HomeMy WebLinkAbout06.30.25 Board Correspondence_ FW_ Request for Delay of Action_Extension of Time submitted in FERC P-2310-000,et al. by Pacific Gas and Electric Company,et al. Power Generation 300 Lakeside Drive Oakland, CA 94612 Mailing Address: P.O. Box 28209 Oakland, CA 94604 June 30, 2025 Via Electronic Submittal (E-File) Frank L. Blackett, P.E., Regional Engineer Federal Energy Regulatory Commission Division of Dam Safety and Inspections 100 First Street, Suite 2300 San Francisco, CA 94105-3084 RE: Drum-Spaulding Hydroelectric Project, FERC No. 2310-CA Spring Gap-Stanislaus Hydroelectric Project, FERC No. 2130-CA Mokelumne River Hydroelectric Project, FERC No. 137-CA Bucks Creek Hydroelectric Project, FERC No. 619-CA Screening-Level Portfolio Risk Analysis for Multiple Dams – Extension of Time Request Dear Frank L. Blackett: This letter presents Pacific Gas and Electric Company’s (PG&E) request for an extension of time to complete a spillway screening-level risk analysis (SSLRA) and prioritize improvements at five of its spillways. PG&E is using the results of the SSLRA to support its long-term spillway capital improvement program (CIP). This extension of time request is accompanied by a reasoned basis for the request, per Title 18 of the Code of Federal Regulations, Section 12.40(d). PG&E submitted its original SSLRA plan and schedule in a letter to your office dated June 26, 2024. As communicated in the plan, PG&E proposed to conduct an in-person SSLRA workshop, prepare a report of the workshop findings, and perform a risk-informed evaluation to prioritize future spillway CIP projects. PG&E planned to complete the work by July 31, 2025. PG&E conducted the in-person SSLRA workshop in the fall of 2024 and is currently finalizing the workshop findings report. However, PG&E has elected to postpone its risk-informed prioritization of future spillway CIP projects. The postponement will allow PG&E to consider the results of two ongoing risk assessments when assigning priorities and scheduling the projects. PG&E’s long-term spillway CIP currently includes planned projects at fourteen spillways. As described in a letter to FERC, dated August 4, 2023, PG&E completed SSLRA and established a risk-informed schedule for projects at nine of the spillways in 2023. As part of the current SSLRA effort, PG&E is reevaluating its CIP portfolio to incorporate projects at five additional spillways. At the same time, PG&E is conducting FERC Part 12D comprehensive assessments (CA) of the spillways at Belden Forebay and Lake Almanor, which are part of the existing CIP portfolio. The CAs include Level 2 risk assessments (L2RA) that will supersede the SSLRAs completed in 2023. Document Accession #: 20250630-5185 Filed Date: 06/30/2025 Frank L. Blackett, P.E. Regional Engineer June 30, 2025 Page 2 Because the L2RAs are based on updated information and follow a more rigorous approach than was used for the SSLRAs, PG&E expects that results of the L2RAs will differ from the SSLRA results and have a significant impact on the risk-informed prioritization of projects in the spillway CIP portfolio. PG&E is scheduled to complete the L2RAs in the summer of 2025 and submit the results to FERC by December 1, 2025. To allow the Belden Forebay and Lake Almanor L2RA results to be included in the spillway CIP project reevaluation, PG&E respectfully requests an extension of time to submit the SSLRA workshop findings report and an updated prioritization and schedule for the spillway CIP project portfolio to FERC by February 27, 2026. Should you have technical questions concerning this matter, please contact Roy Arnold, program engineering lead, at 559-575-5122. For general questions, please contact Jackie Pope, license coordinator for PG&E, at (530) 254-4007. Sincerely, David L. Ritzman, P.E., G.E. Chief Dam Safety Engineer Document Accession #: 20250630-5185 Filed Date: 06/30/2025 Document Content(s) PGE20250630_MultipleProjects_EOT-SSLRAforSpillways.pdf....................1 Document Accession #: 20250630-5185 Filed Date: 06/30/2025 From:Clerk of the Board To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug Cc:Loeser, Kamie; Nuzum, Danielle Subject:Board Correspondence: FW: Request for Delay of Action/Extension of Time submitted in FERC P-2310-000,et al. by Pacific Gas and Electric Company,et al. Date:Monday, June 30, 2025 4:52:51 PM Please see Board Correspondence -----Original Message----- From: 'FERC eSubscription' <eSubscription@ferc.gov> Sent: Monday, June 30, 2025 12:25 PM Subject: Request for Delay of Action/Extension of Time submitted in FERC P-2310-000,et al. by Pacific Gas and Electric Company,et al. .ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying.. On 6/30/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.: Filer: Pacific Gas and Electric Company Pacific Gas & Electric Company (as Agent) Docket(s): P-2310-000 P-2130-000 P-137-008 P-619-000 Lead Applicant: Pacific Gas and Electric Company Filing Type: Request for Delay of Action/Extension of Time Description: Pacific Gas and Electric Company submits request for extension of time until 02/27/2026 to submit Screening-Level Portfolio Risk Analysis for Multiple Dams of the Drum-Spaulding Hydroelectric Project, et al. under P-2310, et al. To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20250630- 5185__;!!KNMwiTCp4spf!CRv5IAi6J2B9MibrXi1LFwiGO1YW8_oshVmI1vitKlM8lkis90ZuUIE6fFB3QHHefIcmv6e9WXYYcNW0Y9BHdqw0sIeqJ_LwvzTt$ To modify your subscriptions, click here: ------------------------------------------------------------------------ Please do not respond to this email. Online help is available here: https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!CRv5IAi6J2B9MibrXi1LFwiGO1YW8_oshVmI1vitKlM8lkis90ZuUIE6fFB3QHHefIcmv6e9WXYYcNW0Y9BHdqw0sIeqJ8FgIgBt$ or for phone support, call 866-208-3676.