HomeMy WebLinkAbout07.05.2024 Board Correspondence - FW_ Compliance Directives issued in FERC P-803-000From:Clerk of the Board
To:Bennett, Robin; Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Lee, Lewis; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney,
Kathleen; Teeter, Doug; Zepeda, Elizabeth; Loeser, Kamie
Cc:Nevers, Dawn
Subject:Board Correspondence - FW: Compliance Directives issued in FERC P-803-000
Date:Wednesday, July 10, 2024 8:49:28 AM
Please see Board correspondence -
LeAnne Hancock
Management Analyst I
Butte County Administration
T. 530.552.3314
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, July 5, 2024 2:55 PM
Subject: Compliance Directives issued in FERC P-803-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 7/5/2024, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Compliance Directives
Delegated Order
Description: Letter authorizing Pacific Gas and Electric Company to proceed with repairing the road to DeSabla Powerhouse, part of the DeSabla-Centerville Hydroelectric Project under P-803.
To view the document for this Issuance, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20240705-
3047__;!!KNMwiTCp4spf!GmqdlrVsID_dv31csG7V58Jz47MwjvuNY1COWG5p2xARpMOejLMSrAAxn4eBi23lHS2dGj9A2gF-nqU560eJTw4ZcGQdgNwMF-Q4$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!GmqdlrVsID_dv31csG7V58Jz47MwjvuNY1COWG5p2xARpMOejLMSrAAxn4eBi23lHS2dGj9A2gF-
nqU560eJTw4ZcGQdgAK1h0RE$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!GmqdlrVsID_dv31csG7V58Jz47MwjvuNY1COWG5p2xARpMOejLMSrAAxn4eBi23lHS2dGj9A2gF-
nqU560eJTw4ZcGQdgMhEzH_G$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections – San Francisco Regional Office
100 First Street, Suite 2300
San Francisco, CA 94105-3084
(415) 369-3300
July 5, 2024
In reply refer to:
Project No. 803-CA
VIA FERC Service
Mr. Russell Cruzen, P.E., Director
Power Generation, Asset Excellence
Pacific Gas and Electric Company
300 Lakeside Dr.
Oakland, CA 94612-3534
Re: Authorization Request for Road Repair for DeSabla Powerhous e
Dear Mr. Cruzen:
This is in response to a letter dated April 11, 2024, from Mr. Kyle Ingvoldsen, that
submitted an authorization request to repair the road to DeSabl a Powerhouse, which is
part of DeSabla-Centerville Hydroelectric Project, FERC Project No. 803. We have
reviewed the submittal, and we have the following comment:
x Mr. Justin Welty is listed as having authority to stop work as shown in the
Quality Control Inspection Program Organizational Chart. Howev er,
Mr. Welty’s resume was not included with the submittal. Provide Mr. Justin
Welty’s resume for our review. He must be authorized to have stop work
authority before performing that function.
Provided that you address the above comment within 10 days of t he date of this
letter, you are immediately authorized to proceed with construc tion. Failure to
adequately address our comments within 10 days will require a s uspension of all work
until the comment is addressed.
You are responsible for ensuring the completion of any necessary environmental
coordination with resource agencies as well as the procurement of any federal, state, or
local permits required for the work.
Document Accession #: 20240705-3047 Filed Date: 07/05/2024
2
Within 90 days of completion or by January 30, 2025, submit a brief report
documenting the road repair. File your submittal using our eFi ling system at
https://www.ferc.gov/ferc-online/overview . When eFiling, select Hydro: Dam Safety and
San Francisco Regional Office from the eFiling menu. The cover page of the filing must
indicate that the material was eFiled. For assistance with eFi ling, contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll fre e), or
(202) 502-8659 (TTY).
We appreciate your continued efforts in this aspect of our dam safety program. If
you have any questions, please contact Ms. Eunhye Kim at (415) 369-3321.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
cc:
Ms. Sharon Tapia, Division Manager
CA Dept. of Water Resources
Division of Safety of Dams
P.O. Box 942836
Sacramento, CA 94236-0001
Frank L Blackett, P.E.
Digitally signed by Frank L
Blackett, P.E.
Date: 2024.07.05 11:15:38 -07'00'
Document Accession #: 20240705-3047 Filed Date: 07/05/2024
Document Content(s)
P-803-000 S64700 S64701_DS PH Road Repair_Auth.pdf........................1