Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, December 5, 2025 10:06 AM
Subject: Compliance Directives issued in FERC P-619-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 12/5/2025, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Compliance Directives
General Correspondence
Delegated Order
Description: Letter to Pacific Gas and Electric Company providing comments on the 07/16/2025 hazard tree removal plan for the Bucks Lake Dam, part of the Bucks Creek Hydroelectric Project
under the P-619.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20251205-
3039__;!!KNMwiTCp4spf!BXaTUEMOmtPeAmsOT9_nA7kyg1FNLTuMrB_JWeAk7e39PHfLjfU1BC690LQ6S9ixqrpz8l3r5lg2s-gFwfbkrEouO-rVuNjUyQ7C$
To modify your subscriptions, click here:
gFwfbkrEouO-rVuIF73ulC$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!BXaTUEMOmtPeAmsOT9_nA7kyg1FNLTuMrB_JWeAk7e39PHfLjfU1BC690LQ6S9ixqrpz8l3r5lg2s-
gFwfbkrEouO-rVuJR42Glw$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
December 5, 2025
In reply refer to:
Project No. 619-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland, CA 94612-3534
Re:Tree Removal
Dear Mr. Cruzen:
This is in response to a letter dated July 16, 2025,from Mr. Robert Ellis
submitting a hazard tree removal plan for Bucks Lake Dam, which is part of the Bucks
Creek Hydroelectric Project, FERC No. 619. We have reviewed the submittal,which
indicates that the tree removal project will potentially consist of three separate projects
over the next 10 years. We have following comments:
1.Your request of a target completion year of 2035 is unacceptable for the
following reasons:
a.Refer to our authorization letter dated March 13, 2025 where we
requested that you provide a brief report documenting the work within
90 days completion of the tree removal or by no later than March 31,
2027, whichever comes first.If additional time is required beyond this
date, you must request an extension of time with an exact due date the
report will be submitted.
b.The access road and spillway projects are scheduled to occur
somewhere in the next 3 to 10 years. With the changes already noted in
your approach to these projects, we cannot authorize tree removal
without having precise designs that could influence the permitting of the
access road and spillway project.
2.You state that the work will occur after September 1st because of our comment
regarding additional consultation required for work between February 15th and
August 31st in any given year. We remind you that any work started after
Document Accession #: 20251205-3039 Filed Date: 12/05/2025
2
September 1st must be completed prior to February 15th of the following year
or the additional consultation with the agencies noted in our March 13, 2025,
letter is required.
3.Provide an updated submittal requesting authorization only for the trees at the
toe of the dam not associated with the future spillway or access road project.
Provide a specific date for the completion of the removal of these trees.
Within 45 days of the date of this letter, provide a response to our comments or a
plan and schedule to address our comments. File your submittal using our eFiling system
at https://www.ferc.gov/ferc-online/overview. For all Dam Safety and Public Safety
Documents, select Hydro: Regional Office and San Francisco Regional Office from the
eFiling menu. The cover page of the filing must indicate that the material was eFiled.
For assistance with eFiling, contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY).
We appreciate your continued efforts in this aspect of our dam safety program. If
you have any questions, contact Ms. Eunhye Kim at (415)369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
cc:
Erik Malvick -Division Manager
CA Dept. of Water Resources
Division of Safety of Dams
P.O. Box 942836
Sacramento, CA 94236-0001
c/o Shawn.Jones@water.ca.gov
Document Accession #: 20251205-3039 Filed Date: 12/05/2025
Frank L Blackett Digitally signed by Frank L Blackett
Date: 2025.12.05 09:36:56 -08'00'