HomeMy WebLinkAbout12.23.22 Board Correspondence - FW Annual Spill Gate Testing Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:BOS
Subject:Board Correspondence - FW: Annual Spill Gate Testing Report submitted in FERC P-803-000 by Pacific Gas and
Electric Company,et al.
Date:Tuesday, December 27, 2022 8:47:31 AM
Please see Board Correspondence below.
Shaina Paulsen
Associate Clerk of The Board
Butte County Administration
25 County Center Drive, Suite 200, Oroville, CA 95965
T: 530.552.3304 | F: 530.538.7120
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, December 23, 2022 11:05 AM
Subject: Annual Spill Gate Testing Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et
al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 12/23/2022, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC),
Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas & Electric Company (as Agent)
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Annual Spill Gate Testing Report
Description: Pacific Gas and Electric Company submits 2022 Annual Spillway Gate Operation Certificate for the
DeSabla-Centerville Hydroelectric Project under P-803.
To view the document for this Filing, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20221223-
5106__;!!KNMwiTCp4spf!GJcoW-x4uC9hBOgm45EfSP3rz8m44-gEj-0NirnV0qMR4__ZmgFOq-
eGv7bJ0NzTthmhRkqWsQSgt646hBcFMB7Demk60sXQecfW$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!GJcoW-
x4uC9hBOgm45EfSP3rz8m44-gEj-0NirnV0qMR4__ZmgFOq-
eGv7bJ0NzTthmhRkqWsQSgt646hBcFMB7Demk60hrkzeYX$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!GJcoW-
x4uC9hBOgm45EfSP3rz8m44-gEj-0NirnV0qMR4__ZmgFOq-
eGv7bJ0NzTthmhRkqWsQSgt646hBcFMB7Demk60lulWsXr$
or for phone support, call 866-208-3676.
Power Generation
77 Beale Street
San Francisco, CA 94105
Mailing Address:
Mail Code N11D
P.O. Box 770000
San Francisco, CA 94177
December 23, 2022
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Philbrook Dam, NATDAM No. CA00345
2022 Annual Spillway Gate Operation Certificate
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
Enclosed is Pacific Gas and Electric Company’s (PG&E) notarized certificate for the 2022
spillway gate operations for the following dam:
FERC Project Dam Name Gate Type No. of
Gates
DeSabla-Centerville Hydroelectric Project, FERC
No. 803 Philbrook Dam Radial 1
The certificate (Enclosure 1) is being submitted pursuant to Part 12, Subpart E, Section
12.44(b) of the Federal Energy Regulatory Commission’s (FERC) regulations.
Should you have technical questions concerning this matter, please contact Roy Arnold, gates
and valves asset management lead engineer for PG&E, at (559) 575-5122. For general
questions, please contact Andrew Garcia, license coordinator for PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. Annual Spillway Gate Operation Certificates