From:Paulsen, Shaina
To:BOS
Subject:Board Correspondence - FW: Compliance Directives issued in FERC P-803-000
Date:Monday, May 9, 2022 8:00:14 AM
Please see Board Correspondence below.
Shaina Paulsen
Associate Clerk of The Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Thursday, May 5, 2022 3:55 AM
Subject: Compliance Directives issued in FERC P-803-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 5/4/2022, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Compliance Directives
Delegated Order
Description: Letter order authorizing Pacific Gas and Electric Company to immediately proceed with construction for the Slope Erosion Control Project etc. at DeSabla Forebay Dam,
part of the
DeSabla-Centerville Project under P-803.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20220504-
3071__;!!KNMwiTCp4spf!FC8T4We1akuOSFzYKl83K74EuF3V1bjt1kGkwyOrCTJgzTaJ7snaWPrxZF8WHbS1EqTgGpMKYnR-PP1I1S_2XiuHcBsxz8AvDx36$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!FC8T4We1akuOSFzYKl83K74EuF3V1bjt1kGkwyOrCTJgzTaJ7snaWPrxZF8WHbS1EqTgGpMKYnR-
PP1I1S_2XiuHcBsxz0hy7d4W$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!FC8T4We1akuOSFzYKl83K74EuF3V1bjt1kGkwyOrCTJgzTaJ7snaWPrxZF8WHbS1EqTgGpMKYnR-
PP1I1S_2XiuHcBsxzxorW_Pe$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
(415) 369-3300 Office (415) 369-3322 Facsimile
May 4, 2022
In reply refer to:
Project No. 803-CA
Mr. Jan Nimick, Vice President
Pacific Gas and Electric Company
Mail Code: N11E
PO Box 770000
San Francisco, CA 94177-0001
Re: Slope Erosion Control Project at DeSabla Forebay Dam
Dear Mr. Nimick:
This is in response to a letter dated April 14, 2022 from Mr. Robert Ellis that
submitted a revised Quality Control Inspection Program (QCIP) for the Slope Erosion
Control Project at DeSabla Forebay Dam, which is part of the DeSabla-Centerville
Project, FERC No. 803. We have reviewed the submittal, and we have no further
comments. PG&E is authorized to immediately proceed with construction.
During construction, we typically require monthly construction reports. However,
due to the short duration of this project, we will not require monthly construction reports.
Within 90 days of completion of construction of the facilities authorized by this letter, or
no later than October 1, 2022, you must file the following:
1. A final construction report, which addresses the applicable items in Enclosure 1.
2. The following construction certifications, which must be verified in accordance
with Title 18, Section 12.13 of the Code of Federal Regulations (18 CFR 12.13):
a. A certification by the Design Engineer that the project was constructed in
accordance with the design intent
2
b. A certification by the Quality Control Manager that the inspection and testing
program resulted in the conclusion that the project was constructed in
accordance with the plans and specifications reviewed by the Commission
c. A certification by the PG&E that the project was constructed in accordance
with the design intent and in accordance with the plans and specifications
reviewed by the Commission
Sample certifications are given in Enclosure 2.
3. Submit for Commission approval, revised Exhibits A, F, and G, as applicable, to
describe and show those project facilities as built. If you determine that
previously approved exhibits reflect the as-built facilities and no revisions are
necessary, you must file a letter stating the approved exhibits reflect the as-built
project facilities. To assist Commission staff in the review of any revised Exhibit
A, we strongly recommend that you file a revised Exhibit A, in its entirety, in two
forms:
a. A strikethrough format (i.e., strikethrough items to be removed, and underline
or bold items to be added to the exhibit), and
b. A final, clean copy incorporating the changes (i.e., without the strikethrough,
underline, and bold notations).
You must separate Exhibit F drawings from the other project exhibits, and label
and file them as Critical Energy Infrastructure Information (CEII) material under
18 CFR § 388.113. The submission should consist of, as applicable: 1) a public portion
consisting of a cover letter and the Exhibits A and G; and 2) a CEII portion containing
only the Exhibit F drawings.
Please eFile all revised exhibit drawings to the Secretary of the Commission with
the transmittal addressed as follows:
Ms. Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
If the plans and specifications are revised during the construction process, it is
rly coordinated between the
Design Engineer, the Resident Engineer, the Project Manager, the FERC, and PG&E,
prior to proceeding with the changes. Also, you are reminded that no changes may be
made to the operation of the project without first coordinating those proposed changes
with the FERC.
3
PG&E is responsible for ensuring completion of any necessary environmental
coordination with resource agencies as well as the procurement of any federal, state, or
local permits required for the work.
All required filings should be submitted
https://www.ferc.gov/ferc-online/overview. For all Dam Safety and Public Safety
Documents, select Hydro: Regional Office and San Francisco Regional Office from the
eFiling menu. The cover page of the filings must indicate that the material was eFiled.
For assistance with eFiling, contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY).
safety program. If you have questions, please contact Mr. Michael Vail at
(415) 369-3346.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
Enclosures:
1. Final Construction Report
2. Sample Final Construction Certifications
cc:
Ms. Sharon Tapia, Division Manager
CA Dept. of Water Resources
Division of Safety of Dams
P.O. Box 942836
Sacramento, CA 94236-0001
Items to be Addressed in Final Construction Report for the Enclosure 1
Slope Erosion Control Project at DeSabla Forebay Dam
FERC No. 803
FINAL CONSTRUCTION REPORTS FROM LICENSEES
The Final Construction Report should be submitted within 90 days of completion of the
work. This report should include all information pertinent to dam safety in a concise form. It
should be included in the project file and should be given to the independent consultant for his
or her safety inspection and analyses, if applicable. As such, the report should contain a
summary of information in each of the applicable sections indicated below (the information was
previously presented in the monthly reports). Construction difficulties should be reported under
the appropriate sections. For conciseness, test results should be presented in a tabular format,
with an indication of the applicable standards. Finally, in those cases where there is nothing to
report under a specific heading, a statement of non-applicability will suffice.
1. General. Briefly present the reason for construction and description of the work with dates of
the beginning and end of construction. Include reservoir drawdown and filing dates, and any
findings regarding the original structure.
2. Foundations. Discuss the condition of the foundation (faults, etc.) and the treatment of the
foundation. Attach a foundation mapping.
3. Embankments. Describe the equipment and the types of materials used in filters and fills.
Attach gradation and compaction requirements and all test results.
4. Concrete work. Describe the equipment and the types of materials used in all concrete work.
Include all grout test results and describe any surface treatments.
5. Anchors. Present a summary of any drilling operations, including boring logs; results of water
pressure tests; anchor design calculations, design loads, and specifications; results of grout tests;
results of proof and performance tests; and a summary of the acceptance criteria.
6. Instrumentation. Present plots of existing instrumentation readings taken during construction
if the readings are affected by the work. Include a plan and schedule for calibration of all new
instrumentation.
7. Drawings. Attach as-built drawings reduced in size to 8.5"x11" or 11"x17". The drawings
should include plan and section views, and details of the structures affected by the new work.
The plan and section views should show any new instrumentation that was installed as part of
the work.
Page 1 of 1
Enclosure 2
CERTIFICATION
By Design Engineer
CERTIFICATION OF CONSTRUCTION PAGE 1 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Design Engineer that the project was constructed in accordance
with the design intent.
*****************************************************************************
VERIFICATION
STATE OF CALIFORNIA \]
COUNTY OF \], SS:
The undersigned, being first duly sworn, states that he/she has read the above document
and knows the contents of it, and that all of the statements contained in that document are
true and correct, to the best of his/her knowledge and belief (per 18CFR Part 12,
Paragraph 12.13).
Design Engineer (Print Name)
Signature
\[STAMP\]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC \[SEAL\]
Enclosure 2
CERTIFICATION
By Quality Control Manager
CERTIFICATION OF CONSTRUCTION PAGE 2 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Quality Control Manager that the inspection and testing program
resulted in the conclusion that the project was constructed in accordance with the plans and
specifications reviewed by the Commission.
*****************************************************************************
VERIFICATION
STATE OF CALIFORNIA \]
COUNTY OF \], SS:
The undersigned, being first duly sworn, states that he/she has read the above document
and knows the contents of it, and that all of the statements contained in that document are
true and correct, to the best of his/her knowledge and belief (per 18CFR Part 12,
Paragraph 12.13).
Quality Control Manager (Print Name)
Signature
\[STAMP\]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC \[SEAL\]
Enclosure 2
CERTIFICATION
By Licensee or Exemptee
CERTIFICATION OF CONSTRUCTION PAGE 3 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Licensee or Exemptee that the project was constructed in
accordance with the design intent and in accordance with the plans and specifications
reviewed by the Commission.
************************************************************************
VERIFICATION
STATE OF CALIFORNIA \]
COUNTY OF \], SS:
The undersigned, being first duly sworn, states that he/she has read the above
document and knows the contents of it, and that all of the statements contained in
that document are true and correct, to the best of his/her knowledge and belief (per
18CFR Part 12, Paragraph 12.13).
For Licensee or Exemptee (Print Name)
Signature
\[STAMP\]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC \[SEAL\]