HomeMy WebLinkAbout12.05.25 Board Correspondence - FW_ Delegated Order issued in FERC P-619-000From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens,
Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: Delegated Order issued in FERC P-619-000
Date:Friday, December 5, 2025 4:27:49 PM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, December 5, 2025 1:26 PM
Subject: Delegated Order issued in FERC P-619-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 12/5/2025, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Delegated Order
Description: Letter to Pacific Gas and Electric Company accepting the 10/20/2025 plan and schedule to address Part 12D Field Inspection follow-up items for the Grizzly Forebay Dam et al.,
parts of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20251205-
3057__;!!KNMwiTCp4spf!AmlNrwBENvPgdgA5CCEEUeQx2XJ0MxBdw8yjbpbK3lAv42fUVWjNE2pCgaCCi8bVXjbXXSd-9wLoLmlVa4c_PKTemRaJMJS2-6uj$
To modify your subscriptions, click here:
9wLoLmlVa4c_PKTemRaJMBxIykTZ$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!AmlNrwBENvPgdgA5CCEEUeQx2XJ0MxBdw8yjbpbK3lAv42fUVWjNE2pCgaCCi8bVXjbXXSd-
9wLoLmlVa4c_PKTemRaJMDn99Gkf$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
December 5, 2025
In reply refer to:
Project No.619-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland, CA 94612-3534
Re:2025 Follow-up Part 12D Field Inspections
Dear Mr.Cruzen:
This is in response to a letter dated October 20, 2025,from Mr. Robert Ellis that
submitted a plan and schedule to address Part 12D field inspection follow-up items for
Grizzly Forebay Dam and for Lower Bucks Lake Dam,which are part of the Bucks
Creek Hydroelectric Project,FERC No. 619. The plan and schedule for submittal of
multiple items by the multiple dates in your letter is acceptable
File your submittal using our eFiling system at https://www.ferc.gov/ferc-
online/overview. When eFiling, select Hydro: Dam Safety; San Francisco Regional
Office from the eFiling menu. The cover page of the filing must indicate that the
material was eFiled. For assistance with eFiling, contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY).
We appreciate your cooperation in this aspect of our dam safety program. If you
have any questions, contact Ms. Eunhye Kim at (415)369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
Document Accession #: 20251205-3057 Filed Date: 12/05/2025
Frank L Blackett Digitally signed by Frank L Blackett
Date: 2025.12.05 12:52:43 -08'00'