HomeMy WebLinkAbout05.08.26 Board Correspondence - FW_ Dam Safety Compliance Report submitted in FERC P-1121-000,et al. by Pacific Gas and Electric CompanyFrom:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater,
Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda,
Elizabeth
Cc:Loeser, Kamie; Cannon, Jamie
Subject:Board Correspondence - FW: Dam Safety Compliance Report submitted in FERC P-1121-000,et al. by Pacific Gas and Electric
Company
Date:Friday, May 8, 2026 8:24:55 AM
Please see Board Correspondence -
Lewis Lee
Administrative Technician - Confidential
Butte County Administration
25 County Center Drive, Suite 200 • Oroville, CA 95965
T: 530.552.3326
www.buttecounty.ca.gov | lelee@buttecounty.ca.gov
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Friday, May 8, 2026 5:46 AM
Subject: Dam Safety Compliance Report submitted in FERC P-1121-000,et al. by Pacific Gas and Electric Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking
on links, or replying..
On 5/7/2026, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-1121-000
P-619-000
P-2310-000
P-137-008
P-77-001
P-2105-000
P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Dam Safety Compliance Report
Description: Pacific Gas and Electric Company submits results of a second spillway screening-level risk analysis to prioritize and
schedule major capital improvement projects at the Battle Creek Hydroelectric Project et al. under P-1121 et al.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?
accession_num=20260507-5129__;!!KNMwiTCp4spf!GOLx7Sn3tZ72q4Cw8kM08jNpv2af-l3ATXFRCT-
TQTjp9hkEWBpILGIZpGnQkjKOOmJwvAEhVDeAmXyat4Fw24eZ0a57ID_3fLRz$
To modify your subscriptions, click here:
l3ATXFRCT-TQTjp9hkEWBpILGIZpGnQkjKOOmJwvAEhVDeAmXyat4Fw24eZ0a57IEQxtgPo$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!GOLx7Sn3tZ72q4Cw8kM08jNpv2af-
l3ATXFRCT-TQTjp9hkEWBpILGIZpGnQkjKOOmJwvAEhVDeAmXyat4Fw24eZ0a57IABBvi0W$
or for phone support, call 866-208-3676.
Power Generation
300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
May 7, 2026
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Battle Creek Hydroelectric Project, FERC No. 1121-CA
Bucks Creek Hydroelectric Project, FERC No. 619-CA
DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Drum-Spaulding Hydroelectric Project, FERC No. 2310-CA
Mokelumne River Hydroelectric Project, FERC No. 137-CA
Potter Valley Hydroelectric Project, FERC No. 77-CA
Upper North Fork Feather River Hydroelectric Project, FERC No. 2105-CA
Findings from PG&E’s Spillway Screening-Level Risk Analysis
ENCLOSURES CONTAIN CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter presents the results of a second spillway screening-level risk analysis (SSLRA)
conducted by Pacific Gas and Electric Company (PG&E) to prioritize and schedule major
capital improvement projects across its portfolio of spillways. In an August 4, 2023, letter to
FERC, PG&E submitted the results of its first SSLRA, along with a prioritized schedule for
nine planned spillway projects. In a subsequent letter to FERC dated June 26, 2024,
PG&E presented a plan to conduct a second SSLRA including five additional spillway
projects. The 14 dams with spillways assessed under the two SSLRAs are listed in Table 1
below.
After completing the second SSLRA in late 2025, PG&E updated its prioritized project
schedules to include the five spillways evaluated in 2025 with the original nine spillways
evaluated in 2023. In addition to the updated schedules, this letter provides a summary of
the interim risk-reduction measures (IRRMs) that PG&E is implementing to manage
potential risks until the major capital improvement projects are completed.
Frank L. Blackett, P.E., Regional Engineer
May 7, 2026
Page 2
Table 1. Spillways Evaluated through PG&E’s Spillway Screening-Level Risk Analyses
Hydroelectric Project Dam
Drum-Spaulding Project, FERC No. 2310 Lake Fordyce Dam, NATDAM No. CA00357
Halsey Afterbay, NATDAM No. CA00352
Bucks Creek Project, FERC No. 619 Bucks Diversion Dam, NATDAM No. CA00331
Spring Gap-Stanislaus Project, FERC No. 2130 Relief Dam, NATDAM No. CA00390
Mokelumne River Project, FERC No. 137 Upper Bear River Dam, NATDAM No. CA00379
Battle Creek Project, FERC 1121 North Battle Creek Dam, NATDAM No. CA00394
Macumber Dam, NATDAM No. CA00393
Upper North Fork Feather River Project, FERC No. 2105 Lake Almanor Dam, NATDAM No. CA00327
Belden Forebay Dam, NATDAM No. CA00413
Butt Valley Dam, NATDAM No. CA00326
DeSabla-Centerville Project, FERC No 803 Philbrook Dam, NATDAM No. CA00345
Round Valley Dam, NATDAM No. CA00346
Bucks Creek Project, FERC No. 619 Bucks Storage Dam, NATDAM No. CA00332
Potter Valley Project, FERC No. 77 Cape Horn Dam, NATDAM No. CA00399
Following the 2017 Oroville Dam spillway incident, PG&E established its Spillway
Assessment and Improvement Program (SAIP) to conduct engineering assessments and
manage follow-up actions to address potential deficiencies at its spillways. To date, the
program has identified 16 spillways that require major capital improvement projects, with
additional spillways currently under evaluation. As part of the SAIP, PG&E established a
dedicated Capital Improvement Program (CIP) to facilitate planning, design, and execution
of the proposed spillway remediation projects.
For the spillway CIP projects at the 14 dams listed in Table 1, PG&E used a risk-informed
framework, including SSLRA, to prioritize and schedule the projects for construction.
PG&E retained Gannett Fleming, Inc., to facilitate the first SSLRA workshop in fall 2022.
PG&E retained Slate Geotechnical Consultants to facilitate the second SSLRA workshop
in fall 2024. The SSLRA reports (dated July 2023 and December 2025) are enclosed with
this letter (Enclosures 1 and 2, respectively). PG&E has reviewed the SSLRA reports and
concurs with the findings and conclusions presented therein.
A PG&E memorandum summarizing the SSLRA results and presenting PG&E’s proposed
prioritization for remedial projects at the 14 spillways is provided in (Enclosure 3). The
memorandum describes the risk-informed framework and methodology used to rank,
prioritize, and schedule the projects. To optimize the use of available resources, the
proposed projects are divided into three tiers with staggered development schedules.
Spillways found to have the highest risk are generally prioritized for earlier remediation,
with some adjustments for existing conditions, logistical considerations, and other factors.
PG&E’s plans and schedules for the long-term spillway remediation projects are provided
in (Enclosure 4). The schedules include proposed timelines for key milestones in the
project execution process. As described in Enclosure 3, PG&E recognizes that additional
Frank L. Blackett, P.E., Regional Engineer
May 7, 2026
Page 3
projects may be added to the spillway CIP as ongoing engineering evaluations are
completed. To incorporate new projects, PG&E plans to perform supplemental risk
assessments and periodically update the prioritized project schedule. When projects are
added, removed, or reprioritized based on new information, PG&E will submit the revised
plans and schedules to FERC.
Because of the extended time frame required to develop and implement the planned
capital improvements, PG&E is implementing IRRMs to manage potential risks until the
long-term remediation projects are completed. As part of the risk-informed process for
prioritizing the projects, PG&E identified and evaluated existing and potential new spillway-
related IRRMs. Results of the evaluation and a summary of IRRMs for spillways at each of
the dams identified in Table 1 are provided in (Enclosure 5).
Should you have technical questions concerning this matter, please contact Chris Duffey,
engineer for PG&E’s SAIP, at (530) 513-9559. For general questions, please contact
Jackie Pope, senior license coordinator for PG&E, at (530) 254-4007.
Sincerely,
David L. Ritzman, P.E., G.E.
Chief Dam Safety Engineer
Enclosures: CUI//CEII – DO NOT RELEASE
1. Spillway Risk Prioritization Workshop, Focused Portfolio Analysis, prepared by Gannett
Fleming and dated October/November 2022
2. Spillway Screening-Level Risk Assessment Report, prepared by Slate Geotechnical
Consultants and dated December 2025
3. Spillway Prioritization for Capital Improvement Program, prepared by PG&E and dated
February 2026
4. Preliminary Spillway Plan and Schedule for Spillway Remediation Projects
5. Summary of Interim Risk-Reduction Measures
cc: via hard copy w/enclosures
Erik Malvick, Ph.D., P.E., G.E., Division Manager
Department of Water Resources, Division of Safety of Dams
2720 Gateway Oaks Drive, Suite 300
Sacramento, CA 95833
via secure file transfer w/enclosures
Tim Jimenez, P.E., Central Regional Engineer
Department of Water Resources, Division of Safety of Dams
timothy.jimenez@water.ca.gov