HomeMy WebLinkAbout04.30.2024 Board Correspondence - FW_ General Correspondence issued in FERC P-96-000,et al.From:Clerk of the Board
To:Bennett, Robin; Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Hancock, LeAnne; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Lee, Lewis; McDonnell,
Susan; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nevers, Dawn
Subject:Board Correspondence - FW: General Correspondence issued in FERC P-96-000,et al.
Date:Tuesday, April 30, 2024 4:44:50 PM
Please see Board correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, April 30, 2024 1:18 PM
Subject: General Correspondence issued in FERC P-96-000,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 4/30/2024, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-96-000
P-137-000
P-175-000
P-233-000
P-606-000
P-619-000
P-803-000
P-1061-000
P-1121-000
P-1962-000
P-1988-000
P-2105-000
P-2106-000
P-2130-000
P-2310-000
P-2661-000
P-2687-000
P-2735-000
P-1354-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: General Correspondence
Description: Letter to Pacific Gas and Electric Company providing a comment on the 2024 planned outage schedule update for the Kerckhoff Project et al. under P-96 et al.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20240430-
3089__;!!KNMwiTCp4spf!AtXblAkihtdFX9PZ2E_WU5sT1u8nQ6AvfVpG4MCO_clwkUXFpzAPD49lafIdN-MikDFWxonjjSeZ4mX3fMvOkdjYrzfaJk03n6G_$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!AtXblAkihtdFX9PZ2E_WU5sT1u8nQ6AvfVpG4MCO_clwkUXFpzAPD49lafIdN-
MikDFWxonjjSeZ4mX3fMvOkdjYrzfaJvpAxi7t$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!AtXblAkihtdFX9PZ2E_WU5sT1u8nQ6AvfVpG4MCO_clwkUXFpzAPD49lafIdN-
MikDFWxonjjSeZ4mX3fMvOkdjYrzfaJvrpDllv$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION Office of Energy Projects Division of Dam Safety and Inspections – San Francisco Regional Office 100 First Street, Suite 2300 San Francisco, CA 94105-3084 (415) 369-3300 April 30, 2024 In reply refer to: Project Nos. 96, 137, 175, 233,
606, 619, 803, 1061, 1121 ,
1354, 1962, 1988, 2105, 2106,
2130, 2310 , 2661, 2687,
2735-CA VIA FERC Service Mr. Russell Cruzen, P.E., Director Power Generation, Asset Excellence Pacific Gas and Electric Company 300 Lakeside Dr. Oakland, CA 94612-3534 Re: 2024 Planned Outage Schedule Update Dear Mr. Cruzen: This is in response to a letter dated Oc tober 26, 2023 from Mr . Matthew Joseph regarding the 2024 planned outage schedule update for the projects listed in Table 1 of
the Enclosure. We have reviewed the updated schedule for the outages and have the
following comment: • Please notify us in the event the proposed outages vary by more than 30 days. We appreciate your continued efforts in this aspect of our dam safety program . If
you have any questions, please contact the FERC engineers listed in Table 1 that are
assigned to the specific projects. The FERC engineers’ phone numbers are listed in
Table 2. Sincerely, Frank L. Blackett, P.E. Regional Engineer Frank L Blackett, P.E.Digitally signed by Frank L
Blackett, P.E.
Date: 2024.04.30 12:31:53 -07'00'
Document Accession #: 20240430-3089 Filed Date: 04/30/2024
2 Enclosure cc: Ms. Sharon Tapia, Division Manager Division of Safety of Dams California Department of Water Resources P.O. Box 942836 Sacramento, CA 94236-0001 Document Accession #: 20240430-3089 Filed Date: 04/30/2024
PG&E Projects Addressed in 2024 Planned Outage Schedule Update Enclosure Page 1 of 1 Table 1. Projects Addressed in 2024 Planned Outage Schedule Update Project No. Project Name FERC Engineer 96 Kerckhoff Samuel Lee 137 Mokelumne River Vincent Vigil 175 Balch Ryan Tom 233 Pit No. 3 Diversion Fengg ang Ma 606 Kilarc Samuel Lee 619 Bucks Creek Eunhye Kim 803 De Sabla-Centerville Eunhye Kim 1061 Phoenix Ryan Tom 1121 Battle Creek Samuel Lee 1354 Crane Valley Samuel Lee 1962 Rock Creek-Cresta Eunhye Kim 1988 Haas-Kings River Ryan Tom 2105 Upper North Fork Feather River Eunhye Kim 2106 McCloud-Pit Fenggang Ma 2130 Spring Gap-Stanislaus Ryan Tom 2310 Drum-Spaulding Thao Bui / Mynul Chowdhury 2661 Hat Creek Nos. 1 and 2 Fenggang Ma 2687 Pit No. 1 Fenggang Ma 2735 Helms P owerhouse Ryan Tom Table 2. FERC Project Engineer Phone Numbers FERC Engineer Phone Number Samuel Lee (415) 369-3393 Vincent Vigil (415) 369-3315 Ryan Tom (415) 369-3347 Fenggang Ma (415) 369-3319 Eunhye Kim (415) 369-3321 Thao Bui (415) 369-3312 Mynul Chowdhury (415) 369-3313 Document Accession #: 20240430-3089 Filed Date: 04/30/2024
Document Content(s)
P-96-000 S62871 FY24 Schedule Planned Outages.pdf .........................1Document Accession #: 20240430-3089 Filed Date: 04/30/2024