HomeMy WebLinkAbout11.25.25 Board Correspondence - FW_ Delegated Order issued in FERC P-803-000From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy;
Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: Delegated Order issued in FERC P-803-000
Date:Tuesday, November 25, 2025 10:33:09 AM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, November 25, 2025 9:46 AM
Subject: Delegated Order issued in FERC P-803-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 11/25/2025, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Delegated Order
Description: Letter to Pacific Gas and Electric Company accepting the 09/04/2025 plan and schedule to address the Dam Safety Inspection Follow-up Items No. 1 through No. 4
of the Philbrook Main Dam et al. for the DeSabla-Centerville Project under P-803.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20251125-
3058__;!!KNMwiTCp4spf!GsQISF1JbMzHl62RE7C_dcWVHqDqIxMtv7EKcOVU9Pe13JYY_e4J7jmSRZi0-QrsoA_e8V_9a-4Bd6OIQKWfHViyryDu0EijHE_0$
To modify your subscriptions, click here:
QrsoA_e8V_9a-4Bd6OIQKWfHViyryDu0NgQvqhV$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!GsQISF1JbMzHl62RE7C_dcWVHqDqIxMtv7EKcOVU9Pe13JYY_e4J7jmSRZi0-
QrsoA_e8V_9a-4Bd6OIQKWfHViyryDu0Jynifeo$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
November 25, 2025
In reply refer to:
Project No. 803-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland, CA 94612-3534
Re:2025 Dam Safety Inspection Follow-up
Dear Mr. Cruzen:
This is in response to a letter dated September 4, 2025,from Mr. Robert Ellis that
submitted a plan and schedule to address follow-up items no. 1 through no. 4 from the
2025 annual dam safety inspection of Philbrook Main Dam and Round Valley Dam,
which are parts of DeSabla-Centerville Project, FERC No. 803. The plan and schedule to
address the 2025 inspection follow-up items by the multiple dates outlined in your letter
is acceptable.
File your submittal using our eFiling system at https://www.ferc.gov/ferc-
online/overview. When eFiling, select Hydro: Dam Safety; San Francisco Regional
Office from the eFiling menu. The cover page of the filing must indicate that the material
was eFiled. For assistance with eFiling, contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY).
We appreciate your continued efforts in this aspect of our dam safety program. If
you have any questions, contact Ms. Eunhye Kim at (415) 369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
Document Accession #: 20251125-3058 Filed Date: 11/25/2025
Frank L Blackett Digitally signed by Frank L Blackett
Date: 2025.11.25 08:53:52 -08'00'