HomeMy WebLinkAbout12.15.25 Board Correspondence - FW_ General Correspondence issued in FERC P-619-000From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen;
Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: General Correspondence issued in FERC P-619-000
Date:Monday, December 15, 2025 1:35:24 PM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Monday, December 15, 2025 12:26 PM
Subject: General Correspondence issued in FERC P-619-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links,
or replying..
On 12/15/2025, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: General Correspondence
Description: Letter to Pacific Gas and Electric Company discussing the 10/14/2025 brief construction report documenting the 115-kV
Transmission Line Rebuild Phase II work at the Bucks Creek Powerhouse, part of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20251215-3076__;!!KNMwiTCp4spf!COiVCWo7V0Q0kKXO6BBK3kDfgNRC5G-
5OtydtBJdTJkHNGuww1DG_bIL_Hu06cj4FNjzn_hUxs4S5qilH0k4iSo3oBxmhTkICg9K$
To modify your subscriptions, click here:
5OtydtBJdTJkHNGuww1DG_bIL_Hu06cj4FNjzn_hUxs4S5qilH0k4iSo3oBxmhQ3DkAXB$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!COiVCWo7V0Q0kKXO6BBK3kDfgNRC5G-
5OtydtBJdTJkHNGuww1DG_bIL_Hu06cj4FNjzn_hUxs4S5qilH0k4iSo3oBxmhZ8zNsVa$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
December 15, 2025
In reply refer to:
Project No. 619-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland, CA 94612-3534
Re:115-kV Transmission Line Rebuild –Phase II
Dear Mr. Cruzen:
This is in response to a letter dated October 14, 2025, from Mr. Kyle Ingvoldsen,
that submitted a brief construction report documenting the 115-kV Transmission Line
Rebuild Phase II work at Bucks Creek Powerhouse, which is part of the Bucks Creek
Hydroelectric Project, FERC No. 619. We have reviewed the submittal, and we have no
comments.
We appreciate your continued efforts in this aspect of our dam safety program.If
you have questions, contact Ms. Eunhye Kim at (415)369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
Document Accession #: 20251215-3076 Filed Date: 12/15/2025
Frank L Blackett Digitally signed by Frank L Blackett
Date: 2025.12.15 11:37:46 -08'00'
Document Content(s)
P-619-000_97475_115kV GrizzlyTap-P2_FCR.docx.pdf .........................1