HomeMy WebLinkAbout10.16.2024 Board Correspondence - FW_ Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:BOS; Loeser, Kamie
Cc:Nevers, Dawn
Subject:Board Correspondence - FW: Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and
Electric Company,et al.
Date:Wednesday, October 16, 2024 8:12:05 AM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Wednesday, October 16, 2024 5:55 AM
Subject: Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 10/16/2024, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC),
Washington D.C.:
Filer: Pacific Gas and Electric Company
Pacific Gas & Electric Company (as Agent)
Docket(s): P-2107-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Dam Safety Compliance Report
Description: Pacific Gas and Electric Company submits Authorization Request to Replace Radial Bypass Gate
Hoist and Controls at the Poe Dam of the Poe Hydroelectric Project under P-2107.
To view the document for this Filing, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20241016-
5035__;!!KNMwiTCp4spf!C7W-RWiWJC6AUk-KfZENs5GKTrkdxSjWiHKngYgMMPVknUShU-
EsOuwazDfbFE1z3EKftCOiAbvMLU_4WVcQoiiLjoIklWsmTHdm$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!C7W-
RWiWJC6AUk-KfZENs5GKTrkdxSjWiHKngYgMMPVknUShU-
EsOuwazDfbFE1z3EKftCOiAbvMLU_4WVcQoiiLjoIklTR3aphK$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!C7W-RWiWJC6AUk-
KfZENs5GKTrkdxSjWiHKngYgMMPVknUShU-
EsOuwazDfbFE1z3EKftCOiAbvMLU_4WVcQoiiLjoIklfq9O4b4$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
October 15, 2024
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Poe Hydroelectric Project, FERC No. 2107-CA
Poe Dam, NATDAM No. CA00328
Authorization Request to Replace Radial Bypass Gate Hoist and Controls
ENCLOSURES CONTAIN CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter presents Pacific Gas and Electric Company’s (PG&E) submittal package for the
project to replace the hoist and controls for the radial bypass gate at Poe Dam, which is part
of PG&E’s Poe Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No.
2107. The purpose of the project is to improve the hoist equipment to safely operate the
radial bypass gate for flow use. The new system will include new anchors, connections, and
the upgraded gate hoist and control system.
Enclosed with this submittal are final 100-percent project documents, which consist of the
project description (Enclosure 1), gate hoist specifications (Enclosure 2), supporting
calculations (Enclosures 3 and 4), design drawings (Enclosures 5 and 6), the design criteria
memorandum (Enclosure 7), and the quality control inspection program (Enclosure 8). PG&E
has reviewed the documents prepared by consultants and concurs with the information
presented therein.
PG&E plans to release the project to construction on August 1, 2025, to support a
construction mobilization on August 8, 2025. PG&E plans to provide a final construction
report within 90 days of completing construction. If a final construction report has not yet
been provided, PG&E will provide an update on the project status and a plan and schedule
for further action by March 30, 2026.
PG&E respectfully requests FERC authorization to proceed with the project. Should you have
technical questions concerning this matter, please contact Chris Tomes, project engineer for
Document Accession #: 20241016-5035 Filed Date: 10/16/2024
Frank L. Blackett, P.E., Regional Engineer
October 15, 2024
Page 2
PG&E, at (530) 531-7976. For general questions, please contact Andrew Garcia, license
coordinator for PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosures: CUI//CEII – DO NOT RELEASE
1. Project Description, Poe Dam Replace Radial Bypass Hoist and Controls Project,
prepared by PG&E and dated September 26, 2024
2. Bypass Gate Hoist Specification for Pacific Gas & Electric Poe Dam Bypass Gate Hoist
and Control Project, prepared by Mesa Associates, Inc., and dated June 28, 2022
3. Poe Dam Bypass Gate Hoist Replacement (Calculations), prepared by Mesa Associates,
Inc., and dated September 13, 2024
4. Poe Dam – Bypass Gate Hoist and Control Project, Calculation Package, prepared by
Timberland Equipment Limited and dated June 28, 2024
5. 100% Design Drawings, Civil Facility, prepared by Mesa Associates, Inc., and dated
September 13, 2024
6. 100% Design Drawings, Gate Hoist, prepared by Timberland Equipment Limited and
dated March 28, 2024
7. Poe Dam Bypass Gate Hoist Replacement, Design Criteria Memorandum, prepared by
Mesa Associates, Inc., and dated August 5, 2024
8. Poe Dam Bypass Gate Hoist Replacement, Quality Control Inspection Program, Revision
1, prepared by PG&E and dated September 26, 2024
cc: via hard copy w/enclosures
Sharon Tapia, Division Manager
Department of Water Resources
Division of Safety of Dams
2720 Gateway Oaks Drive, Suite 300
Sacramento, CA 95833
Document Accession #: 20241016-5035 Filed Date: 10/16/2024