HomeMy WebLinkAbout06.09.25 Board Correspondence - FW_ Procedural Motion submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen;
Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: Procedural Motion submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.
Date:Monday, June 9, 2025 4:45:39 PM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Monday, June 9, 2025 1:16 PM
Subject: Procedural Motion submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or
replying..
On 6/9/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
PG&E Corporation (as Agent)
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Procedural Motion
Description: Pacific Gas and Electric Company submits Request to be designated as a Non-Federal Representative for Consultation Section 7
of the Endangered Species Act re BW- 3 and BW-40 Temporary Flow Modification re the DeSabla-Centerville Project under P-803.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20250609-5170__;!!KNMwiTCp4spf!AQOzgGPuDaMP52rtelxMMRBWS1fXbKxj4t-
CQw1u2t9RqTHGVFQ7YoafYnWiC4fN8yMdx1v1u9gqIk3RuOuIFS_5ClRghkm2H76o$
To modify your subscriptions, click here:
CQw1u2t9RqTHGVFQ7YoafYnWiC4fN8yMdx1v1u9gqIk3RuOuIFS_5ClRghoaMihnb$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!AQOzgGPuDaMP52rtelxMMRBWS1fXbKxj4t-
CQw1u2t9RqTHGVFQ7YoafYnWiC4fN8yMdx1v1u9gqIk3RuOuIFS_5ClRghgdcpECm$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
June 9, 2025
Via Electronic Submittal (E-File)
Debbie-Anne Reese, Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
RE: DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
BW- 3 and BW-40 Temporary Flow Modification:
Delegation of Authority Regarding Section 7
Dear Secretary Reese:
On June 6, 2025, Federal Energy Regulatory Commission (FERC) issued a letter to Pacific
Gas and Electric Company (PG&E), regarding Section 7 consultation for a temporary flow
modification request for the DeSabla-Centerville Hydroelectric Project, FERC No. 803
(P803). This letter respectfully requests that FERC designate PG&E as its non-federal
representative to conduct informal consultation with the United States Fish and Wildlife
Service on the potential effects to foothill yellow-legged frogs (Rana boylii), and
conferencing on the northwestern pond turtle (Actinemys marmorata); when implementing
a temporary flow modification at compliance points BW-3 and BW-40, which are part of the
P803.
The temporary flow modification is being requested to support the 2025 Central Valley
Spring Run Chinook Salmon holding population in Butte Creek. Pursuant to 50 CFR
section 402.08, PG&E requests FERC designate PG&E as its non -federal representative
for informal consultation under the Section 7 of the Endangered Species Act.
For general questions, please contact Sky Ramirez-Doble, license coordinator for PG&E,
at (530) 250-7002.
Sincerely,
Megan Young
License Project Manager
cc: via email
Stephanie Millsap (USFWS) - Stephanie_Millsap@fws.gov
Brittany Reaves (USFWS)- Brittany_reaves@fws.gov
Document Accession #: 20250609-5170 Filed Date: 06/09/2025