HomeMy WebLinkAbout02.23.26 FW_ Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric CompanyFrom:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug;
Zepeda, Elizabeth
Cc:Loeser, Kamie; Nuzum, Danielle; Cannon, Jamie
Subject:FW: Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
Date:Monday, February 23, 2026 1:48:03 PM
Please see Board Correspondence
Sharleen L Krater
Administrative Analyst Supervisor
Butte County Administration
25 County Center Drive, Suite 200 • Oroville, CA 95965
T: 530.552.3353
www.buttecounty.net | skrater@buttecounty.ca.gov
.
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Monday, February 23, 2026 1:16 PM
Subject: Dam Safety Compliance Report submitted in FERC P-619-000 by Pacific Gas and Electric Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 2/23/2026, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-619-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Dam Safety Compliance Report
Description: Pacific Gas and Electric Company submits response to FERC's 01/08/2026 Comment 1 on the 2025 Annual Dam Safety Inspection of the Bucks Storage Dam of the Bucks Creek Hydroelectric Project under P-619.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20260223-
5158__;!!KNMwiTCp4spf!FLdGIbtP1JCmcmV1CKG8aDUZxxyLuhaQDNhndsO14Klg8SFatU_Tcn59aLC75_tABGWH7RekF8PHUspbQxhJ9dGL360pfAx-Kx-D$
To modify your subscriptions, click here:
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!FLdGIbtP1JCmcmV1CKG8aDUZxxyLuhaQDNhndsO14Klg8SFatU_Tcn59aLC75_tABGWH7RekF8PHUspbQxhJ9dGL360pfLmUV5Dy$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
February 23, 2026
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Bucks Creek Hydroelectric Project, FERC No. 619-CA
Bucks Storage Dam, NATDAM No. CA00332
2025 Annual FERC Dam Safety Inspection –
Response to FERC Comment 1
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter presents Pacific Gas and Electric Company's (PG&E) response to address the
Federal Energy Regulatory Commission’s (FERC) comment (C-1) on PG&E’s summary
and conclusion to address Action Item 1 (I-1) from the 2025 annual FERC dam safety
inspection of PG&E’s Bucks Creek Hydroelectric Project, FERC No. 619. I-1 is regarding
Bucks Storage Dam. PG&E provided its summary and conclusion for I-1 to FERC in a
letter dated July 17, 2025. PG&E received C-1 in a letter dated January 8, 2026.
PG&E's response to C-1 is enclosed with this letter (Enclosure 1).
Should you have technical questions concerning this matter, please contact Ben Fontana,
senior dam safety engineer for PG&E, at (530) 762 -9459. For general questions, please
contact Jackie Pope, senior license coordinator for PG&E, at (530) 254-4007.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. FERC Comment Regarding Action Item 1 from the 2025 Annual FERC Dam Safety
Inspection
Document Accession #: 20260223-5158 Filed Date: 02/23/2026