HomeMy WebLinkAbout10.28.25 Board Correspondence - FW_ Part 12 Consultant Safety Inspection Reports submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen;
Teeter, Doug; Zepeda, Elizabeth
Cc:Loeser, Kamie; Nuzum, Danielle
Subject:Board Correspondence - FW: Part 12 Consultant Safety Inspection Reports submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.
Date:Tuesday, October 28, 2025 4:29:27 PM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, October 28, 2025 1:50 PM
Subject: Part 12 Consultant Safety Inspection Reports submitted in FERC P-619-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 10/28/2025, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas & Electric Company (as Agent)
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Part 12 Consultant Safety Inspection Reports
Description: Pacific Gas and Electric Company submits 12th Part 12D Periodic Inspection Report re the Bucks Diversion Dam of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20251028-
5180__;!!KNMwiTCp4spf!CcwFBRSKLVVyWBku3yf3PxcjFmoAP2CNmSDb1ETn8XTjjUKtutvoq7LFAvfgzRl5Zek8ikGMi_P65Mgg_KmXTu45Oj-YaTp8HaPF$
To modify your subscriptions, click here:
YafBzNf9p$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!CcwFBRSKLVVyWBku3yf3PxcjFmoAP2CNmSDb1ETn8XTjjUKtutvoq7LFAvfgzRl5Zek8ikGMi_P65Mgg_KmXTu45Oj-
YacA34Km2$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
October 28, 2025
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Bucks Diversion Dam, NATDAM No. CA00331
12th Part 12D Inspection – Periodic Inspection Report
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter presents the periodic inspection (PI) report for the 12th Part 12D safety inspection
for Bucks Diversion Dam, which is part of Pacific Gas and Electric Company’s (PG&E) Bucks
Creek Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 619. The
report was prepared in accordance with Title 18 of the Code of Federal Regulations (CFR),
Section 12.36. FERC authorized the inspection plan and independent consultant (IC) team for
this dam in a letter to PG&E dated February 11, 2025. PG&E provided the PI pre-inspection
preparation report to FERC in a letter dated May 16, 2025.
The PI report is enclosed with this letter for FERC review (Enclosure 1). In accordance with
Title 18 of the CFR, Section 12.41, PG&E will prepare plans and schedules for addressing IC
recommendations. PG&E will submit the plans and schedules to FERC by January 1, 2026.
Should you have technical questions concerning this matter, please contact Ben Fontana,
senior dam safety engineer for PG&E, at (530) 762 -9459. For general questions, please
contact Andrew Garcia, license coordinator for PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. 12th Part 12D Inspection, Periodic Inspection Report, Bucks Diversion Dam, prepared
by HDR Engineering and dated October 20, 2025
Document Accession #: 20251028-5180 Filed Date: 10/28/2025
Document Content(s)
PGE20251028_619_BucksDiversion_P12PI_InspRpt_Ltr.pdf......................1
Document Accession #: 20251028-5180 Filed Date: 10/28/2025