From:Paulsen, Shaina
To:BOS
Subject:Board Correspondence - FW: Request for Delay of Action/Extension of Time submitted in FERC P-619-000 by
Pacific Gas and Electric Company,et al.
Date:Tuesday, July 12, 2022 8:30:39 AM
Please see Board Correspondence below.
Shaina Paulsen
Associate Clerk of The Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, July 1, 2022 6:35 AM
Subject: Request for Delay of Action/Extension of Time submitted in FERC P-619-000 by Pacific Gas and Electric
Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 7/1/2022, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC),
Washington D.C.:
Filer: Pacific Gas and Electric Company
No Organization Found (as Agent)
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Request for Delay of Action/Extension of Time
Description: Pacific Gas and Electric Company submits Request for Extension of Time until December 31, 2023
to Address Recommendations 12 and 14 from 11th Part 12D Inspection Report for Bucks Creek Hydroelectric
Project under P-619.
To view the document for this Filing, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20220701-
5047__;!!KNMwiTCp4spf!EybC6Y2jDuT-88_bDglwwMu-
duABwyWJZw96L20Hl7vof9WtLhJOHyVvZo0oFgRVg9tJiqbO8Mn9zWVt3cjUfx8NR-_9i96VsOhm$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!EybC6Y2jDuT-
88_bDglwwMu-duABwyWJZw96L20Hl7vof9WtLhJOHyVvZo0oFgRVg9tJiqbO8Mn9zWVt3cjUfx8NR-
_9i85C024y$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!EybC6Y2jDuT-
88_bDglwwMu-duABwyWJZw96L20Hl7vof9WtLhJOHyVvZo0oFgRVg9tJiqbO8Mn9zWVt3cjUfx8NR-_9i0-
z0LRT$
or for phone support, call 866-208-3676.
245 Market Street
tƚǞĻƩ DĻƓĻƩğƷźƚƓ
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
June 30, 2022
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Extension of Time Request
Bucks Creek Hydroelectric Project, FERC No. 619
Dear Frank L. Blackett:
In accordance with ongoing efforts for
continuous improvement in achieving timely responses to filings requested in numerous
letter
presents, in Enclosure 1, newly proposed due dates for efforts to address near-term
coming due items in the Bucks Creek Hydroelectric Project (FERC No. 619). The
enclosure includes Extension of Time (EOT) requests for two items, including PG&E's
basis for them.
Should you have any technical questions concerning this matter, please contact PG&E
chief dam safety engineer, Dave Ritzman, at (415) 264-1795. For general questions,
please contact the manager of FERC compliance, Will Landreth, at (530) 782-0218.
Sincerely,
Will Landreth, P.E.
Interim Manager, FERC and DSOD Compliance
Enclosure:
1. Bucks Creek Extension of Time Request