HomeMy WebLinkAbout5.2.22 Board Correspondence - FW_ Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al. (2)
From:Paulsen, Shaina
To:BOS
Subject:Board Correspondence - FW: Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric
Company,et al.
Date:Monday, May 2, 2022 8:18:23 AM
Please see Board Correspondence below.
Shaina Paulsen
Associate Clerk of The Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Sunday, May 1, 2022 10:45 AM
Subject: Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking
on links, or replying..
On 4/29/2022, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas & Electric Company (as Agent)
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits Construction Schedule re Reservoir Remote Monitoring Installation in
Response to Comments in FERC April 21, 2022 for Round Valley Dam for DeSabla-Centerville Hydroelectric Project under P-803.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20220429-5586__;!!KNMwiTCp4spf!GnuhXvFoipatbNHSlAfdeMrNrIRj-
nMTg4i0Taguu29axuq_ODHY8NIY71aKfNyKHCpWKjv4RififVk6Mt2Ps-6CEeiJQ2QZE5u2$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!GnuhXvFoipatbNHSlAfdeMrNrIRj-
nMTg4i0Taguu29axuq_ODHY8NIY71aKfNyKHCpWKjv4RififVk6Mt2Ps-6CEeiJQ4p5ewmw$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!GnuhXvFoipatbNHSlAfdeMrNrIRj-
nMTg4i0Taguu29axuq_ODHY8NIY71aKfNyKHCpWKjv4RififVk6Mt2Ps-6CEeiJQ8BxaEwD$
or for phone support, call 866-208-3676.
tƚǞĻƩ DĻƓĻƩğƷźƚƓ
245 Market Street
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
April 29, 2022
Via Electronic Submittal (E-file)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Round Valley Dam, NATDAM No. CA00346
Reservoir Remote Monitoring Installation Comment Responses
Dear Frank L. Blackett:
This ) responses to Federal
Energy Regulatory Commission (FERC) comments regarding the submittal package for
installation of remote monitoring equipment at Round Valley Reservoir, which is part of
DeSabla-Centerville Hydroelectric Project, FERC No. 803. PG&E received
and conditional authorization to proceed with construction in a letter
dated April 21, 2022. this letter
(Enclosure 1).
has been adequately addressed and no further action is necessary. Should you have
s dam safety engineer,
Kaitlyn Daniels, at (707) 342-
coordinator, Jackie Pope, at (530) 254-4007.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure:
1. Response to FERC Comment Regarding Reservoir Remote Monitoring Installation
ENCLOSURE 1
Enclosure 1
DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Round Valley Dam, NATDAM No. CA00346
Response to FERC Comment
Regarding Reservoir Remote Monitoring Installation
In a letter to Pacific Gas and Electric Company (PG&E) dated April 21, 2022, the
Federal Energy Regulatory Commission (FERC) provided a comment regarding the
installation of remote monitoring equipment at Round Valley
Reservoir, which is part of PG DeSabla-Centerville Hydroelectric Project, FERC
No. 803is
response.
Comment 1:
Please provide a detailed construction schedule including milestone dates and
durations for completing the various work tasks associated with this project.
PG&E has prepared a construction schedule, below, which includes major milestone
dates and durations for the various work tasks associated with the project. PG&E plans
to perform this work when the reservoir is empty. Based on historic trends, construction
activities are expected to begin as soon as mid-July of 2022; however, these dates
depend on the reservoir level at these times and may shift slightly.
Phases and Key Milestones Target Completion Date
FERC approval (received conditional authorization) April 21, 2022
Permitting complete / environmental release to May 13, 2022
construction
Mobilization of construction crews July 18, 2022
Construction July 25, 2022
Project construction cleanup/demobilization October 5, 2022
FERC submission of final construction report February 1, 2023