HomeMy WebLinkAbout08.06.25 Board Correspondence_ FW_ Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug;
Zepeda, Elizabeth
Cc:Loeser, Kamie; Nuzum, Danielle
Subject:Board Correspondence: FW: Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.
Date:Wednesday, August 6, 2025 11:02:39 AM
Please see Board Correspondence
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Wednesday, August 6, 2025 10:15 AM
Subject: Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 8/6/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas & Electric Company (as Agent)
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Dam Safety Compliance Report
Description: Pacific Gas and Electric Company submits summaries and conclusions of efforts to address the action items from the 2025 Annual Dam Safety Inspection re the Bucks Diversion Dam, et al. of the Bucks Creek
Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20250806-
5097__;!!KNMwiTCp4spf!Bwwi_TxlXKDnse6jPzPV8YMdFkoEkBr5ceV0gTGBUXRIkjc8OI4mc39OxinxH_t1WdLosQGR9g7shpxyYMAs6v9Jq8TI8hS7ucrW$
To modify your subscriptions, click here:
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!Bwwi_TxlXKDnse6jPzPV8YMdFkoEkBr5ceV0gTGBUXRIkjc8OI4mc39OxinxH_t1WdLosQGR9g7shpxyYMAs6v9Jq8TI8hLf2Pxw$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
August 6, 2025
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Bucks Diversion Dam, NATDAM No. CA00331
Grizzly Forebay Dam, NATDAM No. CA00333
2025 Annual FERC Inspection – Summaries and Conclusions for Action Items
ENCLOSURE CONTAIN CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter reports on the completion of Pacific Gas and Electric Company's (PG&E) efforts
to address Action Items 1, 2, and 3 (I-1, I-2, and I-3) from the 2025 annual Federal Energy
Regulatory Commission (FERC) dam safety inspection of PG&E’s Bucks Creek
Hydroelectric Project, FERC No. 619. I-1 and I-2 are regarding Grizzly Forebay Dam and I-3 is
regarding Bucks Diversion Dam. FERC inspected the project facilities with PG&E staff on
June 23 and 24, 2025 and provided the action items to PG&E in a letter dated June 30, 2025.
Summaries and conclusions of PG&E’s efforts to address the action items are enclosed
with this letter (Enclosure 1).
PG&E believes I-1, I-2, and I-3 have been satisfactorily addressed based on the
information enclosed with this letter and no further action is necessary. Should you have
technical questions concerning this matter, please contact Ben Fontana, senior dam safety
engineer for PG&E, at (530) 762-9459. For general questions, please contact Andrew
Garcia, license coordinator for PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. Summaries and Conclusions for Action Items from the 2025 Annual FERC Dam Safety
Inspection
Document Accession #: 20250806-5097 Filed Date: 08/06/2025