HomeMy WebLinkAbout08.12.25 Follow-up - Five Mile Basin Documents Presenting at August 12 BOS MeetingFrom:Pack, Joshua
To:BOS
Cc:Hightower, Scott; Scott DeLeon; Nuzum, Danielle
Subject:Follow-up - Five Mile Basin Documents Presenting at August 12 BOS Meeting
Date:Tuesday, August 12, 2025 1:24:11 PM
Attachments:PW.Five-Mile Basin Update August 2025.2.PowerPoint.pdf
Revised Emergency Rationale Letter with attachment.pdf
Thank you for the opportunity to provide an update on the Five-Mile Basin and for the
Board’s direction in addressing the short-term concerns.
At today’s meeting, the Board requested some of the documentation previously shared with
the Board and the public. I’ve included a copy of the emergency rationale letter outlining the
urgent need for action, as well as the PowerPoint presentation I presented earlier today. These
are public documents, so please feel free to share them with stakeholders as appropriate.
I will continue to provide updates to the Board on our next steps in the coming months.
As always, I appreciate and value your continued support of this project and our department. –
Josh
Joshua Pack
Director of Public Works
7 County Center Drive Oroville, CA 95965
530.538.7681 Phone
530-538-7171 Fax
jpack@buttecounty.net
Five Mile Basin Flood ConcernsShort-Term Treatment Alternatives
Joshua Pack
Butte County Director of Public Works
Board of Supervisors
August 12, 2025
Five-Mile Basin
Background Since June 2025
Department directed to explore short-term alternatives
Coordination with regulatory agencies and stakeholders
Engaged with State and Federal Representatives
Chico City Council –scheduled to consider adoption of
resolution supporting County action on August 19th
Regulatory agency status –permits submitted
Regional Water Quality Control Board (RWQCB)
California Department of Fish and Wildlife (CDFW)
United States Army Corps of Engineers (USACE)
Federal earmark funding was unsuccessful
Park Fire -Upcoming Winter Concerns
Second winter post-fire may present
increased risks:
Roots fully decayed with minimal regrowth
Minimal vegetation to help stabilize slopes
Increased potential for debris flows,
mudslides, and flooding
Increased risk to Chico and
surrounding communities
Short-Term Urgency Action Alternatives
Alternative 1 –Routine maintenance actions
Alternative 2 –Sediment removal
Alternative 3 –Targeted treatments to support stormwater
conveyance
Alternative 1 –Routine Maintenance
Focus on treatment actions currently under our Routine
Maintenance Agreement (RMA) with CDFW
Provides limited benefit
Replicates 2025 winter storm season response -mobilize staff
and resources to mitigate issues
Largely dependent on storm size and severity
Avoid actions that would violate existing regulatory agency
permits or authority
Alternative 2 –Sediment Removal
Restore Basin to original condition as constructed in the
1960s
Removal of nearly 70,000 cubic yards of material
Address scour issues near Big Chico Structure
Removal of vegetation and storm debris
Creates additional space in the Basin
Alternative 2 –Concerns
During a storm, extra capacity is filled by floodwaters
Work may impact the ability to discharge floodwaters
efficiently out of the Basin
May not have tangible impacts on flood levels
Increased risk of sediment deposit with unpredictable
impacts on floodwaters
Significant costs (>$4 million)
Doesn’t address root issues or resolve short-term concerns
May lead to considerable regulatory violations
Alternative 3 –Targeted Treatments
Targeted treatments to improve stormwater conveyance
and address short-term flood risk
Channel excavation to redirect flow depths & velocities away from Big
Chico Diversion Structure
Make repairs to scour damage at Big Chico Diversion Structure
Reduce impacts from vegetation
Redistribute stormwater flows
Support sustainable operations
Reduce the risk of additional sediment loads
Findings –Sycamore Weir and Lindo Channel
Sediment does not appear to affect flows negatively
Woody vegetation in recently deposited sands risks
encroaching on flows, potentially raising flood elevations
These Structures do not need significant amounts of urgent
treatment
Findings –Big Chico Creek and Structure
Big Chico Creek approach to structure has narrowed from
180 feet to 50 feet
Sediment load has created a natural levee, directing
stormwater flows directly at the structure
Structure designed to handle a fraction of stormwater flows
during peak events
Fast-moving water adds pressure, which may increase
flood water elevations higher
Floodwaters eroding the adjacent levee, potentially
affecting structural integrity of levee and structure
Targeted Treatment Areas of Focus
1
234
Big Chico Creek and Structure
Levee of sediment (hatched area)
diverts stormwater flows directly
into Big Chico Creek
Stormwater rises quickly due to
Big Chico Structure’s capacity
Floodwaters are diverted (blue
arrow), creating significant scour
This activity threatens the levee
and structure
Vegetation Concerns
Small zone of dense, mid-channel
vegetation
Emerging saplings and other
vegetation at Sycamore Weir
Has potential to increase flood
surface elevations
Vegetation has grown more dense
this spring and summer
Findings –Big Chico Creek
Rediverting and reestablishing stormwater flows to Lindo
and Sycamore can provide much-needed relief to Big
Chico Creek Structure
Lindo and Sycamore were designed to handle most of the
stormwater flow
Alternative 3 –Targeted Treatments
Alternative 3 –Targeted Treatments
Delivered through the Job Order Contracting Program
20-day project duration
Install a construction entrance to the basin
Cleaning and grubbing
Channel slot excavation and reformation
Off -haul additional sediment and gravel
Project completion before October 15
Estimated cost of $500k
Budget amendment approved by the Board earlier today
Alternative Comparisons
Criteria
Alternative 1
Routine
Maintenance
Alternative 2
Sediment Removal
Alternative 3
Targeted Treatments
Benefit Minimal Brief, temporary
stormwater storage
Up to 3 feet reduction in
peak surface elevations
Permanence No No Yes -Self-sustaining
Regulatory
Risk
Minimal Considerable to
severe
Modest to High
Costs Minimal Likely >$4 million $500,000
Fully Funded Yes –CSA 24 No –supplemental
action needed
Yes –CSA 24
Board Action
Provide direction to staff
1144 65th Street, Suite B
Oakland, CA 94608
(510) 250-9189
August 8, 2025
Joshua Pack, Director
Butte County Department of Public Works
7 County Center Drive
Oroville, CA 95965
RE: 5-Mile Basin Emergency Action Rationale
Mr. Pack:
Following receipt of the attached email dated August 7th from Matthew Roberts, a representative of the
Corps of Engineers, wherein Mr. Roberts states there is no indication of an immediate threat to life,
property, or essential infrastructure in order to support an Emergency Activity Project under the Regional
General Permit #8 (Emergency Activities), please accept this letter outlining NCE’s rationale for urgent
actions to be taken during the dry season to address significant flood risks at the 5 Mile Basin facility above
the City of Chico California. By way of this correspondence, we respectfully request that you initiate official
action by your Board of Supervisors and the City Council for the City of Chico to concur with the findings
and recommendations of this letter.
Background
NCE was engaged by Butte County Public Works to develop alternatives to reduce flood risk related to 5
Mile Basin. This facility has received limited maintenance over the last 20 years, and the recent (2024) Park
Fire and associated peak flow events in November 2024 and February 2025 have resulted in community
concerns regarding flood risk at the facility. Potential concerns were also raised by State Agencies as
described in the Watershed Emergency Response Team (WERT) report for the Park Fire, which states
“Flood control infrastructure on Big Chico Creek at the 5-Mile Diversion System (BC-04) may be
impacted by increased postfire streamflow, sedimentation, and debris accumulation…[and]
aggradation along the diversion system has altered the hydraulics such that an elevated head
develops on the Big Chico Creek gates that causes flows above design limits to pass.”
The WERT report identifies future risks from the 2024 Park Fire that intensively burned a significant portion
of the Big Chico Creek upper watershed. The result (already observed over the 2024/5 winter) was larger
floods than expected (up to 70% larger relative to similar pre-fire rainfall volumes), and substantially more
sediment production. Extensive post-fire sand bar and floodplain deposits can be observed between the 5
Mile facility and the mouth of the watershed (roughly 2 miles upstream). Some of these deposits are 5-6
feet deep.
P a g e | 2
The engineering and geomorphology of the facility’s existing conditions are complex. The original facility
was designed and constructed in the 1960s by the US Army Corps of Engineers (USACE). The USACE
“stilling basin” design objective for the facility is to slow and distribute flows into three primary
downstream channels (Sycamore, Lindo, and Big Chico). However, over the last 2 decades, a significant
accumulation of bedload sediments (primarily gravels and cobbles in a sandy matrix) and emergent riparian
vegetation (willows, sycamores, alder, cottonwoods, and others) have developed along the right bank of
Big Chico Creek immediately downstream of the pedestrian bridge, and opposite the hydraulically smooth
flood wall along the left bank. Additionally, substantial erosion of several key landforms associated with
the original 1960-era design have widened the channel from a design width of 140 ft to as much as 240 ft
(the natural channel width is closer 50—70 ft), and have resulted in a loss of part of a levee extension that
partially protected the Big Chico structure from direct head-on flow orientations. The existing configuration
funnel flows directly at the Big Chico Creek Diversion and affects flows entering the 5 Mile Basin in a
manner that significantly reduces channel stability within the facility. The result is a current channel
expression that directs up to 12-foot-deep flows with estimated velocities of 8-15 ft/s directly into the Big
Chico headwall structure (per the City’s HECRAS model). Furthermore, a roughly 8500 ft2 (0.2 acre) patch
of dense vegetation has encroached into the active floodway at a critical location within the facility. This
“wall” of vegetation increases the water surface elevation during large events by roughly 1.0 to 2.4 feet and
has established itself as an effective grade control on the bed of the channel, elevating the bed by 4 feet
relative to the downstream reach.
A graphic illustration of this feature is shown in Figure 1 below.
Figure 1) Significant sediment accumulation and riparian vegetation along the west bank of Big Chico Creek
is highlighted above.
P a g e | 3
More critical (and urgent) is the potential containment risk for the Q100 design flow. Using a 1D, steady
state hydraulic model (HECRAS), Northstar concluded that the Q100 storm would be contained by the
facility with 1.7 feet of freeboard in the vicinity of Big Chico diversion. The City of Chico’s HECRAS model
(developed by Wood Rodgers) indicates Q100 water surface elevation equal to, or just slightly below
(within a few tenths of a foot) the existing levee / headwall elevation. However, as steady-state 1D models,
neither study appears to factor the runup effect associated from velocity head, and neither study factored
the effect of vegetation that currently exists within the basin. The City of Chico model shows velocity of 8-
15 ft/s within the vicinity of Big Chico diversion structure, which would theoretically super-elevate the flood
surface against the headwall by an additional 1.0-3.5 ft. If these preliminary calculations are correct, the
Q100 storm event is likely to overtop the Big Chico headwall and/or surrounding levee.
Given the information described above, NCE focused our review on immediate flood risks related to the
current condition of 5-Mile Basin. A summary of current impacts to the physical structure and flows into the
facility include:
1. Channel alignment now forces 100% of peak flows directly into the headwall structure for the Big
Chico Diversion, which is only capable of passing 10-15% of these flows
2. Big Chico Creek approaching the Big Chico diversion structure has been narrowed from a design
width of 140 ft to 50 ft under existing conditions.
3. The reduced opening into the 5-Mile Basin has resulted in high-velocity flows which has caused
localized scour adjacent to the base of the levee directly above the Big Chico Creek Diversion and
excavated approximately 0.9 acres of inset floodplain that was part of the original 1960-era design.
4. Dense riparian vegetation has encroached within a 100 ft longitudinal section of the active channel,
increasing water surface elevations by an estimated 1.0 to 2.4 feet.
5. The super-elevation of flood water surface, together with the increase in flood water elevations due
to vegetation suggest the Big Chico Creek Diversion Structure and/or the adjacent levees are
incapable of containing 100-year storm event flows.
• According to both post-event field evidence and first-person reports, the February 4, 2025
event came within a few tenths of a foot of overtopping the levee (and may have even
“splashed” over in a few locations). That event (estimated at 10,000 cfs) was only 5/8ths of
the USACE design storm of 16,000 cfs.
6. The 2024 Park Fire effects are likely to
a) Continue to deliver large volumes of sediments (sands, silts, and clays)
b) Increase the magnitude, frequency, and possibly duration of peak flows
c) Increase the bedload transport rate of gravels entering the facility
P a g e | 4
These findings suggest a strong need to address the current condition with an emergency project prior the
upcoming winter season, which may deliver additional peak flows that will stress the facility. The risk to
the downstream community and infrastructure of not taking immediate emergency action include:
• Increased risk of flooding of residential properties and businesses
• Impacts on roadway, water, and sewer infrastructure
• Increased threat to public safety
• Potential for significant monetary impacts to local property owners, businesses, and government
agencies
Proposed Actions
NCE has identified 5 urgent, short-term treatments that should be addressed prior to this coming winter
that will assist in reducing short term flood risk. The core of NCE’s approach is allowing the river to do much
of the work (as intended by the original 1960’s design) of re-distributing sediment in ways that support
long-term, sustainable function of the facility. We note that these actions are the first step in what the
County envisions as a long-term management strategy to update and restore function of the 5-Mile facility.
Given the urgency of these issues, and the limited time to address them before the winter season arises,
NCE is seeking regulatory relief from the typical permitting process to expedite construction of these
emergency actions.
The objective is to reduce flow depths and velocity (to the extent practicable) away from the Big Chico
diversion headwall, making repairs to damage within the Basin from the 2024/5 winter, and reduce the
negative effects of local vegetation. NCE expects these actions to reduce the flood surface elevation in the
event of a large peak flow event during this upcoming winter season. These actions are premised on our
current understanding of the system and will be subject to change pending ongoing hydraulic modeling
efforts.
Emergency treatments include:
1) Restoring / re-activating a historic back-channel to divert flows away from Big Chico diversion.
This action involves light “pilot-channel” excavation (working estimate of 1500 cubic yards) and
construction of temporary hydraulic structures (rock vanes and/or graded riffle) to guide natural
flows into this relict channel feature.
2) Filling two 4.5-foot-deep scour holes immediately adjacent to the levee and Big Chico diversion
structure. These scour holes risk undercutting the levee, and possibly the structural integrity of the
diversion headwall and/or levee. Long-term solutions will likely require restoring or improving the
levee geometry in this vicinity.
3) Removing emerging trees / shrubs that have naturally recruited in recently deposited (Park Fire)
sands immediately upstream of Sycamore Weir. These emerging trees and shrubs risk negatively
P a g e | 5
affecting the performance of the weir, potentially increasing water surface elevations in the facility
pool during peak events.
4) Carefully and selectively thin / prune about 1/3 acre of existing stands of dense mid-channel
vegetation (shrubs and trees). This vegetation directly impinges flows and acts as a de facto grade
control, resulting in about 2 feet of additional gravel deposits from last winter. These trees also
likely increase the water surface elevation during extreme events. Note, we anticipate leveraging
much of this vegetation for future restoration of the adjacent inset floodplain, so treatments will be
conservative.
5) Selective experiments to support future sediment transport and restoration design / management
studies. This may include local pot-hole sampling, tiny sediment traps (trenches / pits), tracer
studies, scour piles, or similar. These may involve some instrumentation infrastructure (e.g.,
datalogger enclosures, conduit, etc). Details are currently under development.
NCE’s proposed emergency treatments are designed to minimize impacts to habitat and recreational values
while addressing these urgent issues. The information gained from this work will also inform continued
long-term management planning.
For additional information, please feel free to contact Scott DeLeon, our Principal Project Manager,
Sincerely,
NCE
Scott DeLeon
Principal Project Manager
Michael Liquori
Principal Water Resources Practice Lead
Attachment
From:Roberts, Matthew James CIV USARMY CESPK (USA)
To:Blodow, Carson@Waterboards; Jepson, Lillian M CIV (USA)
Cc:Pack, Joshua; Scott DeLeon; Emily Pullman
Subject:RE: Butte County 5-Mile Basin Emergency Maintenance Project - Application for 401 Certification
Date:Thursday, August 7, 2025 1:04:18 PM
Attachments:image003.png
image004.png
Carson,
Good afternoon. Lilly Jepson will serve as the U.S. Army Corps of Engineers Project Manager for this
action; however, she is currently on leave this week and will be attending mandatory training next
week.
We understand from your recent communication with the applicant that you are reviewing the
nature of the proposed impacts and whether they should be characterized as temporary or
permanent. Based on our preliminary review and the information provided to date, it does not
appear that the proposed activity qualifies for authorization under Regional General Permit 8
(Emergency Activities), as there is no indication of an immediate threat to life, property, or essential
infrastructure. We wanted to ensure that this understanding is clearly communicated at the outset
of the coordination process.
The Corps remains committed to working collaboratively with the Water Board and the applicant to
evaluate the proposed activity through the standard permitting procedures, consistent with
applicable regulations under Section 404 of the Clean Water Act.
Please don’t hesitate to reach out if you would like to schedule a time to discuss further.
Respectfully,
Matthew Roberts
Chief, CA North Section
Regulatory Division/Sacramento District
US Army Corps of Engineers
(Primary) 530-723-3355
(Secondary) 530 223-9538
(fax) 530-223-9539
*We want your feedback! Take the survey: https://regulatory.ops.usace.army.mil/ords/f?p=136:4
* Our customer service hours are 9am to 3pm Monday through Friday.
* Visit our website at www.spk.usace.army.mil/Missions/Regulatory.aspx for more info and to sign up
for public notices.