Subject:Board Correspondence - FW: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
Date:Tuesday, October 14, 2025 11:33:57 AM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, October 14, 2025 10:55 AM
Subject: Project Operations Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 10/14/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits Brief Construction Report for the 115-kV Transmission Line Rebuild Phase II Project at the Grizzly Powerhouse of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20251014-
5231__;!!KNMwiTCp4spf!FlYOUsFHrpyGZiJ7v0jbxr4wYFzie6NhWzTsfN12cLMEFKp8sPPgYjzEkNONkzLuZhmemBGzksamFGBG254aJkx0fxEJHzajkrng$
To modify your subscriptions, click here:
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!FlYOUsFHrpyGZiJ7v0jbxr4wYFzie6NhWzTsfN12cLMEFKp8sPPgYjzEkNONkzLuZhmemBGzksamFGBG254aJkx0fxEJHzkaq7MD$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
October 14, 2025
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Grizzly Powerhouse
Brief Construction Report - 115-kV Transmission Line Rebuild, Phase II
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
On June 21, 2024, the Federal Energy Regulatory Commission (FERC) issued a letter
authorizing Pacific Gas and Electric Company (PG&E) to proceed with construction of the
115-kV Transmission Line Rebuild – Phase II Project, part of the Bucks Creek Hydroelectric
Project (FERC Project No. 619). As part of that authorization, PG&E was required to file a
brief construction report for the Phase II project.
The brief construction report is provided as (Enclosure 1) to this letter.
PG&E appreciates FERC’s continued support for the effort to rebuild the Grizzly Tap. If you
have any technical questions regarding this matter, please contact Handel Chavez, Senior
Transmission Line Engineer, at (415) 349-0831. For general questions, please contact Jamie
Visinoni, license project manager at (530) 215-6676.
Sincerely,
Kyle Ingvoldsen, P.E.
Supervisor, Power Generation Project Engineering
Enclosure: CUI//CEII – DO NOT RELEASE
1. Brief Report Summarizing Work for the 115 kV Transmission Line Rebuild, Phase II,
prepared by PG&E and dated October 13, 2025
cc: via email w/enclosure:
Valentina Guzman, City of Santa Clara – Vguzman@SantaClaraCA.gov
Paulo Rocha, City of Santa Clara - procha@santaclaraca.gov
Diane Asuncion, City of Santa Clara – dasuncion@santaclaraca.gov
Document Accession #: 20251014-5231 Filed Date: 10/14/2025