HomeMy WebLinkAbout2014 New Carr Mine Inspection Report_FinalNew Carr Mine
(CA Mine ID# 91‐04‐0038)
2014 SMARA Mine Inspection Report
Prepared by:
Butte County Development Services Department
7 County Center Drive
Oroville, California 95965
November 4, 2014
1
2014 SMARA Mine Inspection
New Carr Mine
CA ID# 91‐04‐0038
Butte County, California
TABLE OF CONTENTS
Section Description Page No.
1.0 Mine Description 2
2.0 Reclamation Objective 3
3.0 Observations 9
4.0 Financial Assurance 10
5.0 Violations / Corrective Measures 11
List of Figures
Figure 1 Location Map
Figure 2 Active Mine Area Zones (Exhibit 1A)
Figure 3 Active Mine Area Zones (Exhibit 1B)
Figure 4 Active Mine Area Typical Cross Sections
Figure 5 Historic Disturbance Area Reclamation Phase Map
List of Attachments
Attachment A 2014 MRRC‐1 Surface Mining Inspection Report
Attachment B Annotated Site Photographs
2
1.0 MINE DESCRIPTION
The Carr Mine is a dryland gold placer mine that involves the excavation of a paleochannel situated on
the eastern end of Carr Ridge, ranging in elevation from 6,420 to 6,695 feet above mean sea level. The
permitted mine site encompasses 34 acres within a 200 acre property located in eastern Butte County,
10.3 miles northeast of Sterling City, and 7 miles southeast of Butte Meadows; Township 25N, Range 5E,
Sections 9 and 6; MDB&M. Assessor Parcel Numbers: 059‐200‐011, 059‐210‐066 and 059‐210‐007. Part
of the mine site includes the historic mining operations that have been conducted at the site
intermittently for the past 130 years. Historic mine operations have resulted in approximately 15 acres
of existing surface disturbances, which include dilapidated mining equipment, scrap metal, deep
erosional cuts, tailing stockpiles, sediment basins, a cabin and an unvegetated landscape.
Mining operations within the permitted area will include excavation of 14 independent mining zones
along the presumed paleochannel. Each mining zone is approximately 1.4 acres in size and
encompasses a total of 19 acres. An additional 2 acres of land will be used to support the mining
operation, and will include the existing cabin, a temporary processing building, cargo storage container,
sediment basins, staging areas, and access roads. It’s anticipated that each mining zone will be
excavated during each mining season, between April 15th and October 15th. The depth of each mine
zone will vary year to year, but the average depth is estimated to be 50 feet below the existing grade,
with a maximum depth estimated at 90 feet.
Excavation of each zone will be performed by an excavator that will remove overburden materials until
excavations reach the ore material within the paleochannel. The ore is then excavated and stockpiled
adjacent to the excavation pit where a front‐end loader will transport the material to a hopper.
Material will be then conveyed to the gold recovery plant where the gold will be sorted from the
overburden. Water for the processing facility would be pumped from an existing catch basin. Waste
water from the plant will be sent back to the basin as part of a closed‐looped system. Processed tailings
will be stockpiled for eventual use in the reclamation of the prior years’ excavation pit. It’s estimated
that a total of 1,031,237 cubic yards of materials will be excavated through the life of the operation,
which is anticipated to be complete by December 31, 2027.
The sequence of mining activities for each mining zone will be as follows:
Prior to removing any vegetation in the active mining zones a pre‐construction survey will be
performed to ensure that no active raptor nests are inadvertently removed.
Remove all standing vegetation pursuant to a Timber Harvest Plan. Marketable timber will be
sold, shrubs and tree seedlings available for replanting will be preserved for later planting, and all
other vegetation will be chipped.
Excavate and stockpile duff (mixture of existing decomposed, chopped, broken or chipped plant
material, pine needles, leaves, grasses) to a depth of four inches, removing rocks and plant
material in excess of 150 mm in greatest dimension.
Remove all large roots, tree stumps and rocks greater than 8 inches in greatest dimension
(oversized rocks) from the top 24 inches of the soil. Over‐sized rocks will be used to line drainage
swales and placed where necessary to dissipate the erosive energy of water flowing in the
drainages.
Once a phase is cleared of vegetation and rock, topsoil and overburden will be separately removed by an
excavator. Duff, topsoil and overburden will be stockpiled and placed in the previous phase’s excavation
at the earliest feasible time but no later than the end of each mining and reclamation season in late
3
October. If immediate placement is not possible, topsoil and overburden must be stockpiled in
accordance with the reclamation plan, which includes revegetation and other erosion control measures.
Processing of the placer gravels and sands occurs mechanically by successive washing, tumbling, and
shaking, using water and gravity to separate gold from coarser materials. Once extracted, a mobile
plant situated near the active excavation pit will process the placer gravels, separating out finer load
bearing material from the heavier cobbles by tumbling, shaking and flushing with water. All water for
the plant will be pumped from Catch Basin #1b and recycled back after use.
Final gold recovery will occur in a building near the existing historic cabin. A jig, sluice and a vibrating
table will separate gold from sands and other fine sediments, utilizing approximately 5,000 gallons of
water re‐circulated through a water storage tank. No chemicals are proposed for the recovery process.
2.0 RECLAMATION OBJECTIVE
The approved reclamation plan covers the reclamation of both the 19‐acre active mining area and
approximately 15 of the 20 acres of previously disturbed lands. The overall reclamation goals of the
plan are to:
Repair portions of the mine immediately as required by violation notices issued to previous
operators, and arrest significant erosion problems;
Re‐contour to more natural conditions as feasible;
Stabilize slopes;
Prevent erosion and sedimentation of down‐gradient streams;
Re‐vegetate with native plant species; and
Monitor and manage the site as open space and habitat for wildlife species.
Reclamation within each active mining zone will occur when processing materials in that zone have been
completed for the season. Following the completion of the year’s active mining area, the disturbed area
will be immediately reclaimed before moving to a new 1.4 acre zone to be mined in the subsequent
year. Reclamation will include backfilling the mined area with the overburden generated by mining the
excavation area, and graded to match the topography of pre‐mining conditions. Backfilled material will
be compacted to 90% maximum density. Stockpiled topsoil will be re‐distributed evenly over the
disturbed area, and compacted to 70% maximum density. The area will be covered with jute netting
and straw wattles, and then seeded and planted with native species.
Previously Disturbed Land Reclamation
Reclamation of previously disturbed lands is approved to occur in 5 phases to be completed over the life
of the active mining operations.
4
Phase 1
Reclamation activities include revegetation of old haul roads, removing the remaining past mining
equipment, including the large trammel. Once the equipment and debris are removed, the
approximately 1.46 acre of will be re‐graded and re‐contoured, with the sub‐grade prepared. A small
processing pond (Pond 2a) located in the Phase 1 area will be backfilled. Disturbed areas will be
stabilized with straw wattles, hydroseeded, and degradable jute netting will be placed over the site.
Container plants will be planted and irrigation will be performed as necessary to establish growth. The
area adjacent to Pond 2a where no earthwork will be performed will also be prepared, hydroseeded,
and planted with vegetation. Finally, existing drainage swales will be armored and repaired as necessary
using live pole cuttings or fascines from vegetation and rocks located on the site.
Phase 2
Settling Basin 1a will be backfilled and approximately 1.06 acres will be re‐contoured to more natural
conditions. Approximately 0.92 acres not requiring grading work will be stabilized, hydroseeded and
revegetated.
Phase 3
Settling Basin 2a will be backfilled to create seasonal wetland habitat. Once completed, the large tailing
pile located on Forest Service land and the large berm around Settling Basin 2a will be cut and used to
fill the basin. The land will then be re‐contoured to natural conditions and stabilized, hydroseeded, and
revegetated. The seasonal wetland habitat will be planted with native wetland plants, consistent with
coverage and species types located in Settling Basin 4.
Approval must be granted by the Forest Service before any earthwork and re‐vegetation activities can be
performed on their land. If Forest Service approval is not acquired, the reclamation plan will be amended
to remove this area located on Forest Service land from the approved reclamation plan.
Phase 4
Catch Basin 1a will be backfilled to create seasonal wetland habitat.
Phase 5
The last phase of reclamation of the historic mining area will be conducted after all active mining on the
site has been completed. The final phase includes backfilling Catch Basin 1b using the remaining large
5
tailing piles present on the site, and using the methods specified in the plan. The steep bank above the
basin will be recontoured to a 2:1 slope and will be stabilized using a live crib wall. Recontoured areas
will be amended, stabilized and revegetated using approved methods discussed in the plan.
Upon completion of reclamation activities of the historic disturbance area, the area will be established
for wildlife habitat. The open space created with the prescribed reclamation activities and revegetation
types is anticipated to create a short term understory for migratory deer and native ground nesting
birds. Once the vegetation matures, it’s anticipated that a suitable habitat would be created for
northern goshawks and spotted owls. Two existing roads and the existing cabin will be retained on the
site and used as a private seasonal residence. An existing well will also remain on the site.
1. General Information
a) Permitted Mineral Product(s): Gold
b) Production Amount (Annual/Gross): No Annual Production Amounts Identified. It’s
anticipated that one zone will be completed each year.
1,031,237 cubic yards/gross
c) End Date of Operations: December 31, 2027
d) Permit End Date: December 31, 2027
e) End Use: Open Space / Wildlife Habitat
2. Boundaries
a) Property Boundary: 200 acres
b) Permit Boundary: 34 acres (19 acres for Active operations)
c) Reclamation Plan Boundary: 34 acres (Includes Active and Historic disturbances)
d) Setbacks: No setbacks identified in the reclamation plan.
3. Grading
Fill Slopes
Pond 2a, Settling Basin 1a, Settling Basin 2a, Catch Basin 1a and Catch Basin 1b are proposed to be
backfilled throughout anticipated mining activities. All areas subject to fill will be re‐contoured to no
greater than a 2:1 slope, and re‐compacted to 90% maximum density. Settling Basin 2a and Catch
Basin 1b will be re‐contoured to a 2:1 slope, where possible. On slopes with a 1.5:1 or steeper ratio,
a live crib wall will be used to stabilize the slope. Slopes for all stockpiles on‐site will be maintained
at a 2:1 ratio.
Cut Slopes
Maximum cut slopes in active excavation areas are generally 1:1 up to a maximum height of 40 feet.
If the height exceeds 45 feet, the maximum slope is 1.5:1 and a 15 feet wide bench must be
constructed. Reclaimed excavation areas will be backfilled and re‐contoured to match the
surrounding terrain.
4. Erosion Control
Erosion and sediment control methods will be used during all phases of operation and reclamation
to minimize erosion of soils and sediments. Erosion control methods include, but are not limited to,
6
the use of berms, silt fences, sediment ponds, revegetation, and hay bales. The mine site will be
monitored after a storm event to ensure that all BMP’s are installed correctly. Persistent erosion
areas will be investigated, and appropriate remedial measures will be implemented to repair and
arrest erosion. Erosion control practices were selected to meet the following objectives:
Retain natural vegetation whenever possible.
Match the site grading, as feasible, to the surrounding terrain. Grade excavation and
reclaimed fill slopes to minimize the length and steepness of the slopes while maintaining
a stable configuration.
Chip vegetation from the land stripping and grubbing to use as a topsoil amendment and
to protect soil from particle disruption during precipitation.
Construct overland cut‐off swales to prevent sheet flow over disturbed areas.
Schedule grading operations to minimize disrupted soil exposures during the rainy season
(generally between October 15 and May 31).
Construct drainages to resemble pre‐mining density and location as feasible. All drainages
shall be vegetated.
Use energy dissipating control measures to minimize surface water runoff flow velocities.
All topsoil, overburden and sediment will be kept on‐site.
Regularly inspect and maintain erosion and sediment control BMPs.
5. Ponds
Existing catch basins and settling basins at the mine site will be used throughout mining active
operations, and will be maintained by the operator. Specific existing basins and ponds identified in
the reclamation plan are planned to be reclaimed throughout active mining operations, and will not
be used as part of planned operations. Information on the capacity of these basins is not discussed
in the approved reclamation plan.
6. Stream & Wetland Protection
No streams are present within the mine site. However, several unnamed ephemeral drainages
transect the site, and surrounding area, eventually draining into the Philbrook Reservoir and the
West Branch of the Feather River.
Seasonal wetland habitats associated with Settling Basin 1b, 2b, 3, and 4 are also located within the
mine site. These seasonal wetlands capture precipitation and runoff, and typically begin the dry in
August. Typical vegetation found in the areas include various willow species, Bolander’s yampah,
iris‐leaved rush, musk monkey flower, cattails, Sierra nerved sedge, tinker’s penny, and Macloskey’s
violet.
Implementation of erosion control measures, and adherence to the project SWPPP, would ensure
that drainages and wetland areas are properly protected. Reclamation activities also include the
creation of new seasonal wetland areas, in addition to the enhancement of existing seasonal
wetlands.
Active mining areas and previously disturbed mining areas will also be marked with flagged stakes
every 100 feet around the perimeters to help preserve existing ponds and wetland areas within the
mine site.
7. Sensitive Wildlife & Plant Protection
Listed Species
7
No rare, threatened or endangered species, as listed by the California Department of Fish and
Wildlife or the U.S. Fish and Wildlife Service, or Species of Special Concern, were identified on the
site. The long‐range goal of reclamation of the mine site is to create a mature forest habitat suitable
for northern goshawks and spotted owls, if feasible. Existing sediment ponds will be preserved, or
restored and/or enhanced with native wetland plantings.
Protection Measures
To conserve and enhance habitat for protected species and sensitive biological communities, active
mining areas and previously disturbed mining areas will be marked with flagged stakes every 100
feet around the perimeters. Additionally, the perimeter of each year’s active mining phase shall be
identified from surrounding vegetation by orange construction fencing. (Mitigation Measure #4)
To protect nesting raptors and their offspring, a qualified biologist in consultation with the
Department of Fish and Wildlife shall conduct pre‐construction surveys for special‐status species
nesting birds and common raptors, if vegetation removal and/or project construction occurs during
the nesting season (March 1 to September 15). The surveys shall be conducted within 14 days prior
to commencement of project activity. If active nests are discovered, appropriate buffers shall be
established. (Mitigation Measure #3)
A qualified biologist will be retained to advise project employees operating equipment regarding the
importance of maintaining construction fencing, and strictly avoiding and protecting all vegetation
outside the active mining areas and previously disturbed mining areas. The biologist shall also
advise project employees on the importance of maintain distance from wildlife and in the
recognition and avoidance of nesting birds. (Mitigation Measure #5)
8. Soil/Overburden Stockpile Management
Topsoil
Topsoil removed during mining operation will be hauled directly from the harvest site to the
application site whenever feasible. If it is necessary to stockpile the topsoil, the topsoil will be
stockpiled on‐site. The topsoil will be stored separately from the reminder of the overburden
material in designated locations. Topsoil will be stockpiled to a depth no greater than the rooting
zone of the plant cover to maintain the biological activity within the soil. If the topsoil is to be
stockpiled for one season, the soil will be covered with an erosion protection blanket. If the topsoil
is to be stockpiled for more than one year, the soil shall be stabilized and vegetated with a native
seed mix. Additional BMP’s will be also implemented to prevent erosion of topsoil stockpiles.
Overburden
Excavated materials will be transported to the mobile processing area and processed immediately.
Overburden will be stockpiled adjacent to the excavation pit, or used directly to backfill the previous
excavation mining zone. Only heavy material trapped in the processing equipment will be
transported to the gold recovery room. Any overburden stockpiles created would be situated in a
manner to facilitate reclamation, and would be segregated from growth media stockpiles. No
specific location for overburden stockpiles are mapped in the reclamation plan. Appropriate erosion
control methods would be used to minimize to erosion of overburden stockpiles.
Topsoil Application
Existing topsoil in historic disturbance areas will need to be re‐created for use in the reclamation of
these areas. This includes mixing soil from the top 4 inches with organic matter including duff,
woodchips, slow release NPK fertilizer, and organic compost. In areas where the topsoil will not be
8
amended, slow release fertilizers or compost may be added to the planting hole of container plants
to facilitate growth.
9. Revegetation
Test Plots
Four separate test plots will be installed during the first year following approval of the reclamation
plan. Each plot will a minimum of 50’ x 50’ in size, and will be located at different locations within
the mine site that will not be disturbed for a minimum of 5 years. One test plot will be used to
determine the degree of herbivorousness of area wildlife, and if tree shelters will be needed. The
remaining test plots will be used to evaluate the effectiveness of different soil amendments and
seeding strategies.
Revegetation Species Mix & Density
Seeding Upland Species Upland Tree/Shrub Species Mix Wetland Species Mix
Plant Type Density
(Lbs/acre) Plant Type Density
(plts/acre) Plant Type Density
Ca. needlegrass 8 Jepson’s willow 20 Willow 20 (pl/ac)
Ca. brome 12 Arroyo willow 20 Arroyo willow 20 (pl/ac)
Blue wildrye 6 Bittercherry 10 Lodgepole Pine 10 (pl/ac)
Creeping wildrye 8 Whitethrorn 5 Balsam cottonwood 5 (pl/ac)
Meadow barley 5 Green leaf manzanita 20 Wood rose 20 (pl/ac)
Bottlebrush squirreltail 12 Pinemat manzanita 10 White alder 10 (pl/ac)
Ca. oat‐grass 9 Tobacco brush 5 Pacific dogwood 5 (pl/ac)
Ca. fescue 9 Sierra gooseberry 20 Thimbleberry 20 (pl/ac)
Ca. barley 10 Creeping snowberry 10 Yampah 8 (lb/ac)
Globe gilia 2 Ponderosa Pine 5 Monkshood 2 (lb/ac)
Buck lotus 2 White fir 20 Horse mint 4 (lb/ac)
Spanish clover 3 Lodgepole Pine 10 Meadow rue 8 (lb/ac)
Naked buckwheat 3 Buck lotus 20 Corn lily 5 (lb/ac)
Mountain pride penstemon 3
Pale spikerush 6 (lb/ac)
Arrow balsamroot 4 Rush 6 (lb/ac)
Mule’s ears 4 Meadow barley 12 (lb/ac)
Blue flax 8 Slender wheatgrass 8 (lb/ac)
Rabbitbrush 8 Blue wild‐rye 10 (lb/ac)
Yarrow 10
Silver Lupine 5
Percent Cover
Not identified in the reclamation plan.
Species Richness
Upland Seeding Richness – 7
Protection
A tree shelter or other plant protector will be used, as needed, to prevent herbivory damage during
the initial establishment period. Mulch from wood chips or pine needles collected on‐site will be
placed around the plantings to help manage vegetation and increase soil moisture retention.
Success Monitoring
9
Following completion of reclamation activities, monitoring will be performed for 3 consecutive years
or until performance criteria are met, whichever is longer. The success of reclamation activities will
be determined by monitoring the site for erosion and proper drainage patterns. The success of re‐
vegetation efforts and wetland creation activities will be determined by monitoring plant survival,
species density and composition. Finally, the success of the created and restored drainage channels
and sediment basins will be determined by monitoring water turbidity.
Invasive Species Control
Noxious weeds will be managed if it threatens the success of revegetation efforts, spread to nearby
areas, or produce a fire hazard. Bull thistle (Cirsium vulgare), a Cal‐IPC List B invasive weed, was
identified within the mine site. This infestation will be controlled through hand removal methods or
spot treatment with chemical herbicides. All outside equipment will be cleaned prior to conducting
mining or remediation activities on‐site. Further, all straw used onsite will be sterilized.
10. Structures / Equipment
Two existing access roads, one existing cabin, and one groundwater well will be retained for
residential uses. All other buildings, structures, and equipment will be dismantled and removed
from the site, prior to final mine closure.
3.0 OBSERVATIONS
Mining activities in Phase 2 of the Active mine area were initiated by the operator during the past year.
Activities include vegetation and tree removal, removal of overburden from the Phase 2 Active mine
area, depositing of overburden materials into the Phase 2 Historic mine area, and build‐up of the
existing overflow weir from Catch Basin 2b. Overburden removal primarily consisted of creating a level
surface over the Phase 2 Active mine area in anticipation of future mine activities to occur in 2015.
Since reclamation plan approval in 2012, the operators has been performing reclamation of historic
mining disturbance areas, in accordance with the approved reclamation plan. Reclamation activities
performed have included: (1) Removing old mining equipment and parts, as well as junk that had been
illegally disposed at the site; (2) Re‐contouring of surfaces of the mine to allow for improved site
drainage; (3) Implementation of erosion control measures, including the installation of jute netting,
straw waddles, silt fencing, rip‐rap, and revegetation; (4) Filling and re‐contouring of Pond 1a; and, (5)
re‐contouring of Catch Basin 1a. With the completion of the above activities, the operator has partially‐
completed the grading activities associated with Phase 2, Phase 3 and Phase 4, and, fully completed the
grading activities of Phase 1. Minimal reclamation activities have been performed in the Phase 3 area,
as the United States Forest Service have not provided permission to complete reclamation activities on
the disturbances areas on their property.
Soil Erosion/BMPs
Erosion control measures were being initiated at the time of inspection. Straw waddles and silt fencing
were being installed around Phase 2 of the Active mine area, where initial grading activities were
recently performed during 2014. The operator indicated that additional erosion control measures
would be implemented following the inspection. No significant erosion was evident during inspection.
A follow‐up inspection will be performed during spring to identify if erosion control measures were
successful, and whether any corrections to the implemented BMP’s would be necessary.
Slope Stability
10
The only significant steep slopes on the mine site is the high wall located above Catch Basin 1b. The
slope is part of the historic disturbance area identified in the reclamation plan, and that would be
subject to reclamation during Phase 5, upon completion of the Active mining areas. The existing slope
appears to be stable. The operator continues to improve the drainage runoff flows above and around
the steep slope to further minimize the potential for erosion on the slope, as well as to divert water
around Catch Basin 1b. Steep slopes are anticipated to be created during mining activities, as the
individual pits are developed. However, no active mining has commenced.
Revegetation/Test Plots
No formal test plots have been established, as prescribed in the reclamation plan. However, the
operator indicated that revegetation efforts in past years are being evaluated to determine the most
successful methods. The most recent revegetation efforts occurred in the Fall of 2013, which included
the planting of pine seedlings within Phase 1 – Historic Disturbance Area. Due to the dry winter
conditions in 2013‐14, establishment of the seedlings were unsuccessful.
Equipment Storage Area
The primary storage area for equipment and parts are located within the designated operations site, and
within an 8’ x 8’ x 40’ metal storage container, located northwest from Settling Basin 2a. All equipment
parts appear to be incidental to operations, and are stored in an orderly manner.
A backhoe, dozer, dump truck, and portable diesel generator were located on the site during inspection.
All heavy equipment are removed from the site prior to winter and then returned to the site at the
onset of activities in Spring.
Protection Measures
Pursuant to Mitigation Measure #4, the perimeter of the active mining area was identified on the mine
site with orange construction fencing. The construction fencing was set on two of the four corners of
the Phase 1 ‐ Active mine area. However, no fencing or identification of mining areas were set around
the Phase 2 and Phase 3 areas of the Active mine area, where activities are anticipated to occur. The
operator noted that construction markers will be established prior to activities, which are anticipated to
occur in Spring 2015. In compliance with Mitigations, a ‘Construction Staking Map’ was prepared for the
mine site by NorthStar Engineering. The map delineated the active mining areas and the limits of the
historic disturbance areas that are subject to staking.
Pursuant to Mitigation Measure #5, a contractor/employee environmental awareness training workshop
was conducted for the operators of the New Carr Mine on July 26, 2013. The workshop was performed
by Elena Gregg, a biologist with NorthStar Engineering. The workshop included a presentation of the
critical species and their habitat that have the potential to be located in the area, as well as, migratory
bird and raptor species. The training also included discussions of the species’ legal status, afforded
protections, penalties for violations, habitat descriptions and the need to minimize disturbance areas.
4.0 FINANCIAL ASSURANCE
A Financial Assurance Cost Estimate was prepared for the mine operation, and subsequently submitted
to OMR for review on September 20, 2012. The estimate calculated the total reclamation costs for each
phase of the historic disturbance area reclamation, as well as Phase 1 of the active mining area. In total,
third‐party reclamation costs were estimated to be $656,639.00.
Since approval of the original estimate, the operator has performed several reclamation objectives for
the historical disturbance area, thereby likely reducing the overall reclamation liabilities of the mine site
11
identified in the 2012 FACE. The operator filed a revised Financial Assurance Cost Estimate on
December 15, 2014. The estimate is currently being reviewed by Butte County. The FACE includes
separate estimates for each of the historic disturbance reclamation phases, and one phase of operations
for the active mine area.
5.0 VIOLATIONS / CORRECTIVE MEASURES
Violation:
1. Submit a financial assurance to coincide with the latest approved financial assurance cost
estimate for the mine. An updated estimate is currently being reviewed. Upon approval of the
updated estimate, the operator shall submit a financial assurance reflecting the Active Mine
Area disturbance area for 2014‐15.
12
Figure 1 – Location Map
13
Figure 2 – Active Mine Area Zones (Exhibit 1A)
14
Figure 3 – Active Mine Area Zone (Exhibit 1B)
15
Figure 4 – Active Mine Area Typical Cross Sections
16
Figure 5 ‐ Historic Disturbance Area Reclamation Phase Map
State of California
DEPARTMENT OF CONSERVATION
OFFICE OF MINE RECLAMATION
MRRC-1 (4/97) Page 1 of 5 (Rev. 07/13)
SURFACE MINING INSPECTION REPORT
(See reverse side of each form page for completion instructions)
I. Mine Name (As Shown on Approved Reclamation Plan) Inspection Date: CA MINE ID#
91-
II. Mine Operator Telephone ( )
Onsite Contact Person Telephone
( )
Mailing Address
City State ZIP Code
E-mail Address (optional)
III. Designated Agent Telephone
( )
Mailing Address
City State ZIP Code
E-mail Address (optional)
IV. SMARA Lead Agency Name (City, County, BCDC, or SMGB)
Inspector Telephone
( )
Title Organization
Mailing Address
City State ZIP Code
E-mail Address (optional)
V. Does the operation have: P NR No Yes
A Permit to Mine Permit # - Start and Expiration Dates
Vested Right to Mine Year of Lead Agency determination
A Reclamation Plan RP# Date Approved
Reclamation Plan Amendment RP Amendment # (as applies) Date Approved or Status of Amendment
Has the Operator filed a Mining Operation Annual Report (Form MRRC-2) this Year?
Check One: Yes No Year of Most Recent Filed
Annual Report:
VI. Is this Operation on Federal Land? Check One: If "Yes,” Provide One or Both of the Federal Mine Land Identification Numbers Below: Yes No
California Mining Claim Number (CAMC#): Latitude/Longitude at Mine Entrance (Decimal Degrees):
U.S. Forest Service or BLM Identification Number (Plan of Operations #) : Status of Plan of Operations (Current/Expired/In Process):
DISTRIBUTION: Lead Agency sends copies of Inspection notice & completed MRRC-1 to operator, operator’s designated agent, BLM or USFS (if required) & retains original.
INSTRUCTIONS FOR COMPLETING SURFACE MINING INSPECTION REPORT
Form MRRC-1 (4/97) Page 1 (Rev. 07/13)
This report is intended to comply with the requirements of California’s Surface Mining and Reclamation Act (SMARA – Public Resources Code Sections §§
2710 et seq., and the associated California Code of Regulations found in Title 14, division 2, beginning at § 3500, hereinafter respectively “PRC” or “CCR”) and
specifically PRC § 2774(b) and CCR § 3504.5 for operations located on private land and/or partly or solely on Bureau of Land Management (BLM) and U.S.
Forest Service (USFS) lands (Title 43, parts 3500, 3600, and 3800 of the Code of Federal Regulations). A Memorandum of Understanding between the U.S.
Department of Interior, BLM; U.S. Department of Agriculture, USFS; the State of California, Department of Conservation; and the State Mining and Geology
Board (SMGB), discusses implementation of SMARA on Federal lands in California that are under the jurisdiction of the BLM and/or the USFS.
As required by PRC § 2774(b) and CCR § 3504.5(g), Lead Agencies shall file an Inspection Notice that includes a statement regarding compliance with
SMARA, a copy of this Surface Mining Inspection Report (MRRC-1) and any other supporting documentation with the Department within 30 days of completion
of the inspection. The Lead Agency shall also forward a copy of the Inspection Notice, MRRC-1, and any supporting documentation to the operator.
BLOCK I: Enter the name of the Mining Operation, the date of the inspection, and the California Mine ID number.
BLOCK II: Enter the name of the Mine Operator, mailing address, phone number, name, and email address (optional) of the person to serve as the
onsite contact.
BLOCK III: Enter the name, mailing address, phone number, and email (optional) of the Designated Agent who, under PRC § 2772(c)(1) and
2207(a)(1), will serve as a contact for any follow-up correspondence or discussions regarding the inspection or noted violations.
BLOCK IV: For "Lead Agency," enter the name of the certified SMARA Lead Agency that is conducting this inspection. Acceptable entries include the
name of the city, county, Bay Conservation and Development Commission (BCDC), or State Mining and Geology Board (SMGB). For
"Organization," enter the name of the agency, firm or other organization that employs the inspector.
BLOCK V:
Check the appropriate boxes.
P
NR, No, Yes
Pending (on appeal or awaiting approval by Lead Agency)
Not required for this operation at the time this inspection was completed
No
Yes, supply information
Note: Where appropriate, to aid in determining when the lead agency recognized that the operation has vested mining rights, inspectors
are advised to review older agency correspondence, minutes of lead agency hearings, including agendas and staff reports associated
with approvals of any kind related to the mining operation.
BLOCK VI: Indicate if the operation is on federal Land; if operation is on federal land, include a California Mining Claim Number and/or a BLM/USFS
Identification Number and Plan of Operations Number, if applicable. Give the status of the BLM/USFS Plan of Operations, as indicated.
Give the latitude and longitude at the mine entrance in decimal degrees.
___________________________________________________________________________________________________________________________________________
DISTRIBUTION INSTRUCTIONS:
One copy of the inspection notice and this completed Inspection Report (all pages) shall be given to the Mine Operator and the
operator’s designated agent by the lead agency (PRC Section 7374(b).
The Lead Agency must retain the original copy of this Inspection Report and submit one copy of this Inspection Report, along
with an original inspection report notice (PRC Subsection 2774(b)), within 30-days of the completion of the inspection, to:
Department of Conservation Office of Mine Reclamation 801 K St MS 09-06 Sacramento, CA 95814-3529
If any part of the operation inspected is on BLM or USFS land, one copy of this Inspection Report should be forwarded to the
appropriate BLM or USFS office.
State of California
DEPARTMENT OF CONSERVATION
OFFICE OF MINE RECLAMATION
MRRC-1 (4/97) Page 2 of 5 (Rev. 07/13)
SURFACE MINING INSPECTION REPORT
VII. Financial Assurance Inspection Date: CA MINE ID#:
91-
Type of Financial
Assurance Mechanism(s) Financial Assurance Mechanism Number(s) Amount of Mechanism Date of Expiration Date of Lead Agency
Approval of
Mechanism
Total Amount of Mechanism(s)
Financial Assurance Mechanism Pending Review by Lead Agency? If yes, provide date submitted/explanation and amount of pending mechanism:
Has there been a change of operator
since last inspection? If yes provide the date
of notice.
Yes No
Date of Change:
If yes, has the new operator posted a Financial Assurance Mechanism?
Yes No
If not, describe status of new operators Financial Assurance Mechanism:
Does new operator’s
Notice of Change include
a statement of responsibility
for reclamation?
Yes No
Posted a Financial Assurance Mechanism?
Yes No
If No, Has The New Operator Been Advised Of Financial Assurance Obligations?
Yes No
Date and Amount of Most Recent Approved
Financial Assurance Cost Estimate:
Date: Amount:
Financial Assurance Cost Estimate
Pending Review with Lead Agency?
Date Submitted/Explanation/Amount of pending estimate:
Financial Assurance Cost Estimate
Appealed by Operator? Date Submitted to State Mining and Geology Board or Lead Agency for Appeal/Explanation:
Other?
DISTRIBUTION: Lead Agency sends copies of Inspection notice & completed MRRC-1 to operator, operator’s designated agent, BLM or USFS (if required) & retains original.
INSTRUCTIONS FOR COMPLETING SURFACE MINING INSPECTION REPORT
Form MRRC-1 (4/97) Page 2 (Rev. 07/13)
BLOCK VII: Type of Financial Assurance Mechanism(s): Fill in the type of mechanism(s) that are on file. PRC § 3803 and SMGB Financial
Assurance Guideline number 10 describe Surety Bonds, Trust Funds, or Irrevocable Letters of Credit as acceptable financial assurance
mechanisms for non-governmental entity operators. For surface mining operations owned and operated by state and local government
entities, Surety Bonds, Trust Funds, Irrevocable Letters of Credit, Pledges of Revenue, and Budget Set Aside are acceptable financial
assurance mechanisms.
State the Financial Assurance Mechanism(s) document number(s). State the dollar amount of each Financial Assurance Mechanism(s)
currently on file. State the date of expiration of the Financial Assurance Mechanism(s) currently on file. State the date of approval for the
most recent lead agency approved Financial Assurance Mechanism(s) on file. State the total dollar amount of mechanisms held for
reclamation.
Indicate if any Financial Assurance Mechanisms are pending review by the lead agency and the date and amount of submittal to the lead
agency.
Indicate if there has been a change of operator of record since the last inspection and, if so, note the date the change occurred and
whether the new operator has signed any document acknowledging reclamation responsibility under the approved reclamation plan and
if the new operator has posted a Financial Assurance Mechanism. If a replacement Financial Assurance Mechanism has not been
posted, indicate the status of the new operator’s replacement Financial Assurance Mechanism. Per PRC § 2773.1(c) and Guideline
number 19 of the SMGB’s Financial Assurance Guidelines, when operatorship is transferred, “the original financial assurance must
remain in effect until the lead agency has approved, following department review, the replacement assurances provided by the
successor operator.”
The Financial Assurance amount must be adjusted and approved annually to account for new lands disturbed by surface mining
operations and lands to be disturbed in coming year, inflation, and reclamation of lands accomplished in accordance with the approved
Reclamation Plan (PRC § 2773.1(a)(3) and SMGB Financial Assurance Guideline #16). In order to determine what adjustments, if any,
are appropriate to the Financial Assurance Mechanism amount, each mine operator must submit annually a revision of the written
Financial Assurance Cost Estimate to the Lead Agency (PRC § 3804(c)). Provide the date of the operator’s most recent revision of the
Financial Assurance Cost Estimate to the Lead Agency and where appropriate, provide a status of the pending Financial Assurance Cost
Estimate. Provide the date and amount of the most recently approved Financial Assurance Cost Estimate.
Also indicate if the Financial Assurance Cost Estimate is under appeal to the lead agency or whether it has been appealed to State Mining
and Geology Board as described in PRC § 2770(e).
Use the Financial Assurance “Other” and “Explanation” blocks to provide any other pertinent information regarding the status of
Financial Assurance(s). If the operation does not have a sufficient Financial Assurance Cost Estimate and/or Financial Assurance
Mechanism, explain in detail.
State of California
DEPARTMENT OF CONSERVATION
OFFICE OF MINE RECLAMATION
MRRC-1 (4/97) Page 3 of 5 (Rev. 07/13)
SURFACE MINING INSPECTION REPORT
VIII. Non-SMARA facility operations conditions solely of local concern (e.g. hours of operation) do
not need to be noted here. See Instructions for Block VIII on reverse side of page.
[Use separate sheet(s) where necessary. Refer to item numbers below]
CA MINE ID #
91-
Potential Reclamation Plan
Requirements:
List Reclamation Plan Requirements
(Recommended to be filled out prior to field inspection)
Note Site Conditions and Compliance Issues
(Note additional comments on Page 5 as necessary)
VN?
1) General Information
a) Permitted Mineral Product(s)
b) Approved Production Amount
(Annual/Gross)
c) End Date of Operations Per RP
d) Permit end date
e) End Use
2) Boundaries
a) Property Boundary
b) Permit Boundary
c) Rec. Plan Boundary (RPB)
d) Setbacks
3) Slopes – Grading
a) Fill Slopes – Note Condition of:
i) Slopes – Working (max/current)
ii) Slopes – Reclaimed
iii) Compaction
b) Cut Slopes – Note Condition of:
i) Slopes – Working (max./current)
ii) Slopes – Reclaimed
4) Erosion Control
a) BMPs
b) Grading
c) Vegetation
5) Ponds
a) Design – Function
b) Capacity (area/depth/volume)
c) Maintenance
6) Stream & Wetland Protection
a) Buffers (distance to channel)
b) Berms (distance/length/height)
c) Best Management Practices
d) Drainage
e) Grading & Slopes
f) Stockpiles
g) Stream Diversions
7) Sensitive Wildlife & Plant Protection
a) List Species
b) Protection Measures
DISTRIBUTION: Lead Agency sends copies of Inspection notice & completed MRRC-1 to operator, operator’s designated agent, BLM or USFS (if required) & retains original.
INSTRUCTIONS FOR COMPLETING SURFACE MINING INSPECTION REPORT
Form MRRC-1 (4/97) Page 3 and 4 (Rev. 07/13)
BLOCK VIII: INSTRUCTIONS FOR EACH DATA COLUMN:
Potential Reclamation Plan Requirements (Column 1): Under CCR § 3504.5(f), “Inspections may include, but shall not
be limited to the following: the operation’s horizontal and vertical dimensions, volumes of materials stored on the site; slope
angles of stock piles, waste piles and quarry walls; potential geological hazards; equipment and other facilities; samples of
materials; photographic or other electronic images of the operation; any measurements or observations deemed necessary
by the inspector or the lead agency to ensure the operation is in compliance with Public Resources Code Chapter 9.”
Column 1 provides a list of items that may be included in the approved reclamation plan, either expressly or by reference as
described in PRC § 2772(d), which may include conditions of approval, other permit requirements and supplementary
documents, including environmental documents, prepared for the project pursuant to Division 13 (commencing with Section
21000).
It is not expected that all reclamation plans will include each item of Section VIII, or be limited to the items listed. Items in
Column 1 that are not operative requirements in the reclamation plan may not need to be addressed by the inspection.
Operative reclamation plan requirements not listed in Items 1 through 12 may be listed in Item 13, under “Other
Reclamation Plan Requirements.”
Reclamation Plan Requirements (Column 2): Prior to field inspection, it is recommended that the inspector review the
approved reclamation plan and any amendments, as well as any other documents included by reference, including
conditions of approval, other permit requirements and supplementary documents, such as environmental documents
prepared for the project pursuant to Division 13 (commencing with Section 21000) that specifically relate to reclamation of
the mine site. The most recently approved Financial Assurance Cost Estimate and any pending or ongoing enforcement
actions should also be reviewed. Conditions of approval that relate to facility operations solely of local concern, such as
hours of operation, noise, and dust control are not subject to the inspection.
Column 2 is intended to provide the inspector a place to match any items noted in Column 1 with those items included in the
approved reclamation plan either expressly or by reference as described in PRC § 2772(d), which may include conditions of
approval, other permit requirements and supplementary documents, including environmental documents prepared for the
project pursuant to Division 13 (commencing with § 21000). Also note any Interim Management Plan (IMP) requirements
where the mine is subject to an IMP pursuant to PRC § 2770(h).
Indicate the source document for the reclamation plan requirements at the end of the entry in parenthesis; i.e. (COA) (POO)
(EIR) (WDR) (SWPPP), etc. Conditions of approval that relate to facility operations solely of local concern, such as hours
of operation, noise, and dust control should not be included in Column 2. If items listed in Column 1 of Section VIII of the
form are not included in the reclamation plan or other documents included by reference, write not applicable or “NA” in
Column 2.
Specific reclamation requirements may not apply to an operation at the time of inspection, but they are important to be
aware of to ensure current activity at the site will not prohibit reclamation in accordance with the approved reclamation plan.
A copy of the Surface Mining and Reclamation Act of 1975 and 1993 SMGB regulations may be obtained at
http://www.conservation.ca.gov/omr/lawsandregulations/Pages/SMARA.aspx.
Site Conditions and Compliance Issues (Column 3): Describe current site conditions and compliance issues noted for
both operating and reclaimed surfaces that pertain to the reclaimed condition of the mining site. Block IX is provided for
additional space to describe site conditions and/or compliance issues. Attach additional sheets as necessary.
Evaluations of slope stability and engineered compaction should be prepared by qualified professionals only. PRC §
2774(b)) states “The lead agency may cause an inspection to be conducted by a state licensed geologist, state licensed
civil engineer, state licensed landscape architect, or state licensed forester, who is experienced in land reclamation and
who has not been employed by a surface mining operation within the jurisdiction of the lead agency in any capacity during
the previous 12 months.”
VN? (Column 4): Use this box to indicate if violations were noted for any of the specific items under the corresponding item
group heading (e.g., Boundaries, Slopes-Grading, etc.) during field inspection of the site. Enter number of violations in the
box.
State of California
DEPARTMENT OF CONSERVATION
OFFICE OF MINE RECLAMATION
MRRC-1 (4/97) Page 4 of 5 (Rev. 07/13)
SURFACE MINING INSPECTION REPORT
VIII. Non-SMARA facility operations conditions solely of local concern (e.g. hours of operation) do not need to be noted here. See Instructions for Block VIII on reverse side of page.
[Use separate sheet(s) where necessary. Refer to item numbers below]
CA MINE ID #
91-
Potential Reclamation Plan
Requirements:
List Reclamation Plan Requirements
(Recommended to be filled out prior to field inspection)
Note Site Conditions and Compliance Issues
(Note additional comments on Page 5 as necessary)
VN?
8) Soil/Overburden Stockpile
Management
a) Topsoil
i) Location
ii) Slope Stability
iii) BMPs
b) Overburden
i) Location
ii) Slope Stability
iii) BMPs
c) Topsoil Application
i) Amendments
ii) Depth
iii) Moisture
iv) Application Methods
9) Revegetation
a) Test Plots
b) Species Mix
c) Density
d) Percent Cover
e) Species Richness
f) Protection
g) Success Monitoring
h) Invasive Species Control
10) Structures
11) Equipment
12) Closure of Adits
13) Other Reclamation Plan
Requirements
DISTRIBUTION: Lead Agency sends copies of Inspection notice & completed MRRC-1 to operator, operator’s designated agent, BLM or USFS (if required) & retains original.
INSTRUCTIONS FOR COMPLETING SURFACE MINING INSPECTION REPORT
Form MRRC-1 (4/97) Page 5 (Rev. 05/13)
BLOCK IX Inspectors may use the large open block for comments to describe violations, corresponding corrective actions, or
preventative measure(s) suggested by the inspector to address noted violations or avoid potential violations, and to explain
any limitations on the inspection conducted. The inspector can also use this space to describe the status of any pending or
current enforcement actions. Separate violations that are the subject of existing enforcement actions from violations
observed during the current inspection.
Enter California Mine ID Number and Date of Inspection.
Weather Codes: CR = Clear; CL = Cloudy; RN = Rain; SN = Snow; WD = Windy
For "Duration of Inspection," indicate the start and end times of the inspection (do not include travel time).
SMARA Status Codes (based on annual report and reported production under CCR § 3695, indicate the appropriate status
code)
I = Idle (Per § 2727.1) NP = Newly Permitted (must be no mining/disturbance)
AB = Abandoned (Per § 2770(h)(6)) NOP-NC = Not in operation, reclamation not completed
NOP-C = Not in operation, reclamation completed
If idle, indicate either the date operation became idle as defined by PRC Section 2727.1, the date an IMP was approved, or the
status of any pending IMP.
Status of Reclamation Codes:
RN = Reclamation not begun P = Post reclamation monitoring
R = Reclamation in progress RC = Reclamation complete
Enter approximate acreage under reclamation (the number of acres actively being reclaimed in accordance with the
approved reclamation plan).
Enter approximate acreage determined to be reclaimed in accordance with the approved reclamation plan by Lead Agency.
Enter approximate total disturbed acreage. This includes all acreage disturbed by the surface mining operation, as defined
by PRC § 2729: “’Mined Lands’ includes the surface, subsurface, and ground water of an area in which surface mining
operations will be, are being, or have been conducted, including private ways and roads appurtenant to any such area, land
excavations, workings, mining waste, and areas in which structures, facilities, equipment, machines, tools or other materials or
property which result from, or are used in, surface mining operations are located.” This should include acreage under
reclamation that has not been determined to be reclaimed in accordance with the approved reclamation plan by the Lead
Agency.
Enter the total number of acres within or adjacent to the disturbance area of the operation disturbed pre-SMARA (disturbance
before January 1, 1976, that has not had mining related disturbance after January 1, 1976).
Enter the disturbed acreage identified in the most recent Financial Assurance Cost Estimate (i.e., the disturbed acreage that
was used to calculate the most recent Financial Assurance Cost Estimate.
Enter the date of the previous lead agency inspection and number of violations noted during that inspection.
Attendees: Provide the names and affiliations of parties in attendance at the inspection.
BLOCK X: Enter the number of violations noted during the inspection. Sign and date the Inspection Report. If the inspector is a
consultant to the lead agency, include the inspector’s certification (PE, PG, CEG, etc.) and license number, if applicable.
The lead agency may cause an inspection to be performed by contracting with private consultants, specifically: state
licensed geologist, state licensed civil engineer, state licensed landscape architect, or state licensed forester per § 2774(b).
No
v
e
m
b
e
r
4
,
2
0
1
4
N
e
w
C
a
r
r
M
i
n
e
In
s
p
e
c
t
i
o
n
(
C
A
I
D
9
1
-
0
4
-
0
0
3
8
)
Ph
o
t
o
1
–
C
a
t
c
h
B
a
s
i
n
1
b
a
n
d
e
x
i
s
t
i
n
g
s
t
e
e
p
sl
o
p
e
f
r
o
m
h
i
s
t
o
r
i
c
m
i
n
e
a
c
t
i
v
i
t
i
e
s
.
P
h
o
t
o
2
–
G
r
a
d
i
n
g
w
o
r
k
w
i
t
h
i
n
P
h
a
s
e
2
o
f
A
c
t
i
ve
M
i
n
e
A
r
e
a
.
Ph
o
t
o
s
3
&
4
–
2
0
1
4
i
m
p
r
o
v
e
m
e
n
t
s
t
o
o
v
e
r
f
l
o
w
w
e
i
r
f
r
o
m
C
a
t
c
h
B
a
s
i
n
1
b
.
No
v
e
m
b
e
r
4
,
2
0
1
4
N
e
w
C
a
r
r
M
i
n
e
In
s
p
e
c
t
i
o
n
(
C
A
I
D
9
1
-
0
4
-
0
0
3
8
)
Ph
o
t
o
5
–
M
e
t
a
l
s
t
o
r
a
g
e
c
o
n
t
a
i
n
e
r
P
h
o
t
o
6
–
O
v
e
r
b
u
r
d
e
n
f
r
o
m
A
c
t
i
v
e
m
i
n
e
a
r
e
a
u
s
e
d
f
o
r
f
i
l
l
h
i
s
t
o
r
i
c
m
i
n
e
d
i
s
t
u
r
b
a
n
c
e
re
h
a
b
i
l
i
t
a
t
i
o
n
(
P
h
a
s
e
2
)
.
Ph
o
t
o
7
–
V
i
e
w
e
a
s
t
a
c
r
o
s
s
Z
o
n
e
s
1
&
9
o
f
t
h
e
A
c
t
i
v
e
M
i
n
e
A
r
e
a
.
Re
h
a
b
i
l
i
t
a
t
i
o
n
w
o
r
k
f
o
r
P
h
a
s
e
4
o
f
H
i
s
t
o
r
i
c
M
i
n
e
D
i
s
t
u
r
b
a
n
c
e
p
er
f
o
r
m
e
d
i
n
2
0
1
3
.
P
h
o
t
o
8
–
C
o
r
n
e
r
m
a
r
k
e
r
in
s
t
a
l
l
e
d
f
o
r
Z
o
n
e
1
o
f
A
c
t
i
v
e
M
i
n
e
A
r
e
a
.