HomeMy WebLinkAbout01.07.26 Board Correspondence - FW_ General Correspondence issued in FERC P-619-000From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod;
Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.;
Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: General Correspondence issued in FERC P-619-000
Date:Thursday, January 8, 2026 8:04:20 AM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Wednesday, January 7, 2026 12:46 PM
Subject: General Correspondence issued in FERC P-619-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 1/7/2026, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: General Correspondence
Description: Letter to Pacific Gas and Electric Company discussing the 03/17/2025 response to FERC's comment
on a Monthly Construction Report for the Spillway Rehabilitation Project at the Lower Bucks Lake Dam, part of the
Bucks Creek Project under P-619.
To view the document for this Issuance, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20260107-
3060__;!!KNMwiTCp4spf!EPIWgilAd-
BKdXcF05JPKB360WF7YGb3DV7QtH5D3XvUZpLANBZA9J91amzf4ci5GprXblUMHF7fd91-
QSMMzV4jQ0KOscDvPuna$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!EPIWgilAd-
BKdXcF05JPKB360WF7YGb3DV7QtH5D3XvUZpLANBZA9J91amzf4ci5GprXblUMHF7fd91-
QSMMzV4jQ0KOsfWr435a$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!EPIWgilAd-
BKdXcF05JPKB360WF7YGb3DV7QtH5D3XvUZpLANBZA9J91amzf4ci5GprXblUMHF7fd91-
QSMMzV4jQ0KOsRFm3j93$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
January 7, 2026
In reply refer to:
Project No. 619-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland,CA 94612-3534
Re:September 2024 Monthly Construction Report for Spillway Rehabilitation Project
at Lower Bucks Lake Dam
Dear Mr. Cruzen:
This is in response to a letter dated March 17, 2025,from Mr. Matthew Joseph that
submitted a response to our comment on a monthly construction report (September 2024)
for the Spillway Rehabilitation Project at Lower Bucks Lake Dam, which is part of the
Bucks Creek Project, FERC No. 619.We have reviewed the submittal, and we have no
comments.
We appreciate your continued efforts in this aspect of our dam safety program.If
you have questions, contact Ms. Eunhye Kim at (415)369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
Document Accession #: 20260107-3060 Filed Date: 01/07/2026
Frank L Blackett Digitally signed by Frank L Blackett
Date: 2026.01.07 11:58:01 -08'00'