Permit to allow for
development within the 350-foot SH Overlay Zone from Skyway Road pursuant to Section 24-42 C, Scenic
highway overlay zone, of the Butte County Code. While the majority of the proposed development would
be set back beyond the 350-foot SH Overlay Zone, the site entrances, as well as portions of the access
roads, sound walls, some residential backyards, and limited portions of the commercial development would
be located within the SH Overlay Zone.
Service Area Annexation
The proposed project would require annexation into the PID service area for water and sanitary sewer
service, subject to approval by Butte LAFCo. The annexation would apply only to the project site itself,
rather than the intervening area between the site and Paradise, California. Connections to PID’s existing
water distribution system would not be extended to the project site. Upon approval of all pertinent permits,
the PID would own, operate, and maintain the water and wastewater systems as an independent utility.
The existing permits to own and operate the water distribution and wastewater system would be transferred
to PID upon completion of the annexation process through Butte LAFCo.
1.5 Requested Entitlements
The proposed project would require County approval of the following:
General Plan Text Amendment;
PD Rezone;
Subdivision Map; and
Minor Use Permit for development within the SH Overlay Zone.
It should be noted that additional Minor Use Permits and/or Conditional Use Permits may subsequently be
required for specific commercial uses in the future.
13
In addition to the above County approvals, the project would also require the following approval by the Butte
LAFCo, as a Responsible Agency:
Annexation of the project site into PID service area for water and sewer service.
2.0 PROBABLE ENVIRONMENTAL EFFECTS AND SCOPE OF THE EIR
Consistent with Appendix G of the CEQA Guidelines, the County anticipates that the EIR will contain the
following chapters:
Aesthetics
Air Quality, Greenhouse Gas Emissions,
and Energy
Biological Resources
Cultural and Tribal Cultural Resources
Geology and Soils
Hazards and Hazardous Materials
Hydrology and Water Quality
Land Use and Planning/Population and
Housing
Noise
Public Services and Recreation
Transportation
Utilities and Service Systems
Wildfire
Effects Not Found to be Significant
Statutorily Required Sections
Alternatives Analysis
Each chapter of the EIR will include identification of the thresholds of significance, identification of project-
level and cumulative impacts, and the development of mitigation measures and monitoring strategies, as
required. The proposed EIR will incorporate by reference the Butte County General Plan, Butte County
General Plan EIR, and project-specific technical studies. The EIR will also include analysis necessary for
Butte LAFCo to use the EIR for their actions as a Responsible Agency.
The following paragraphs summarize the anticipated analyses that will be included in the EIR.
Aesthetics: The Aesthetics chapter of the EIR will summarize existing regional and project area aesthetics
and visual setting. To the extent applicable, the chapter will describe project-specific aesthetics issues such
as the SH Overlay Zone, scenic vistas, trees, historic buildings, existing visual character or quality of the
project area, as well as light and glare. Pursuant to Appendix G of the CEQA Guidelines, the focus of the
analysis concerning the project’s effects on visual character or quality of the project site and the surrounding
area will be on whether the proposed project will substantially degrade the existing visual character or
quality of public views of the site and the surrounding area. The chapter will be based in part on photo
simulations, which would show pre- and post-project views of the project site from key public vantage points.
Air Quality, Greenhouse Gas Emissions, and Energy. The air quality and greenhouse gas (GHG) emissions
analysis for the proposed project will be performed using the California Emissions Estimator Model
(CalEEMOD) software program and following Butte County Air Pollution Control District (BCAPCD) CEQA
Guidelines.
The air quality impact analysis will include a quantitative assessment of short-term (i.e., construction) and
long-term (i.e., operational) increases of criteria air pollutant emissions of primary concern (i.e., ROG, NOX,
and PM10). The project’s cumulative contribution to regional air quality will be discussed, based in part on
the modeling conducted at the project level. The analysis will also address any potential odor impacts that
may occur, as well as toxic air contaminant (TAC) emissions.
The GHG emissions analysis will include a quantitative estimate of carbon dioxide equivalent emissions
from the proposed project, including indirect emissions (e.g., electricity, propane) and construction
emissions. The chapter will include an analysis of the project’s consistency with the 2021 Butte County
Climate Action Plan (CAP).
14
The significance of air quality and GHG impacts will be determined in comparison to BCAPCD significance
thresholds. BCAPCD-recommended mitigation measures will be incorporated, if needed, to reduce any
significant air quality impacts, and anticipated reductions in emissions associated with proposed mitigation
measures will be quantified.
The chapter will also evaluate whether the proposed project could result in a potentially significant
environmental impact due to wasteful, inefficient, or unnecessary consumption of energy resources, during
project construction or operation. The discussion will also evaluate whether the proposed project would
conflict with or obstruct a State or local plan for renewable energy. The chapter will review the 2021 Butte
County CAP to identify energy-related measures that may be applicable to the proposed project.
Biological Resources. The Biological Resources chapter of the EIR will summarize the setting and describe
the potential project effects to plant communities, oak woodlands, wildlife, and wetlands, including adverse
effects on rare, endangered, candidate, sensitive, and other special-status species for the project site.
Effects associated with all on-site and off-site improvements will be included in the analysis. Analysis in the
chapter will be based on a Biological Evaluation Report and the proposed project will be evaluated for
consistency with the Butte Regional Conservation Plan (BRCP).
Cultural and Tribal Cultural Resources. The Cultural Resources analysis will describe the potential effects
to historical and archaeological resources from buildout of the proposed project. Analysis in the chapter will
be based on an Archaeological Inventory Survey prepared for the proposed project, which will include the
results of a field survey and records search. Effects associated with all on-site and off-site improvements
will be included in the analysis.
The Tribal Cultural Resources analysis will describe the potential effects to tribal cultural resources from
buildout of the proposed project. The County will conduct Native American tribal consultation pursuant to
Assembly Bill (AB) 52 and Senate Bill (SB) 18, the latter of which is required for the proposed project due
to the proposed General Plan Amendment. Any input from tribes will be incorporated into the Tribal Cultural
Resources chapter. Feasible and appropriate mitigation measures to avoid or reduce adverse impacts will
be identified, as needed.
Geology and Soils. The Geology and Soils chapter of the EIR will summarize the setting and describe the
potential effects from soil erosion, earthquakes, liquefaction, expansive/unstable soils, as well as identify
any known paleontological resources or unique geological features within the project area. The chapter will
be based primarily on a site-specific Geotechnical Engineering Report prepared for the proposed project,
as well as a paleontological records search.
Hazards and Hazardous Materials. The Hazards and Hazardous Materials chapter of the EIR will
summarize the setting and describe any potential for existing or possible hazardous materials within the
project area. The chapter will also assess the potential for the proposed project to create a significant
hazard to the public or environment through the routine transport, use, or disposal of hazardous materials.
Impacts of the environment on a project (as compared to impacts of a project on the environment) are
beyond the scope of required CEQA review. The California Supreme Court has held that, “CEQA does not
generally require an agency to consider the effects of existing environmental conditions on a proposed
project’s future users or residents. What CEQA does mandate… is an analysis of how a project might
exacerbate existing environmental hazards” (California Building Industry Assn. v. Bay Area Air Quality
Management Dist. (2015) 62 Cal.4th 369, 392). As such, the mere presence of possible hazardous
materials at the site or in the vicinity, should such exist, would be considered an existing environmental
condition and, thus, would not be considered an impact under CEQA. Rather, the proposed project could
have the potential to result in an impact associated with possible hazardous materials should the proposed
project exacerbate the existing conditions (e.g., contaminated soils become airborne during ground-
disturbing activities and expose construction workers or future residents of the proposed project). The
chapter will be based primarily on site-specific Phase I Environmental Site Assessment.
15
Hydrology and Water Quality. The Hydrology and Water Quality chapter of the EIR will summarize setting
information and identify potential impacts on stormwater drainage, flooding, groundwater, and water quality,
including stormwater runoff water quality. The Hydrology and Water Quality chapter will evaluate project-
related increases in impervious surfaces and stormwater flows, groundwater recharge and depletion,
increases in downstream flooding, and on-site facilities necessary to treat and possibility detain on-site
runoff. In addition, the chapter will evaluate impacts associated with alteration of the 100-year floodplain
limits and existing drainage patterns.
Land Use and Planning/Population and Housing. The Land Use and Planning/Population and Housing
chapter of the EIR will evaluate the consistency of the proposed project with the policies and regulations
included in the Butte County General Plan and County Code adopted for the purpose of avoiding or
mitigating an environmental effect. In addition, the chapter will include an evaluation of the potential for the
project to induce substantial unplanned population growth in the area, either directly or indirectly (e.g.,
through extension of roads or other infrastructure). Additionally, the chapter will include a discussion of
Butte County’s affordable housing requirements. The chapter will rely on information from the California
Department of Finance and the Butte County General Plan Housing Element.
Noise. The Noise chapter of the EIR will be based on a project-specific Noise Study. The chapter will
address potential noise impacts resulting from project construction and operation, including existing and
future traffic noise levels on the local roadway network. Noise-sensitive land uses or activities in the project
vicinity will be identified and ambient noise and vibration level measurements on, and in the vicinity of, the
project site will be conducted to quantify existing background noise and vibration levels for comparison to
the predicted project-generated levels. Operational noise levels will also be evaluated. Noise exposure
levels will then be compared to applicable significance criteria in the Butte County General Plan Noise
Element and CEQA. Feasible and appropriate mitigation measures to avoid or reduce adverse impacts will
be identified, as needed.
Public Services and Recreation. The Public Services and Recreation chapter of the EIR will evaluate
whether the proposed project could increase demands upon local services including fire, law enforcement,
schools, parks, and recreation. In accordance with Appendix G, the focus of the analysis will be on whether
the project’s demand would require physical alteration of, or need for new governmental facilities, in order
to maintain acceptable service ratios, response times, or other performance objectives, the construction of
which could cause significant environmental impacts.
Transportation. The Transportation chapter of the EIR will be based on a Transportation Impact Study (TIS)
prepared specifically for the proposed project. Impact determination for CEQA purposes will be based on
vehicle miles traveled (VMT), consistent with CEQA Guidelines Section 15064.3, which became effective
statewide on July 1, 2020. The VMT analysis will be quantitative in nature and will be prepared consistent
with Butte County’s current guidance regarding analysis of VMT.
The proposed project’s impacts to alternative modes such as pedestrian, bicycle and transit facilities will
be assessed based on their significance criteria contained in the adopted Butte County guidelines. The EIR
chapter will also include an analysis of the proposed project’s potential impacts related to conflicting with
applicable programs, policies, and ordinances addressing the circulation system, vehicle safety hazards,
and emergency access. Feasible and appropriate mitigation measures to avoid or reduce adverse impacts
will be identified, as needed.
Utilities and Service Systems. The Utilities and Service Systems chapter will evaluate the proposed
project’s increase in water supply demand and wastewater generation and identify any needed
improvements to the existing water and sewer infrastructure systems to accommodate demands from the
proposed project. The chapter will also evaluate the receiving landfill’s capacity to accommodate the
increase in solid waste associated with the proposed project. Electricity and propane service will also be
addressed in the chapter. The chapter will be based on existing information from the Butte County General
Plan and information obtained from direct consultation with appropriate service providers.
16
Wildfire. The Wildfire chapter of the EIR will address the questions in Section XX, Wildfire, of Appendix G
of the CEQA Guidelines. Specifically, the proposed project will be evaluated to determine if the project
would substantially impair an adopted emergency response plan or emergency evacuation plan. This will
include an evaluation of how the proposed project may impact evacuation patterns of nearby residents. In
addition, the chapter will consider whether the proposed project would exacerbate fire risk, as well as
whether the project would expose people or structures to significant post-fire risks, including downslope or
downstream flooding or landslides. Mapping prepared by CAL FIRE regarding fire hazard severity zones
will be reviewed, and the analysis will include consultation with CAL FIRE. The chapter will include
information from an Emergency Preparedness and Evacuation Plan (EPEP) to be prepared for the
proposed project.
Effects Not Found to be Significant. Section 15128 of the CEQA Guidelines states that an EIR shall contain
a brief statement indicating the reasons that various possible significant effects of a project were determined
not to be significant and were, therefore, not discussed in detail in the EIR. Accordingly, the Effects Not
Found to be Significant chapter of the EIR will include abbreviated discussions of impacts determined not
to be significant.
Statutorily Required Sections. Pursuant to CEQA Guidelines Section 21100(B)(5), the Statutorily Required
Sections chapter of the EIR will address the potential for growth-inducing impacts of the proposed project,
focusing on whether removal of any impediments to growth would occur with the proposed project. A
summary of the significant and unavoidable impacts identified within the EIR will be included in this chapter,
as well as a discussion of significant irreversible impacts. The chapter will generally describe the cumulative
setting for the proposed project; however, a detailed description of the subject-specific cumulative setting,
as well as analysis of the cumulative impacts, will be included in each technical chapter of the EIR.
Alternatives Analysis. In accordance with Section 15126.6(a) of the CEQA Guidelines, the EIR will include
an analysis of a range of alternatives, including a No Project Alternative. Consideration will be given to
potential off-site locations consistent with CEQA Guidelines, Section 15126.6(f)(2), and such locations will
be determined in consultation with County staff. If it is determined that an off-site alternative is not feasible,
the EIR will include a discussion describing why such a conclusion was reached. The project alternatives
will be selected when more information related to project impacts is available in order to be designed to
reduce significant project impacts. The chapter will also include a section of alternatives considered but
dismissed, if necessary. The Alternatives Analysis chapter will describe the alternatives and identify the
environmentally superior alternative. The alternatives will be analyzed at a level of detail less than that of
the proposed project; however, the analyses will include sufficient detail to allow a meaningful comparison
of the impacts. Such detail may include conceptual site plans for each alternative, basic quantitative traffic
information (e.g., trip generation), as well as a table that will compare the features and the impacts of each
alternative.