Subject:Board Correspondence: FW: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
Date:Friday, July 25, 2025 11:04:24 AM
Please see Board Correspondence
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, July 25, 2025 10:55 AM
Subject: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 7/25/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits update to the schedule of planned outages in 2025 for the Bucks Powerhouse Unit 2 part of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20250725-
5082__;!!KNMwiTCp4spf!HxS2S30o4mEa34vg1H77IUIUDjOjrHBRtVdZsHbPzlqKpbMimCXfPlqWJwcopflUVsWoqR68u1EkhMHsl_v6y4q_7cCSIzygLGCw$
To modify your subscriptions, click here:
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!HxS2S30o4mEa34vg1H77IUIUDjOjrHBRtVdZsHbPzlqKpbMimCXfPlqWJwcopflUVsWoqR68u1EkhMHsl_v6y4q_7cCSI19rtweF$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
July 25, 2025
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Outage Schedule Update – Bucks Creek Unit 2
Dear Frank L. Blackett:
This letter presents an update to Pacific Gas and Electric Company's (PG&E) schedule of
planned outages which require dewatering of tunnels, conduits, or penstocks. Penstock
dewatering is required for the Bucks Powerhouse Unit 2, which is part of PG&E’s Bucks
Creek Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 619.
PG&E submitted the 2025 outage schedule to FERC on October 29, 2024 and updates on
January 17, 2025, March 7, 2025, and April 22, 2025.
Table 1: Bucks U2 Current Outage Schedule and Updated Outage Schedule
Current Outage Schedule
FERC
No. Region Location Description of Work Dewatered
Start
Date End Date
619 DeSabla Bucks
Creek
U2
Annual, Replace Shaft and
Bearings, Rewind and Restack
Unit, TSV Refurbish, Grizzly Frby
Dam LLO Repair, Grizzly Frby
Subsurface Debris Removal, Xfmr
Mgmt Relay/Protection package
upgrade
Penstock 1/1/2023 7/31/2025
Updated Outage Schedule
FERC
No. Region Location Description of Work Dewatered
Start
Date End Date
619 DeSabla Bucks
Creek
U2
Annual, Replace Shaft and
Bearings, Rewind and Restack
Unit, TSV Refurbish, Grizzly Frby
Dam LLO Repair, Grizzly Frby
Subsurface Debris Removal, Xfmr
Mgmt Relay/Protection package
upgrade
Penstock 1/1/2023 8/31/2025
Document Accession #: 20250725-5082 Filed Date: 07/25/2025
Frank L. Blackett, P.E., Regional Engineer
July 25, 2025
Page 2
The Bucks U2 outage extension is necessary due to delays caused by a pressure
boundary failure on the lower bonnet of the TSV. PG&E is currently evaluating both
temporary and permanent repair options. While the outage may extend beyond one month,
the team hopes to have more clarity in the coming weeks to support an additional
extension request. The extension will also account for the extensive testing required before
the unit can be safely returned to service. This routine maintenance outage will follow the
previously executed procedures that have been coordinated with your office.
If you have questions or comments regarding this matter, please contact Jamie Visinoni,
senior license coordinator for PG&E, at (530) 215-6676.
Sincerely,
Jamie Visinoni
On behalf of
Matthew Joseph
Supervisor, Hydro License Management
Document Accession #: 20250725-5082 Filed Date: 07/25/2025
Document Content(s)
PGE20250725_619_BucksCreek_Dewatering_Update.pdf .........................1
Document Accession #: 20250725-5082 Filed Date: 07/25/2025