HomeMy WebLinkAbout12.3.2024 Board Correspondence - FW_ Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Lee, Lewis; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda,
Elizabeth; Loeser, Kamie
Cc:Nuzum, Danielle
Subject:Board Correspondence - FW: Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.
Date:Monday, December 9, 2024 4:47:30 PM
Please see Board Correspondence -
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, December 3, 2024 5:05 AM
Subject: Project Operations Compliance Report submitted in FERC P-803-000 by Pacific Gas and Electric Company,et al.
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 12/3/2024, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
PG&E Corporation (as Agent)
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Project Operations Compliance Report
Description: Pacific Gas and Electric Company submits status update re the Return to Service for Butte Creek Canal of the DeSabla-Centerville Hydroelectric Project under P-803.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20241203-
5017__;!!KNMwiTCp4spf!FH2_qTvqQ0o0v2s0tCU5Edk9dZXpd0IVYfpchckvZRcX2WXWOUyvzdH0DsrjP3Gwx2oH2kqPcIvV1t7irmpA64oFzbu-wo2JFMDQ$
To modify your subscriptions, click here:
whRU5OA7$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!FH2_qTvqQ0o0v2s0tCU5Edk9dZXpd0IVYfpchckvZRcX2WXWOUyvzdH0DsrjP3Gwx2oH2kqPcIvV1t7irmpA64oFzbu-wgL-
PoRH$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
December 2, 2024
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Butte Canal – Return to Service Status Update
Dear Frank L. Blackett:
This letter presents a status update regarding the operational status of Butte Canal,
which is part of Pacific Gas and Electric Company's (PG&E) DeSabla-Centerville
Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 803. On
March 14, 2024, PG&E committed to providing FERC a final decision regarding the
future of Butte Canal by December 1, 2024. PG&E has decided that it will not pursue
returning Butte Canal to service because of the extent and cost of the necessary
repairs, which would negatively impact PG&E customers. As a result, flows will remain
in Butte Creek and will not be diverted for generation purposes .
As required by the November 19, 2024, FERC Notice of Violation (NOV), PG&E will
indicate PG&E’s future plans for the ultimate disposition of Butte Canal, or plans for
filing an amendment to the project license or modifying our relicense application to
remove it from the project, by February 17, 2025.
If you have questions or comments regarding this matter, please contact Sky Ramirez-
Doble, license coordinator for PG&E, at (530) 250-7002.
Sincerely,
Janet Walther
Director, Hydro Licensing
Document Accession #: 20241203-5017 Filed Date: 12/03/2024